MahaRERA shows it completed
- This projectRegistered 26 Apr 2019, completion promised 2 Mar 2025.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Building No 39 floors · 56 units66% booked
- Building No 49 floors · 56 units95% booked
- Building (P51700020587)Size not on record75% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700020587
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700020587 | 26 Apr 2019 | 2 Mar 2025 | 2 Mar 2025 | Abhijeet Pride | Project page |
Documents108
2 documents held by Deedo, 106 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Legal
Show all 108 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)PLOT-1.pdf · uploaded 12 Apr 2019Source
- 2 Copy of Layout Approval (in case of layout)PLOT-2.pdf · uploaded 12 Apr 2019Source
- 3 Copy of Layout Approval (in case of layout)PLOT-3.pdf · uploaded 12 Apr 2019Source
- 4 Copy of Layout Approval (in case of layout)PLOT-4.pdf · uploaded 12 Apr 2019Source
- 5 Copy of Layout Approval (in case of layout)PLOT-5.pdf · uploaded 12 Apr 2019Source
- 1 Building Plan Approval (IOD)compresspdf_STP7w9ER.pdf · uploaded 12 Apr 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentcompresspdf_STP7w9ER.pdf · uploaded 12 Apr 2019Source
- 1 Declaration in FORM BFORM B-ABHIJEET PRIDE (1).pdf · uploaded 12 Apr 2019Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)combinepdf (1).pdf · uploaded 18 Apr 2019Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2.pdf · uploaded 18 Apr 2019Source
- 1 Certificates of CA (Form 3)FORM-3.pdf · uploaded 18 Apr 2019Source
- 1 Proforma of Allotment letterFINAL DRAFT AGREEMENT.pdf · uploaded 20 Apr 2019Source
- 2 Proforma of Allotment letterRera Draft Agreement Revised.pdf · uploaded 30 Dec 2019Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP Form I June_compressed.pdf · uploaded 22 Feb 2020Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP Form I Sep_compressed.pdf · uploaded 22 Feb 2020Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP Form II June_compressed.pdf · uploaded 22 Feb 2020Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP Form II Sep_compressed.pdf · uploaded 22 Feb 2020Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM2A June.pdf · uploaded 22 Feb 2020Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM2A Sep.pdf · uploaded 22 Feb 2020Source
- 2 Certificates of CA (Form 3)FORM 3 June 19.pdf · uploaded 22 Feb 2020Source
- 3 Certificates of CA (Form 3)FORM 3 Sep 19.pdf · uploaded 22 Feb 2020Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM 1-30-06-2020.pdf · uploaded 12 Nov 2020Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM 1-31-03-2020.pdf · uploaded 12 Nov 2020Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM 1-30-09-2020.pdf · uploaded 12 Nov 2020Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM 1-31-12-2019_compressed.pdf · uploaded 12 Nov 2020Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM 1-30-06-2019_compressed.pdf · uploaded 12 Nov 2020Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP-FORM 2-30-06-2020.pdf · uploaded 12 Nov 2020Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP-FORM 2-30-09-2020.pdf · uploaded 12 Nov 2020Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP-FORM 2-31-03-2020.pdf · uploaded 12 Nov 2020Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP FORM 2-31-12-2019_compressed (1).pdf · uploaded 12 Nov 2020Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)AP-FORM 2A-31-12-2019.pdf · uploaded 12 Nov 2020Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)AP-FORM 2A-31-03-2020.pdf · uploaded 12 Nov 2020Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)AP-FORM 2A-30-06-2020.pdf · uploaded 12 Nov 2020Source
- 6 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)AP-FORM 2A-30-09-2020.pdf · uploaded 12 Nov 2020Source
- 4 Certificates of CA (Form 3)AP-FORM 3-31-12-2019.pdf · uploaded 12 Nov 2020Source
- 5 Certificates of CA (Form 3)AP-FORM 3-31-03-2020.pdf · uploaded 12 Nov 2020Source
- 6 Certificates of CA (Form 3)AB-FORM 3-30-06-2020_compressed.pdf · uploaded 12 Nov 2020Source
- 7 Certificates of CA (Form 3)AB-FORM 3-30-09-2020_compressed.pdf · uploaded 12 Nov 2020Source
- 8 Certificates of CA (Form 3)AB-FORM 3-30-09-2020_compressed.pdf · uploaded 12 Nov 2020Source
- 7 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)AP 31ST DEC 2020.pdf · uploaded 26 Mar 2021Source
- 9 Certificates of CA (Form 3)AP 31 DEC 2020.pdf · uploaded 26 Mar 2021Source
- 10 Certificates of CA (Form 3)AP 31 DEC 2020.pdf · uploaded 26 Mar 2021Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 DEC 2020.pdf · uploaded 5 Apr 2021Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 DEC 2020.pdf · uploaded 5 Apr 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)AP.pdf · uploaded 14 May 2021Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM-1-31-03-2021.pdf · uploaded 12 Jun 2021Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM-1-31-03-2021.pdf · uploaded 12 Jun 2021Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP-FORM-2-31-03-2021.pdf · uploaded 12 Jun 2021Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP-FORM-2-31-03-2021.pdf · uploaded 12 Jun 2021Source
- 8 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)AP-FORM 2A-31-03-2021.pdf · uploaded 12 Jun 2021Source
- 9 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)AP-FORM 2A-31-03-2021.pdf · uploaded 12 Jun 2021Source
- 11 Certificates of CA (Form 3)AP-FORM 3 -31-03-2021.pdf · uploaded 12 Jun 2021Source
- 12 Certificates of CA (Form 3)AP-FORM 3 -31-03-2021.pdf · uploaded 12 Jun 2021Source
- 13 Certificates of CA (Form 3)ABHIJEET PRIDE FORM 3 31-03-2021.pdf · uploaded 12 Aug 2021Source
- 14 Certificates of CA (Form 3)ABHIJEET PRIDE FORM 3 31-03-2021.pdf · uploaded 12 Aug 2021Source
- 1 Declaration about Commencement CertificateAP-PHASE I-FORM D.pdf · uploaded 13 Aug 2021Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM-1-30-06-2021.pdf · uploaded 14 Aug 2021Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP-FORM-2-30-06-2021-compressed.pdf · uploaded 14 Aug 2021Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM-1-30-06-2021.pdf · uploaded 20 Aug 2021Source
- 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP-FORM-2-30-06-2021.pdf · uploaded 20 Aug 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)AP-FORM-2A-30-06-2021.pdf · uploaded 20 Aug 2021Source
- 15 Certificates of CA (Form 3)FORM 3 31032021.pdf · uploaded 31 Aug 2021Source
- 16 Certificates of CA (Form 3)form 3 30062021.pdf · uploaded 31 Aug 2021Source
- 1 Disclosure of sold/ booked inventoryAP-UNSOLD LIST-31-03-2021.pdf · uploaded 1 Sep 2021Source
- 17 Certificates of CA (Form 3)FORM-3 30062021.pdf · uploaded 16 Sep 2021Source
- 18 Certificates of CA (Form 3)abhijeet pride form3-c.pdf · uploaded 18 Nov 2021Source
- 10 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)AP-FORM 2A-30-09-2021.pdf · uploaded 12 Dec 2021Source
- 19 Certificates of CA (Form 3)AP-FORM 3 -30-09-2021.pdf · uploaded 12 Dec 2021Source
- 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM-1-30-09-2021.pdf · uploaded 25 Dec 2021Source
- 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP-FORM-2-30-09-2021.pdf · uploaded 25 Dec 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form 5.pdf · uploaded 30 Dec 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)AP-I-FORM-2A-31-12-2021.pdf · uploaded 11 Mar 2022Source
- 2 Disclosure of sold/ booked inventoryUnsold-AP-I-31-12-2021.pdf · uploaded 12 Mar 2022Source
- 3 Disclosure of sold/ booked inventoryUnsold-AP-I-31-12-2021_compressed.pdf · uploaded 12 Mar 2022Source
- 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM-1-31-12-2021.pdf · uploaded 29 Mar 2022Source
- 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AP-FORM-2-31-12-2021.pdf · uploaded 29 Mar 2022Source
- 20 Certificates of CA (Form 3)AP-I-FORM-3-31-12-21.pdf · uploaded 27 Apr 2022Source
- 4 Disclosure of sold/ booked inventoryAP-PHASE I -31-03-22_compressed.pdf · uploaded 4 May 2022Source
- 21 Certificates of CA (Form 3)Form 3 1_compressed.pdf · uploaded 4 May 2022Source
- 16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1-AP-I-31-03-22.pdf · uploaded 23 May 2022Source
- 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2-AP-I-31-03-22.pdf · uploaded 23 May 2022Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM-2A-AP-I-31-03-22.pdf · uploaded 28 May 2022Source
- 5 Disclosure of sold/ booked inventoryVPRECIOUS I.pdf · uploaded 14 Nov 2022View
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC-AP-I.pdf · uploaded 19 Nov 2022Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM-4-AP-I.pdf · uploaded 19 Nov 2022Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM-2A-AP-I -30-06-22.pdf · uploaded 24 Nov 2022Source
- 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2-AP-1-10-06-22.pdf · uploaded 29 Nov 2022Source
- 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM-2-AP-1-10-06-22.pdf · uploaded 29 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM-5-AP-PH-I-21-22.pdf · uploaded 29 Nov 2022Source
- 17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AP-FORM 1-10-06-2022.pdf · uploaded 7 Dec 2022Source
- 22 Certificates of CA (Form 3)AP-I-FORM -3-30-06-22.pdf · uploaded 14 Dec 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5-AP-I.pdf · uploaded 30 Oct 2023Source
Technical
- Documentcompresspdf_STP7w9ER.pdf · uploaded 12 Apr 2019Source
- DocumentPLOT-1.pdf · uploaded 12 Apr 2019Source
- DocumentPLOT-2.pdf · uploaded 12 Apr 2019Source
- DocumentPLOT-3.pdf · uploaded 12 Apr 2019Source
- DocumentPLOT-4.pdf · uploaded 12 Apr 2019Source
- DocumentPLOT-5.pdf · uploaded 12 Apr 2019Source
Technical (Architect)
- DocumentAP-FORM 1-10-06-2022.pdf · uploaded 7 Dec 2022Source
Technical (Engineer)
- DocumentFORM-2-AP-1-10-06-22.pdf · uploaded 29 Nov 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK112 units in all
- Address
- Survey No 32, Suryve No 33/1(P), Survey No 30, Hissa No 12 A, B(P), C & D, Survey No 54/3 And Survey No 70/1 (P), Varap, VarapPIN 421301
- Village
- Varap, Kalyan taluka
- Land area for this project
- 2,453 sq m (26,404 sq ft)
- Permissible built-up area
- 4,620 sq m (49,732 sq ft)
- Sanctioned built-up area
- 4,620 sq m (49,732 sq ft)
- Recreational open space
- 238 sq m (2,562 sq ft)
- Designated bank account
- 87
- Developed in phases
- Yes
Land as published on MahaRERA's project page
SURVEY NO 32, SURYVE NO 33/1(P), SURVEY NO 30, HISSA NO 12 A,B(P), C & D, SURVEY NO 54/3 AND SURVEY NO 70/1 (P)
Boundaries
- North
- Survey No 31
- South
- Survey No 6 And 65
- East
- Survey No 30 And Dp Road
- West
- Survey No 54 And Survey No 34
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking112 units
90 of 112 units booked (80%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 3 | 1BHK | 34.45 sq m · 371 sq ft | 28 | 19 |
| Building No 3 | 1BHK | 35.45 sq m · 382 sq ft | 28 | 18 |
| Building No 4 | 1BHK | 33.6 sq m · 362 sq ft | 28 | 26 |
| Building No 4 | 2BHK | 51 sq m · 549 sq ft | 28 | 27 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mahendra Sharma | — |
| Engineer | Jai Talreja | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Varap
- Mohan Parkland Phase IARERA PR1331012601971
- Vishwajeet Precious Phase VRERA PR1333032600324
- Precious OrchidRERA P51700080873
- Precious Greenwoods Phase IRERA P51700080748
- Krishna Empire Phase 4RERA P51700078148
- Krishna Empire 3RERA P51700055823
- Vishwajeet Precious Phase IVRERA P51700051424
- Vedaant MeadowsRERA P51700049153
All 18 projects in Varap · Compare Vishwajeet Precious Phase I with another project