RERA projects in Devad

7 projects under 7 MahaRERA registrations, registered 2017–2025. 29% have a completion date extended beyond the one promised.

Locality
7RERA projects
7Registrations
1Completion still due6 past their completion date
18 monthsMedian extension beyond promised date29% of registrations extended
1Regulatory caseson 1 project
6Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20181
20191
20202
20210
20220
20230
20240
20251

Projects in Devad

7 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Shree AshtavinayakInfiniti DevelopersP5200008037829 May 202530 Jun 2027—Not yet due0
Ekvira ApartmentEkvira DevelopersP520000269367 Nov 202030 Jun 202430 Jun 2026Extended 24 mo0
Pratham PridePratham InfraP5200002507718 Mar 202030 Mar 202429 Mar 2025Extended 12 mo0
Anant SakshiAnant BuildersP520000197735 Mar 201930 Dec 202230 Dec 2022Promised date passed0
Kokan ResidencySmile Intra Trade (I) Private LimitedP5200001829322 Oct 201831 Dec 201931 Dec 2019Promised date passed0
Dattnath AanganSheetal Prabhakar SonawaneP520000144614 Dec 201731 Dec 201831 Dec 2018Promised date passed1
neelsankalpNeelsankalpP5200001324721 Sep 201721 Dec 201921 Dec 2019Promised date passed0

Other localities in Panvel

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Anant Builders1 project
  2. Ekvira Developers1 project
  3. Infiniti Developers1 project
  4. Neelsankalp1 project
  5. Pratham Infra1 project
  6. Sheetal Prabhakar Sonawane1 project
  7. Smile Intra Trade (I) Private Limited1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology