RERA projects in Jawhar (M Cl)

14 projects under 14 MahaRERA registrations, registered 2017–2024. 7% have a completion date extended beyond the one promised.

Locality
14RERA projects
14Registrations
2Completion still due12 past their completion date
18 monthsMedian extension beyond promised date7% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20181
20191
20202
20212
20221
20233
20241

Projects in Jawhar (M Cl)

14 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Mannat RegencyHimanshu Shyam TendulkarP9900007789813 Nov 202430 Apr 2029—Not yet due0
The EmpireShahji InfraP990000519017 Jul 202331 Mar 2026—Promised date passed0
Reality HeightsReality Builders and DevelopersP990000503255 Apr 202331 Dec 2027—Not yet due0
Spandan Landmark ResidencyImran Haji Yusuf JummaniP9900004870713 Jan 202331 Dec 2024—Promised date passed0
Gulmohar AvenueHimanshu Shyam TendulkarP9900003473420 Apr 202230 Apr 2025—Promised date passed0
Shree Ganesh HeritageHimanshu Shyam TendulkarP9900003228122 Dec 202131 Oct 2024—Promised date passed0
Sara Govind ApartmentSara Developers And CoP9900002920810 May 202131 Dec 2023—Promised date passed0
Yashodhan ResidencyKadar Gaffar KargathraP9900002770731 Dec 202030 Dec 2022—Promised date passed0
Yeshwanta HeightsNivrutti Yashwant ShindeP9900002613421 Aug 202030 Jun 2022—Promised date passed0
Varad Vinayak ResidencyHimanshu Shyam TendulkarP9900001923214 Jan 201930 Dec 2023—Promised date passed0
Ahmad ResidencyKadar Gaffar KargathraP9900001824116 Oct 201830 Jun 2022—Promised date passed0
Royal ResidencyHimanshu Shyam TendulkarP990000145298 Dec 201731 Aug 202028 Feb 2022Extended 18 mo0
Shiv ParadiseHimanshu Shyam TendulkarP9900001160231 Aug 20171 Dec 2018—Promised date passed0
Renuka ResidencyHimanshu Shyam TendulkarP9900000924122 Aug 20171 Dec 2019—Promised date passed0

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Himanshu Shyam Tendulkar7 projects
  2. Kadar Gaffar Kargathra2 projects
  3. Imran Haji Yusuf Jummani1 project
  4. Nivrutti Yashwant Shinde1 project
  5. Reality Builders and Developers1 project
  6. Sara Developers And Co1 project
  7. Shahji Infra1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology