Palidevad, Raigarh
2 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects5
Registrations5
Completion still due05 past their date
Median extension27 months20% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
5 MahaRERA registrations in Palidevad
5 past even the latest date
Extended registrations moved their completion date by a median of 27 months.
Projects in Palidevad
5 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Navnath ResidencyPandharinath Changdev Thakur | 1 yr 10 mo late | — | 0% |
| Kaivalya ResidencyShree Siddhivinayak Developers | 2 yrs 4 mo late | — | 0% |
| Swastik ResidencyRamanuj Sidhariram Sharma | 3 yrs 4 mo late | — | 0% |
| Balaji ParkAyaz Ahmed Mohommedali Kabadi | 3 yrs 7 mo late | — | 21% |
| Saanvi ResidencySPH Builders & Developers | 5 yrs 10 mo late | — | 0% |
Nearby: other localities in Panvel
Most active promoters
- Ayaz Ahmed Mohommedali Kabadi1 project
- Pandharinath Changdev Thakur1 project
- Ramanuj Sidhariram Sharma1 project
- Shree Siddhivinayak Developers1 project
- SPH Builders & Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology