Skip to content
Deedo home
Menu

RERA projects in Varap

17 projects under 17 MahaRERA registrations, registered 2017–2026. 12% have a completion date extended beyond the one promised.

17RERA projects
17Registrations
10Completion still due7 past their completion date
30 monthsMedian extension beyond promised date12% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20180
20191
20202
20212
20221
20232
20242
20252
20262

Projects in Varap

17 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Mohan Parkland Phase IAMohan Built-Spaces LLPPR133101260197121 Sep 202631 Dec 2032—Not yet due0
Vishwajeet Precious Phase VAbhijeet PridePR13330326003244 May 202625 Apr 2030—Not yet due0
Precious OrchidPrecious Keystone LLPP5170008087328 Jul 202531 May 2029—Not yet due0
Precious Greenwoods Phase IPrecious Group LLPP517000807483 Jul 202531 May 2029—Not yet due0
Krishna Empire Phase 4Chirag EnterprisesP5170007814825 Nov 202431 Dec 2028—Not yet due0
Krishna Empire 3Jai Mata Di ConstructionP5170005582322 Apr 202431 Dec 2026—Not yet due0
Vishwajeet Precious Phase IVAbhijeet ConstructionP5170005142414 Jun 202330 Mar 2028—Not yet due0
Vedaant MeadowsVedaant BuildersP517000491531 Feb 202331 Dec 2027—Not yet due0
Vasudev Laxmi ParkMahesh Manohar SalphaleP5170004582115 Jun 20221 Jan 2027—Not yet due0
Vishwajeet Precious Phase IIIAbhijeet PrideP5170003131815 Oct 20212 Mar 2024—Promised date passed0
Vishwajeet Precious Phase IIAbhijeet PrideP5170003079313 Sep 202116 May 2026—Promised date passed0
Mohan DeepSunil Purushottam DeshmukhP517000265614 Oct 202030 Sep 2026—Promised date passed0
Sadguru Krupa II PhaseChirag EnterprisesP5170002394414 Jan 20201 Oct 2026—Promised date passed0
Krishna EmpireShree Sai Balaji AssociatesP5170002115310 Jun 201930 Dec 202331 Dec 2026Extended 36 mo0
KONARK MEADOWS Phase-1Atlanta LandmarkP5170000931322 Aug 201730 Dec 2022—Promised date passed0
Sai SpringMohan Kedarnath KrishnavanshiP5170000981322 Aug 201730 Jun 2023—Promised date passed0
Krishna HeritageShree Balaji ConstructionP5170000711817 Aug 201731 Dec 202030 Dec 2022Extended 24 mo0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Abhijeet Pride3 projects
  2. Chirag Enterprises2 projects
  3. Abhijeet Construction1 project
  4. Atlanta Landmark1 project
  5. Jai Mata Di Construction1 project
  6. Mahesh Manohar Salphale1 project
  7. Mohan Built-Spaces LLP1 project
  8. Mohan Kedarnath Krishnavanshi1 project
  9. Precious Group LLP1 project
  10. Precious Keystone LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology