Varap, Thane
Deedo IDDL-THN-VARAP8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects18
Registrations18
Completion still due108 past their date
Median extension4 months50% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
18 MahaRERA registrations in Varap
1 completed2 not yet due8 extended, not yet due7 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Varap
18 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Mohan Parkland Phase IAMohan Built-Spaces LLP | Due Dec 2032 | — | — |
| Vishwajeet Precious Phase VAbhijeet Pride | Due Aug 2030, extended 4 mo | — | — |
| Precious OrchidPrecious Keystone LLP | Due Sep 2029, extended 4 mo | — | — |
| Precious Greenwoods Phase IPrecious Group LLP | Due Sep 2029, extended 4 mo | — | — |
| Krishna Empire Phase 4Chirag Enterprises | Due Apr 2029, extended 4 mo | — | — |
| Krishna Empire 3Jai Mata Di Construction | Due Apr 2027, extended 4 mo | — | — |
| Vishwajeet Precious Phase IVAbhijeet Construction | Due Jul 2028, extended 4 mo | — | — |
| Vedaant MeadowsVedaant Builders | Due Dec 2027 | — | 30% |
| Vasudev Laxmi ParkMahesh Manohar Salphale | Due May 2027, extended 4 mo | — | — |
| Vishwajeet Precious Phase IIIAbhijeet Pride | Completed | — | 79% |
| Vishwajeet Precious Phase IIAbhijeet Pride | Completed | — | 61% |
| Mohan DeepSunil Purushottam Deshmukh | Due Sep 2027 | — | 10% |
| Sadguru Krupa II PhaseChirag Enterprises | 1 mo late | — | 53% |
| Krishna EmpireShree Sai Balaji Associates | Due Dec 2026, extended 3 yrs | — | 56% |
| Vishwajeet Precious Phase IAbhijeet Pride | Completed | — | 80% |
| KONARK MEADOWS Phase-1Atlanta Landmark | Completed | — | 91% |
| Sai SpringMohan Kedarnath Krishnavanshi | Completed | — | — |
| Krishna HeritageShree Balaji Construction | Completed, extended 2 yrs | — | 99% |
Nearby: other villages in Kalyan
Most active promoters
- Abhijeet Pride4 projects
- Chirag Enterprises2 projects
- Abhijeet Construction1 project
- Atlanta Landmark1 project
- Jai Mata Di Construction1 project
- Mahesh Manohar Salphale1 project
- Mohan Built-Spaces LLP1 project
- Mohan Kedarnath Krishnavanshi1 project
- Precious Group LLP1 project
- Precious Keystone LLP1 project
Varap, in questions
How many projects in Varap run late?
8 in 10 MahaRERA registrations (15 of 18): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Varap by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology