Skip to content

Delayed projects in Raigarh

1,042 MahaRERA projects in Raigarh are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 14 of 21.

ProjectLocalityPromisedRevisedDelivery
Aarish HeightsDilshad Mushtaq PatelPanvelMar 2024Mar 20242 yrs 8 mo late
Bayt AaishaHd Builders & DevelopersTaloje PanchnadMar 2024Jul 20252 yrs 8 mo late
Bhagirathi ApartmentShree Builders And DevelopersBhuwaneshwar (Ct)Mar 2024Mar 20242 yrs 8 mo late
Durva ParkSaishwar Bajrang PatilVadghar (Ct)Mar 2024Mar 20242 yrs 8 mo late
Galaxy TwoAbdul Wahid Wamique ShaikhPanvelMar 2024Mar 20242 yrs 8 mo late
Hmd ApartmentHmd DevelopersTaloje PanchnadMar 2024Mar 20262 yrs 8 mo late
Mahindra Meridian PlotsMahindra Lifespace Developers limitedNagaonMar 2024Mar 20252 yrs 8 mo late
Patil EleganceAshwin Chandrakant PatilPoynadMar 2024Mar 20242 yrs 8 mo late
Rudraksh ResidencySwaraj DevelopersVarasoliMar 2024Mar 20242 yrs 8 mo late
Gamiraj TakshBebibai Ganpat PatilUlaweApr 2024Apr 20242 yrs 7 mo late
Lata HeightsKrishna Krupa DevelopersKarjatApr 2024Apr 20242 yrs 7 mo late
Nityanand Co Operative Housing Society LtdLifespace Builders And DevelopersPanvelApr 2024Apr 20242 yrs 7 mo late
Jamila MansionNusrat Rashid KhanUlaweApr 2024Apr 20242 yrs 7 mo late
Om Crystal OrchidS S InfraVadghar (Ct)Apr 2024Apr 20242 yrs 7 mo late
Punir Gaurav - B WingPunir Gaurav Developers Pvt Ltd.PunirApr 2024Apr 20262 yrs 7 mo late
Sarang AmberAarconUlaweApr 2024Apr 20242 yrs 7 mo late
Om Sai ApartmentOm Sai Builders & DevelopersRoha Ashtami (M Cl)May 2024May 20242 yrs 6 mo late
Subhash PremierStonewood Properties LLPSajgaonMay 2024May 20242 yrs 6 mo late
J M V HeightsJai Malahar Vansh Infra TechVadghar (Ct)May 2024May 20242 yrs 6 mo late
Pushp PinnacleMokal Brothers Realty Private LimitedKhargharMay 2024May 20242 yrs 6 mo late
ShivtirthRakesh Vikas PardeshiVadghar (Ct)May 2024May 20242 yrs 6 mo late
21 EnclavePushpam Infra LLPKasheleMay 2024May 20242 yrs 6 mo late
Crystal HeightsCrystal DevelopersKarjatJun 2024Jun 20242 yrs 5 mo late
Shree Kutir Chs LtdLifespace Builders And DevelopersPanvelJun 2024Jun 20242 yrs 5 mo late
Swaraj HeightsSwaraj Homes Builders And DevelopersKaranjadeJun 2024Jun 20242 yrs 5 mo late
Anand NiwashMahendra Kumar MahtoChipaleJun 2024Jun 20242 yrs 5 mo late
Aradya PridePrashant Janardan KoliWahalJun 2024Jun 20242 yrs 5 mo late
Balkrishna ChhabiBalkrishna DevelopersWahalJun 2024Jun 20242 yrs 5 mo late
Brajesh SapphireLife Good Happiness HomesHarigramJun 2024Jun 20252 yrs 5 mo late
Deep PlanetSambhav Planet ProjectsKhargharJun 2024Jun 20252 yrs 5 mo late
Dev KrupaDev EnterpriseUlaweJun 2024Jun 20242 yrs 5 mo late
Ekvira ApartmentEkvira DevelopersDevadJun 2024Jun 20262 yrs 5 mo late
Ganga NiwasArihant BuildconUlaweJun 2024Jun 20242 yrs 5 mo late
JanaiNeelkanth InfraUlaweJun 2024Jun 20242 yrs 5 mo late
Kc Dream PlazaShri A M AssociatesWahalJun 2024Jun 20242 yrs 5 mo late
Krishna VasuMahesh Baban BhoirWahalJun 2024Jun 20242 yrs 5 mo late
Kaivalya ResidencyShree Siddhivinayak DevelopersPalidevadJun 2024Jun 20242 yrs 5 mo late
Laxmi IconLaxmi RealtyDhamoteJun 2024Jun 20242 yrs 5 mo late
Matoshree ResidencyRk Builders And DevelopersWahalJun 2024Jun 20242 yrs 5 mo late
Mahalaxmi DarshanBharat Vishanji PatelNeralJun 2024Jun 20242 yrs 5 mo late
NandanvanShree Vasturachana HomesAjivaliJun 2024Jun 20252 yrs 5 mo late
Om Shree Guru AdvaitamrutVinayak Baburao WadekarVadghar (Ct)Jun 2024Jun 20242 yrs 5 mo late
Omkar ResidencyOmkar DevelopersWahalJun 2024Jun 20242 yrs 5 mo late
ParasmaiRati Builders And DevelopersUlaweJun 2024Jun 20242 yrs 5 mo late
Praradi PearlRakeshkumar Avadha SrivastavaKevaleJun 2024Jun 20242 yrs 5 mo late
Raj HeightRajhas EnterpriseNeralJun 2024Jun 20242 yrs 5 mo late
Royal Diamond ApartmentAmol Ashok PatilVadghar (Ct)Jun 2024Jun 20252 yrs 5 mo late
Sakshi ApartmentSujata Samir ModiMahadJun 2024Jun 20242 yrs 5 mo late
Savitri ArpanSavitri Group Builders & DevelopersVadghar (Ct)Jun 2024Jun 20242 yrs 5 mo late
Shiv PratimaFly DevelopersBopeleJun 2024Jun 20242 yrs 5 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology