Gondhalpada, Raigarh
3 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects6
Registrations6
Completion still due24 past their date
Median extension14 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
6 MahaRERA registrations in Gondhalpada
1 not yet due1 extended, not yet due4 past even the latest date
Extended registrations moved their completion date by a median of 14 months.
Projects in Gondhalpada
6 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Indraprastha Building 4Indraprastha Associates | Due Dec 2026 | — | — |
| Indraprastha Building 6M/S Indraprastha Associates | 10 mo late | — | — |
| Esmeralda by ForstarForstar D B Realty | Due Jun 2030, extended 4 mo | — | — |
| AshwamedhaManoj Eknath Gharat | 1 yr 4 mo late | — | 100% |
| INDRAPRASTHA PHASE II Includes Building No 08Indraprastha Associates | 2 yrs 11 mo late | — | 65% |
| INDRAPRASTHA PHASE 2 Includes Building no. 5,9M/s Indraprastha Associates | 5 yrs 5 mo late | — | 63% |
Nearby: other localities in Alibag
Most active promoters
- Indraprastha Associates2 projects
- M/s Indraprastha Associates2 projects
- Forstar D B Realty1 project
- Manoj Eknath Gharat1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology