RERA projects in Kawir

3 projects under 3 MahaRERA registrations, registered 2017–2024. 33% have a completion date extended beyond the one promised.

3RERA projects
3Registrations
2Completion still due1 past their completion date
120 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20190
20200
20210
20220
20231
20241

Projects in Kawir

3 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Balibaug RekreasiPushpam Infra LLPP5200007703716 Jul 202431 Dec 2026—Not yet due0
BalibaugPushpam Infra LLPP520000502921 Apr 202321 Mar 2025—Promised date passed0
Cidade VidaBhide LifespacesP520000127627 Sep 201731 Dec 201931 Dec 2029Extended 120 mo0

Other localities in Alibag

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Pushpam Infra LLP2 projects
  2. Bhide Lifespaces1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology