Skip to content

Delayed projects in Maharashtra

8,431 MahaRERA projects in 36 districts are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 22 of 169.

ProjectLocalityPromisedRevisedDelivery
Mohan PetalsAkshay BhujbalBhosariPuneOct 2020Oct 20216 yrs 1 mo late
Parshwa HillJrv Construction CoAmbarnath(M Cl)ThaneOct 2020Oct 20206 yrs 1 mo late
Pearl ResidencyPushpa Construction CoWard GnorthMumbai CityOct 2020Apr 20236 yrs 1 mo late
Sai Vision ResidencyAvision RealtorsAsangaon (Ct)ThaneOct 2020Dec 20246 yrs 1 mo late
SeascapesVijay BuildconHarnaiRatnagiriOct 2020Feb 20226 yrs 1 mo late
Swastik Spira Phase IISwastik RealtyChikhaliPuneOct 2020Oct 20206 yrs 1 mo late
Sai MannatBhushan Bhalchandra MhatreVadghar (Ct)RaigarhOct 2020Dec 20236 yrs 1 mo late
prathamesh Residencyprathamesh builders & developersBaramati (M Cl)PuneOct 2020Oct 20206 yrs 1 mo late
Evergreen ApartmentsKaiyomerz Cowas PaliaDalkhanThaneNov 2020Nov 20206 yrs late
Royale PlazaRoyale Developers AopDhankawadiPuneNov 2020Dec 20246 yrs late
Sampada HouseSampasa Landmarksprivate LimitedPimpri Chinchawad (M Corp.)PuneNov 2020Nov 20206 yrs late
Siddhagiri ResidencySs EngineeringUlaweRaigarhNov 2020Dec 20246 yrs late
Ryyan ViewHidayat KhanThane (M Corp.)ThaneNov 2020Nov 20206 yrs late
RAGA ALTIS Phase IKundalwal And GroupAurangabad (M Corp.)AurangabadNov 2020—6 yrs late
RAGA ALTIS Phase IIKundalwal And GroupAurangabad (Cb)AurangabadNov 2020May 20226 yrs late
City Center ComplexMaheboobali Mahmmadgous ManerSangli Miraj Kupwad (M Corp.)SangliNov 2020Nov 20216 yrs late
Bhagirathi TowerAditya RathiTeosaAmravatiNov 2020—6 yrs late
SahyadriJ.v.r. AssociatesVaralePuneNov 2020Nov 20206 yrs late
Brahmanchaitanya ApartmentSatish Ramchandra ShedgePhaltan (M Cl)SataraNov 2020Mar 20216 yrs late
R K WonderMohammad Rashid Abdul Qayyum KhanChinchvali GoheRaigarhNov 2020Mar 20256 yrs late
Swami ResidencySatish Bapu GiriShahapurThaneNov 2020Nov 20206 yrs late
Aadiraj ApartmentShree Ganesh DevelopersVasaivirar City (M Corp)PalgharNov 2020May 20246 yrs late
Aarcon-SuyogPradeep Janardan AarasKhed (M Cl)RatnagiriNov 2020Oct 20216 yrs late
AnuthamAmardeep ConstructionsKurlaMumbai SuburbanNov 2020Jun 20236 yrs late
Devdatta Toweryashraj corporationKurlaMumbai SuburbanNov 2020Sep 20236 yrs late
FelicitaVyankatesh Builders and DevelopersBanerPuneNov 2020Nov 20206 yrs late
FelicitaAbhiraj DevelopersBanerPuneNov 2020Nov 20206 yrs late
Kakade HouseJva And AssociatesKothrudPuneNov 2020Nov 20206 yrs late
LotusSwasti InfraZiradRaigarhNov 2020Nov 20206 yrs late
Nirmiti ArmaanNirmiti DevelopersPandharpurSolapurNov 2020Nov 20206 yrs late
Paramount HeightMahir Builders And DevelopersTaloje PanchnadRaigarhNov 2020Nov 20206 yrs late
Royal CastleShreenath DevelopersAmbarnath(M Cl)ThaneNov 2020Mar 20246 yrs late
Sai SagarSanjay Mahendra SinghNeralRaigarhNov 2020Nov 20206 yrs late
Shree Abhishek Co-Operative Housing Society LimitedDivya EnterpriseBorivaliMumbai SuburbanNov 2020Jun 20236 yrs late
Shree Samarth ResidencyShree Samarth Infra DevelopersPashaneRaigarhNov 2020May 20236 yrs late
V AawasAtharva DevelopersKaranjadeRaigarhNov 2020May 20226 yrs late
V AmberAtharva DevelopersVadghar (Ct)RaigarhNov 2020May 20226 yrs late
V MallVijaykumar Jagannath ValanjuKankavaliSindhudurgNov 2020Jun 20246 yrs late
V NiwasAtharva DevelopersVadghar (Ct)RaigarhNov 2020May 20226 yrs late
Vedant EnclaveSara EnterprisesBadlapur (M Cl)ThaneNov 2020Nov 20206 yrs late
Vithai DevelopersVithai DevelopersCharholiPuneNov 2020May 20226 yrs late
Whispering Towers Efg WingsHousing Development And Infrastructure LtdKurlaMumbai SuburbanNov 2020Nov 20206 yrs late
Kotak RoyaleKotak SonsPalgharDec 2020May 20255 yrs 11 mo late
Shree Ganesh ParkShree Ganesha DevelopersKadamwak WastiPuneDec 2020Jun 20225 yrs 11 mo late
Raj Villa GPravin Balaprasad BiyaniWadi Bk.NandedDec 2020Dec 20205 yrs 11 mo late
Govind NiwasShree Sai Datta DevelopersMumbai CityDec 2020Apr 20235 yrs 11 mo late
Noor PlazaKGN ConstructionsAkkalkotAkolaDec 2020—5 yrs 11 mo late
ElysiumAnand Yashwant BuchadeMarunjiPuneDec 2020Jun 20245 yrs 11 mo late
sahil manzils.s.m.developerTaloje PanchnadRaigarhDec 2020Dec 20205 yrs 11 mo late
Vinayak Heights Phase 1Vinayak AssociateKurlaMumbai SuburbanDec 2020Dec 20235 yrs 11 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology