Skip to content
Residential / Group Housing · 2 buildings · 88 unitsRERA P51700009813

Sai Spring

Deedo IDDP-THN-NQ7K

MahaRERA shows it completed; no MahaRERA orders on record.

Varap, Thane 421301 · Promoter: Mohan Kedarnath Krishnavanshi

DeliveryCompletedAs MahaRERA showsRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read
Sai Spring project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

MahaRERA shows it completed

  • This projectRegistered 22 Aug 2017, completion promised 30 Jun 2023.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700009813
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000981322 Aug 201730 Jun 2023—Mohan Kedarnath KrishnavanshiProject page
Documents61

29 documents held by Deedo, 32 filings listed on MahaRERA's project page

Title report (2)

Encumbrance details

Commencement certificate

Form B

Form 1 (5)

Show all 61 documentsShow fewer documents

Form 1 (5)

Form 2 (3)

Allotment letter (2)

Form 5 (5)

Registration certificate

Occupancy / completion certificate

  • Occupancy / completion certificate27 Aug 2022ViewSource

Form 4

Other (4)

Layout plan

Building plan

Document library

  • Copy of the legal title reportTITLE REPORT - LAXMAN.pdf · uploaded 30 Jul 2017View
  • Details of encumbrancesKedar Developers Encumbranches.pdf · uploaded 30 Jul 2017View
  • Copy of Layout Approval (in case of layout)KEDAR PLAN 1-LAYOUT.pdf · uploaded 30 Jul 2017View
  • Proforma of Allotment letterFormat Flat Sale Varap-PERFOMA.pdf · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)KEDAR PLAN 2-BUILDING PLAN.pdf · uploaded 30 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)kedar developer AC.PDF · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)kedar developer EC.PDF · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCc.pdf · uploaded 31 Jul 2017View
  • Copy of the legal title reportTITLE REPORT-DILIP KAMLAKAR.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterAllotment Sai Spring-PERFOMA.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BKEDAR DEVELOPER FORM B.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARC CERT UPLOAD.pdf · uploaded 8 Nov 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sai Spring Architect Certificate.pdf · uploaded 12 May 2018View
  • Certificates of CA (Form 5)FORM 5.pdf · uploaded 15 Oct 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)kD Architect certificate-min.pdf · uploaded 3 Apr 2019View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)kd engineer certificate-min.pdf · uploaded 3 Apr 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)sai spring.pdf · uploaded 31 Dec 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)kedar developers.pdf · uploaded 30 Sep 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)kedar Developer-compressed.pdf · uploaded 8 Apr 2022View
  • Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 27 Aug 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentORIGINAL OC (1).pdf · uploaded 27 Aug 2022View
  • Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 27 Aug 2022View
  • Status of Formation of Legal Entity (Society/Co Op etc.)society registration certificate (1).pdf · uploaded 21 Oct 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)kedar dev form 5.pdf · uploaded 15 Feb 2023View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)KEDAR DEVELOPERS FORM 1.pdf · uploaded 14 Mar 2023View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)KEDAR DEVELOPERS FORM 2.pdf · uploaded 14 Mar 2023View

Promoter documents

  • Legal Title reportTITLE REPORT - LAXMAN.pdf · uploaded 30 Jul 2017View
  • Legal Title reportTITLE REPORT-DILIP KAMLAKAR.pdf · uploaded 31 Jul 2017View
  • Declaration Form BKEDAR DEVELOPER FORM B.pdf · uploaded 31 Jul 2017View

Technical documents

  • Building Plan ApprovalKEDAR PLAN 2-BUILDING PLAN.pdfView
  • Layout ApprovalKEDAR PLAN 1-LAYOUT.pdfView

Proforma allotment letter

  • Proforma allotment letterFormat Flat Sale Varap-PERFOMA.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSURVEY NO 43 HISSA NO 3 PART

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Unit types
1 BHK FLAT, 2BHK FLAT, 1BHK, 2 BHK FLAT88 units in all
Address
Survey No 43 Hissa No 3 Part, Kalyan, KalyanPIN 421301
Village
Varap, Kalyan taluka
Land area for this project
6,000 sq m (64,583 sq ft)
Permissible built-up area
3,311 sq m (35,640 sq ft)
Sanctioned built-up area
3,311 sq m (35,640 sq ft)
Recreational open space
785 sq m (8,450 sq ft)
Designated bank account
Bank Of Baroda
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

SURVEY NO 43 HISSA NO 3 PART

Land as published on MahaRERA's project page

SURVEY NO 43 HISSA NO 3 PART

Boundaries

North
18m Dp Road
South
S No 42
East
S No 43-3 Part
West
Existing Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking88 units · 34 parking spaces

88 units registered

1 BHK FLAT · 37 units2BHK FLAT · 7 units1BHK · 37 units2 BHK FLAT · 7 units
BuildingTypeCarpet areaUnits
A Wing1 BHK FLAT32.68 sq m · 352 sq ft37
A Wing2BHK FLAT47.72 sq m · 514 sq ft7
B Wing1BHK32.68 sq m · 352 sq ft37
B Wing2 BHK FLAT47.72 sq m · 514 sq ft7

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
A WingClosed/Covered000012
A WingOpen Space00005
B WingClosed/Covered000012
B WingOpen Space00005

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress3 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

A Wing

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

B Wing

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Common areas and amenities

  • Internal Roads & FootpathsWORK COMPLETED100%
  • Water SupplyWORK COMPLETED100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)WORK COMPLETED100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingWORK IN PROGRESS70%
  • Street LightingWORK IN PROGRESS80%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingWORK COMPLETED100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsWORK IN PROGRESS90%
  • Electrical meter room, sub-station, receiving stationWORK COMPLETED100%
  • Aggregate area of recreational Open SpaceWORK IN PROGRESS70%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGurunathan Jayavel Mudaliyar—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology