RERA projects in Harigram
8 projects under 8 MahaRERA registrations, registered 2022–2026. 88% have a completion date extended beyond the one promised.
Locality
8RERA projects
8Registrations
7Completion still due1 past their completion date
4 monthsMedian extension beyond promised date88% of registrations extended
0Regulatory casesnone on MahaRERA's lists
11Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2022 | 1 |
| 2023 | 2 |
| 2024 | 0 |
| 2025 | 2 |
| 2026 | 3 |
Projects in Harigram
8 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sai NilayOm Sairam Nilay LLP | PR1270002602134 | 5 Oct 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Calista cornerS And W Buildcon LLP | PM1270002601178 | 15 Jul 2026 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
| Sai MajestyOm Sairam Developers LLP | PR1270002600638 | 3 Jun 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Sai MannatOm Sairam Developers | PR1270002500157 | 30 Jun 2025 | 10 Jun 2028 | 10 Oct 2028 | Extended 4 mo | 0 |
| Pearl ResidencyDiva Buildcon Private Limited | P52000080685 | 25 Jun 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Shanti SkyraaShanti Developers | P52000052940 | 5 Oct 2023 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Vrindavan RiversideGreenscape Builders And Developers | P52000051515 | 23 Jun 2023 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Brajesh SapphireLife Good Happiness Homes | P52000033994 | 17 Mar 2022 | 30 Jun 2024 | 29 Jun 2025 | Extended 12 mo | 0 |
Other localities in Panvel
Most active promoters
By projects registered here, as named on MahaRERA.
- Diva Buildcon Private Limited1 project
- Greenscape Builders And Developers1 project
- Life Good Happiness Homes1 project
- Om Sairam Developers1 project
- Om Sairam Developers LLP1 project
- Om Sairam Nilay LLP1 project
- S And W Buildcon LLP1 project
- Shanti Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology