Vrindavan Riverside
Deedo IDDP-RAI-MJSRCompletion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 4% of its units are booked.
Harigram, Raigarh 410206 · by Greenscape Builders And Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 23 Jun 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000051515
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000051515 | 23 Jun 2023 | 31 Dec 2026 | 30 Apr 2027 | Greenscape Builders And Developers | Project page |
Documents87
1 document held by Deedo, 86 filings listed on MahaRERA's project page
Finance
- PAN CardPAN - GREENSCAPE.pdf · uploaded 11 May 2023Source
Legal
Show all 87 documentsShow fewer documents
Migrated
- 1 a Details of encumbrances concerned to FinanceFINANCIAL ENCUMBRANCES.pdf · uploaded 11 May 2023Source
- 1 b Details of encumbrances concerned to LegalFINANCIAL ENCUMBRANCES.pdf · uploaded 11 May 2023Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT NEW.pdf · uploaded 11 May 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificates.pdf · uploaded 11 May 2023Source
- 1 Declaration about Commencement CertificateCOMMENCEMENT CERTIFICATE.pdf · uploaded 11 May 2023Source
- 1 Declaration in FORM BFORM B MULAY_NEW.pdf · uploaded 11 May 2023Source
- 2 Declaration in FORM BFORM B SAHU SHEWALE.pdf · uploaded 11 May 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A MULAY.pdf · uploaded 11 May 2023Source
- 1 Proforma of Allotment letter1 Proforma of Allotment letter.pdf · uploaded 11 May 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK AC.pdf · uploaded 11 May 2023Source
- 1 Deviation Report with respect to Allotment letterDEVIATION REPORT ALLOTMENT REPORT.pdf · uploaded 11 May 2023Source
- 1 Deviation Report with respect to model copy of AgreementNO DEVIATION REPORT.pdf · uploaded 11 May 2023Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 18 May 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 18 May 2023Source
- 2 a Details of encumbrances concerned to Financelegal encum.pdf · uploaded 25 May 2023Source
- 2 b Details of encumbrances concerned to Legallegal encum.pdf · uploaded 25 May 2023Source
- 1 Other – LegalANN A.pdf · uploaded 25 May 2023Source
- 1 Proforma of Agreement for saleLATEST SAMPLE AGREEMENT.pdf · uploaded 6 Jun 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentPLAN.pdf · uploaded 10 Jun 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentLAYOUT NEW.pdf · uploaded 10 Jun 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 311223.pdf · uploaded 8 Oct 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 310324.pdf · uploaded 8 Oct 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 300624.pdf · uploaded 8 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form1300923.pdf · uploaded 8 Oct 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 300624.pdf · uploaded 8 Oct 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 310324.pdf · uploaded 8 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 31122023.pdf · uploaded 8 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 300923.pdf · uploaded 8 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form2300923.pdf · uploaded 8 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 311223.pdf · uploaded 8 Oct 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 310324.pdf · uploaded 8 Oct 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 300624.pdf · uploaded 8 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5.pdf · uploaded 22 Oct 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 300924.pdf · uploaded 26 Oct 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 300924.pdf · uploaded 26 Oct 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 300924.pdf · uploaded 26 Oct 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 300924.pdf · uploaded 13 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 jan 2025.pdf · uploaded 6 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 31122024.pdf · uploaded 6 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 31122024.pdf · uploaded 6 Mar 2025Source
- Form 1form 1 31032025.pdf · uploaded 1 Jul 2025Source
- Form 2FORM 31325.pdf · uploaded 1 Jul 2025Source
- Form 3form 3 310325 (2).pdf · uploaded 1 Jul 2025Source
- Disclosure of Sold and Booked Inventorysold 310325.pdf · uploaded 1 Jul 2025Source
- Withdrawal Update Form 1FORM 1 (1).pdf · uploaded 20 Aug 2025Source
- Withdrawal Update Form 2ARCH.pdf · uploaded 20 Aug 2025Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 20 Aug 2025Source
- Form 5 (FY 2023-2024)FORM 5.pdf · uploaded 23 Sep 2025Source
- Form 5 (FY 2024-2025)DocScanner 30 Sept 2025 15-49.pdf · uploaded 23 Sep 2025Source
- Withdrawal Update Form 1fORM 1 300925.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 2FORM 2 300925.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 3form 3 30092025_compressed (1).pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 1FORM 1 31122025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 2FORM 2 30122025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 1FORM 1 31032026.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 2FORM 2 31032026.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 3Form 3 31032026.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 1FORM 1 30062026.pdf · uploaded 16 Jul 2026Source
- Withdrawal Update Form 2FORM 2 30062026.pdf · uploaded 16 Jul 2026Source
- Withdrawal Update Form 3FORM 3 30062026.pdf · uploaded 16 Jul 2026Source
- Form 5 (FY 2025-2026)FORM 5 25-26.pdf · uploaded 30 Sep 2026Source
Technical
Technical (Architect)
- Documentform1300923.pdf · uploaded 8 Oct 2024Source
- Documentform 1 311223.pdf · uploaded 8 Oct 2024Source
- Documentform 1 310324.pdf · uploaded 8 Oct 2024Source
- Documentform 1 300624.pdf · uploaded 8 Oct 2024Source
- Documentform 1 300924.pdf · uploaded 26 Oct 2024Source
- DocumentFORM 1 jan 2025.pdf · uploaded 6 Mar 2025Source
- DocumentFORM 1 30062026.pdf · uploaded 14 Jul 2026Source
Technical (Engineer)
- Documentform2300923.pdf · uploaded 8 Oct 2024Source
- Documentform 2 311223.pdf · uploaded 8 Oct 2024Source
- Documentform 2 310324.pdf · uploaded 8 Oct 2024Source
- DocumentFORM 2 300624.pdf · uploaded 8 Oct 2024Source
- Documentform 2 300924.pdf · uploaded 26 Oct 2024Source
- Documentform 2 31122024.pdf · uploaded 6 Mar 2025Source
- DocumentFORM 2 30062026.pdf · uploaded 14 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SURVEY NO 32C
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK24 units in all
- Address
- SURVEY NO 32C, Panvel, PanvelPIN 410206
- Village
- Harigram, Panvel taluka
- Land area for this project
- 2,559 sq m (27,550 sq ft)
- Permissible built-up area
- 970 sq m (10,443 sq ft)
- Sanctioned built-up area
- 970 sq m (10,443 sq ft)
- Recreational open space
- 264 sq m (2,844 sq ft)
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO 32C
Boundaries
- North
- Survey No 32b
- South
- 32d
- East
- Survey No 20 1
- West
- Survey No 32k
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking24 units
1 of 24 units booked (4%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 31.79 sq m · 342 sq ft | 4 | 0 |
| 1BHK | 31.89 sq m · 343 sq ft | 4 | 0 |
| 1BHK | 33.33 sq m · 359 sq ft | 4 | 0 |
| 1BHK | 33.47 sq m · 360 sq ft | 4 | 1 |
| 1BHK | 33.56 sq m · 361 sq ft | 8 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Meenakshi Shrivastav | — |
| Chartered accountant | Pratik Hawal | — |
| Engineer | Yateesh Tare | — |
Source: MahaRERA project page. Contact details are not shown.