RERA projects in Taloje Majkur
43 projects under 44 MahaRERA registrations, registered 2017–2026. 7% have a completion date extended beyond the one promised.
43RERA projects
44Registrationssome projects hold several
27Completion still due17 past their completion date
12 monthsMedian extension beyond promised date7% of registrations extended
1Regulatory caseson 1 project
13Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 4 |
| 2018 | 7 |
| 2019 | 5 |
| 2020 | 2 |
| 2021 | 1 |
| 2022 | 5 |
| 2023 | 7 |
| 2024 | 5 |
| 2025 | 5 |
| 2026 | 3 |
Projects in Taloje Majkur
43 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shri Basaveshwar Park 1New Life Space Developers LLP | PR1271012600687 | 8 Jun 2026 | 30 Jun 2029 | — | Not yet due | 0 |
| Shree Gatha ResidencyShree Builders And Developers | PM1270002600584 | 1 Jun 2026 | 31 Dec 2032 | — | Not yet due | 0 |
| Shelter OneShelter Builders | PM1270002600406 | 13 May 2026 | 31 Dec 2032 | — | Not yet due | 0 |
| The Green Crest Phase IISai Shradha Developer | PR1271012501229 | 15 Oct 2025 | 30 Dec 2029 | — | Not yet due | 0 |
| Om AnantaOm Group | PR1270002501176 | 10 Oct 2025 | 8 Jan 2029 | — | Not yet due | 0 |
| Laxmi PrestigeLaxmi Builders | PR1270002501012 | 29 Sep 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Rudra Dream CitySai Ashirwad | PM1270002500392 | 28 Jul 2025 | 30 Jun 2030 | — | Not yet due | 0 |
| Mahaavir AmberOmprakash Bhanwarlal Chhajer | P52000080039 | 21 Apr 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Pioneer Aura - Phase 1Pioneer Builders and Developers | P52000077851 | 7 Nov 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Abri CrystalAbufaiz Rabbani Khan | P52000055781 | 16 Apr 2024 | 31 Dec 2031 | — | Not yet due | 0 |
| AyaanaShree Sai Developers | P52000055490 | 2 Apr 2024 | 31 Dec 2030 | — | Not yet due | 0 |
| Nandanvan Phase 2H B Realty | P52000055464 | 22 Mar 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Gauri Shankar CornerGanesh Baban Patil | P52000055236 | 14 Mar 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Sm EliteS M Hitech Developers | P52000052521 | 8 Sep 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Sm EmeraldS M Hitech Developers | P52000051962 | 13 Jul 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Jijai TulsiShubham Realty | P52000050705 | 28 Apr 2023 | 31 Dec 2028 | — | Not yet due | 0 |
| Om UnnatiOm Group | P52000050075 | 13 Mar 2023 | 30 Nov 2026 | — | Not yet due | 0 |
| Sai PalaciaEarth India Infrastructure | P52000049544 | 15 Feb 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Arihant Anant Phase IIMahalaxmi Cotton Mills | P52000049395 | 8 Feb 2023 | 30 Dec 2027 | — | Not yet due | 0 |
| Shelter DreamRabbani khan | P52000049410 | 8 Feb 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Bhiva TowerYash Developers Unit Of Vikrant V Raikar Huf | P52000045952 | 15 Jun 2022 | 30 Apr 2025 | 30 Apr 2027 | Extended 24 mo | 0 |
| NandanvanH B Realty | P52000045672 | 6 Jun 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| AlampataShree Sai Developers | P52000035080 | 4 May 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Krishna ResidencyPratap Babaji Shinde | P52000034269 | 30 Mar 2022 | 30 Jun 2026 | — | Promised date passed | 0 |
| Sm Hitech TulipS M Hitech Developers | P52000033133 | 9 Feb 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Arihant AnantMahalaxmi Cotton Mills | P52000030053 | 26 Jul 2021 | 30 Dec 2026 | — | Not yet due | 0 |
| Royal ComplexRoyal Developers | P52000026820 | 28 Oct 2020 | 31 Dec 2026 | — | Not yet due | 0 |
| Orchid EnclaveSiddhivinayak Associates | P52000024194 | 24 Jan 2020 | 30 Dec 2026 | — | Not yet due | 0 |
| Siddheshwar Residency 2Siddhivinayak Associates | P52000023608 | 20 Dec 2019 | 30 Dec 2024 | — | Promised date passed | 0 |
| Sai SnehBabulal Tulsi Manani | P52000022834 | 30 Oct 2019 | 30 Mar 2023 | — | Promised date passed | 0 |
| Armaan HeightsArmaan Height | P52000022607 | 9 Oct 2019 | 30 Mar 2024 | — | Promised date passed | 0 |
| QN HeightsQualitas Naman Home Makers LLP | P52000021242 | 14 Jun 2019 | 30 Dec 2024 | — | Promised date passed | 1 |
| Shree SaiSaras Associates | P52000020668 | 3 May 2019 | 30 Jun 2021 | — | Promised date passed | 0 |
| Sea Queen ParkSea Queen Developers Pvt Ltd | P52000018773 | 4 Dec 2018 | 12 Jun 2025 | — | Promised date passed | 0 |
| RathodsDharmendra Rathod | P52000018395 | 30 Oct 2018 | 30 Jun 2027 | — | Not yet due | 0 |
| Neem VatikaH B Realty | P52000017108 | 13 Jul 2018 | 28 Dec 2020 | — | Promised date passed | 0 |
| Siddheshwar ResidencySiddhivinayak Associates | P52000016759 | 12 Jun 2018 | 30 Dec 2022 | — | Promised date passed | 0 |
| Swarn JeevanOmkaresh Infratech LLP | P52000016381, P52000017887 | 10 May 2018 | 30 Dec 2023 | — | Promised date passed | 0 |
| Shree Krupa DarshNitin Ananta Mhatre | P52000015367 | 20 Feb 2018 | 30 Dec 2020 | — | Promised date passed | 0 |
| Arjun ResidencyVijay Vasdev Bathija | P52000012321 | 1 Sep 2017 | 30 Jun 2019 | — | Promised date passed | 0 |
| Venus HeightsRupal Enterprises | P52000004341 | 9 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Extended 12 mo | 0 |
| Metro ApartmentMetro Enterprises | P52000003818 | 6 Aug 2017 | 31 Mar 2019 | — | Promised date passed | 0 |
| Simran MajesticVikrant Vikas Raikar | P52000002117 | 31 Jul 2017 | 30 Jun 2018 | 31 Dec 2018 | Extended 6 mo | 0 |
Other localities in Panvel
- Ulawe678 projects
- Vadghar (Ct)421 projects
- Panvel301 projects
- Wahal299 projects
- Karanjade250 projects
- Taloje Panchnad151 projects
- Dapoli142 projects
- Kharghar137 projects
- Kamothe86 projects
- New Panvel74 projects
- Kalamboli58 projects
- Koyana Velhe41 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- H B Realty3 projects
- Siddhivinayak Associates3 projects
- S M Hitech Developers3 projects
- Mahalaxmi Cotton Mills2 projects
- Om Group2 projects
- Shree Sai Developers2 projects
- Abufaiz Rabbani Khan1 project
- Armaan Height1 project
- Babulal Tulsi Manani1 project
- Dharmendra Rathod1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology