RERA projects in Kihim

3 projects under 3 MahaRERA registrations, registered 2017–2025. None has an extended completion date on record.

3RERA projects
3Registrations
1Completion still due2 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20190
20200
20210
20220
20231
20240
20251

Projects in Kihim

3 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Coco MarinaAtharva Realty Private LimitedPR127000250174911 Dec 202531 Dec 2031—Not yet due0
Bharadi ResidencyMetRP5200005068128 Apr 202331 Dec 2025—Promised date passed0
Paradiso BayAtharva Realty Private LimitedP520000122411 Sep 201730 Dec 2021—Promised date passed0

Other localities in Alibag

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Atharva Realty Private Limited2 projects
  2. MetR1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology