Deedo IDDL-THN-SHAHAD10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects8
Registrations10some projects hold several
Completion still due46 past their date
Median extension4 months70% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
10 MahaRERA registrations in Shahad
4 extended, not yet due6 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Shahad
8 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sunteck Crescent ParkSunteck Property Holdings Private Limited | Due Apr 2032, extended 4 mo | — | 5% |
| Gurudev OrchidGurudev Developers | Due Jan 2027, extended 4 mo | — | 4% |
| Mangalmurti HeightsRamesh Nanalal Jain | Due Jul 2027, extended 4 mo | — | 39% |
| Yashvi ResidencyPatel & Co. | 3 yrs 11 mo late | — | — |
| Birla VanyaCentury Textiles & Industries Ltd | Completed | — | — |
| Palm PrismP J Construction | 6 yrs 4 mo late | — | 67% |
| Royal Meadows C 1 , C 2Siddhivinayak Developers | 11 mo late | — | 47% |
| Millenium HeightsK P Developers | 2 yrs 11 mo late | — | 73% |
Nearby: other villages in Kalyan
Most active promoters
- Century Textiles & Industries Ltd1 project
- Gurudev Developers1 project
- K P Developers1 project
- Patel & Co1 project
- P J Construction1 project
- Ramesh Nanalal Jain1 project
- Siddhivinayak Developers1 project
- Sunteck Property Holdings Private Limited1 project
Shahad, in questions
How many projects in Shahad run late?
10 in 10 MahaRERA registrations (10 of 10): their completion date was extended or has passed, data through 30 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Shahad by Deedo. Medians on fewer than 3 deeds are not shown.
Data through30 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology