RERA projects in Varasoli

13 projects under 14 MahaRERA registrations, registered 2017–2026. 14% have a completion date extended beyond the one promised.

13RERA projects
14Registrationssome projects hold several
5Completion still due9 past their completion date
18 monthsMedian extension beyond promised date14% of registrations extended
1Regulatory caseson 1 project
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20180
20191
20202
20211
20222
20232
20242
20250
20262

Projects in Varasoli

13 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Prajyot ExtendGaurav Pravin GharatPR127000260202523 Sep 202631 Dec 2028—Not yet due0
Golden PalmsAkshay BuildersPM127000260056929 May 202631 Dec 2029—Not yet due0
Ambika ResidencyPradeep Ramchand KotwaniP5200007849517 Dec 202430 Jun 2027—Not yet due0
ShivamSarch Properties Private LimitedP520000546936 Feb 202430 Jun 2026—Promised date passed0
Abhyuday ResidencySrinath Ashok PatilP520000498926 Mar 202331 Mar 2026—Promised date passed0
Vithai ResidencyRamchandra Parshuram NakateP520000493577 Feb 202331 Mar 2026—Promised date passed0
Rudraksh ResidencySwaraj DevelopersP5200004553724 May 202231 Mar 2024—Promised date passed0
Alibag WestendAcorpP520000336952 Mar 202231 Dec 2027—Not yet due0
SadguruShekhar Janardan GandhiP520000257204 Jul 202015 Nov 202215 Nov 2024Extended 24 mo0
Aashirwad HeightsSwaraj DevelopersP5200002494912 Mar 20201 Feb 2023—Promised date passed0
Aaryahi ResidencyMvk DevelopersP5200002046115 Apr 20196 Apr 2025—Promised date passed1
EkaanteGreen Park DevelopersP52000009962, P5200002953323 Aug 201731 Dec 202629 Jun 2025Not yet due0
Shivalay ResidencyRaju Ghanshyam PurswaniP5200000683316 Aug 201731 Dec 2018—Promised date passed0

Other localities in Alibag

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Swaraj Developers2 projects
  2. Acorp1 project
  3. Akshay Builders1 project
  4. Gaurav Pravin Gharat1 project
  5. Green Park Developers1 project
  6. Mvk Developers1 project
  7. Pradeep Ramchand Kotwani1 project
  8. Raju Ghanshyam Purswani1 project
  9. Ramchandra Parshuram Nakate1 project
  10. Sarch Properties Private Limited1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology