Delayed projects in Maharashtra
8,426 MahaRERA projects in 36 districts are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 2 of 169.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| KalaniketanSiroyaFM Constructions Pvt Ltd | KurlaMumbai Suburban | Jan 2018 | Jan 2019 | 8 yrs 10 mo late |
| Prayeja PearlPrayeja Realty Private Limited | Wadgaon BkPune | Jan 2018 | Jan 2018 | 8 yrs 10 mo late |
| Vastu Pratibha ResidencySunil Dayanandrao Dhilpe | Aurangabad (M Corp.)Aurangabad | Jan 2018 | — | 8 yrs 10 mo late |
| Greystone ParkSiddheshwar Construction | HarishchandriPune | Feb 2018 | Feb 2018 | 8 yrs 9 mo late |
| Anuradha ShrushtiVidhi Builders & Associates | Sangli Miraj Kupwad (M Corp.)Sangli | Feb 2018 | Feb 2018 | 8 yrs 9 mo late |
| Piccadilly IVRoyal Palms India Pvt. Ltd. | BorivaliMumbai Suburban | Feb 2018 | Feb 2019 | 8 yrs 9 mo late |
| Sai ShaktiMangesh Eknath Thakur | KaranjadeRaigarh | Feb 2018 | Feb 2018 | 8 yrs 9 mo late |
| Royal ResidencyAkshay Builders & Developers | SatkarsthalPune | Mar 2018 | Dec 2020 | 8 yrs 8 mo late |
| ganadish krupa palaceganadish krupa palace | TitwalaThane | Mar 2018 | Mar 2018 | 8 yrs 8 mo late |
| Asmi DreamzAjay Malshi Dedhia | BorivaliMumbai Suburban | Mar 2018 | Dec 2024 | 8 yrs 8 mo late |
| Ammons Eminent WING AUnited Constructions | Kondhwa KhurdPune | Mar 2018 | Dec 2018 | 8 yrs 8 mo late |
| Balasaheb Deoras Sahaniwas Phase 2Prakash Narayanrao Raole | Nagpur (M Corp.)Nagpur | Mar 2018 | Mar 2022 | 8 yrs 8 mo late |
| Castle PeakInnerspace | KurlaMumbai Suburban | Mar 2018 | Mar 2019 | 8 yrs 8 mo late |
| Charu Ved ApartmentGandhi Associates | DighiPune | Mar 2018 | Jun 2023 | 8 yrs 8 mo late |
| Construction of 69 shops at sno 263 CTS no 6A/6 Ekta nagar Malwani Malad west Mumbai95Mumbai Housing And Area Development Board | BorivaliMumbai Suburban | Mar 2018 | Oct 2020 | 8 yrs 8 mo late |
| Dnyandhurv ApartmentKamlesh Nana Kothawade | Nashik | Mar 2018 | — | 8 yrs 8 mo late |
| EcogramShri Siddhivinayak Builders | ShikrapurPune | Mar 2018 | Mar 2018 | 8 yrs 8 mo late |
| Garden County Type BSanklecha Constructions | Nashik (M Corp.)Nashik | Mar 2018 | Mar 2018 | 8 yrs 8 mo late |
| Hirani RegencyHirani Lifespaces | BoisarPalghar | Mar 2018 | Nov 2024 | 8 yrs 8 mo late |
| Kamtam Icon A WingPrakash Shankar Kamtam | Solapur (M Corp.)Solapur | Mar 2018 | Dec 2022 | 8 yrs 8 mo late |
| KanyakapuramMetrocity Homes | Nagpur (M Corp.)Nagpur | Mar 2018 | Dec 2021 | 8 yrs 8 mo late |
| Malwani West View CHS LTDMalwani West View CHS LTD | BorivaliMumbai Suburban | Mar 2018 | Mar 2018 | 8 yrs 8 mo late |
| Nath ResidencyShraddha Sankul | DighiPune | Mar 2018 | Aug 2022 | 8 yrs 8 mo late |
| Om ImperiaShree Samarthya Builders & Developers | Pen (M Cl)Raigarh | Mar 2018 | Mar 2022 | 8 yrs 8 mo late |
| Padmadevi EnclaveManjusha Girish Pande | Aurangabad (M Corp.)Aurangabad | Mar 2018 | — | 8 yrs 8 mo late |
| Pure GoldSudhir Vasu Shetty | KurlaMumbai Suburban | Mar 2018 | Mar 2019 | 8 yrs 8 mo late |
| Rohini AppartmentSujata Samir Modi | Mahad (M Cl)Raigarh | Mar 2018 | Mar 2019 | 8 yrs 8 mo late |
| Regent PalaceSadhna Infrastructures | BorivaliMumbai Suburban | Mar 2018 | Mar 2019 | 8 yrs 8 mo late |
| Sai PalaceSai Deveopers | Thane (M Corp.)Thane | Mar 2018 | Mar 2018 | 8 yrs 8 mo late |
| Sai SapphireDkm Realtors | Thane (M Corp.)Thane | Mar 2018 | Mar 2018 | 8 yrs 8 mo late |
| Shri Yamai KrupaJeevandeep Developers | BorivaliMumbai Suburban | Mar 2018 | Oct 2022 | 8 yrs 8 mo late |
| Sakaar NashikSakaar Developers | Ashok NagarNashik | Mar 2018 | Mar 2019 | 8 yrs 8 mo late |
| Satra Business ParkSatra Developers | KurlaMumbai Suburban | Mar 2018 | Mar 2024 | 8 yrs 8 mo late |
| Shwet VillaKamla Ranjit Singh | KurlaMumbai Suburban | Mar 2018 | Mar 2018 | 8 yrs 8 mo late |
| Swami ArcadeVertical Spaces | KaranjadeRaigarh | Mar 2018 | Oct 2020 | 8 yrs 8 mo late |
| Tungwa PowaiMHADA | AndheriMumbai Suburban | Mar 2018 | Mar 2019 | 8 yrs 8 mo late |
| skywards nirvanaskywards developers | HadapsarPune | Mar 2018 | Oct 2020 | 8 yrs 8 mo late |
| Ajmal HeightsMrk Realty | Mumbai City | Apr 2018 | Apr 2018 | 8 yrs 7 mo late |
| Buildings on portion of Sub plot A CTS no 671A 662A 610A etc of KandivaliAnubhav Anilkumar Aggarwal | BorivaliMumbai Suburban | Apr 2018 | Oct 2020 | 8 yrs 7 mo late |
| Grande View7 Capital 1Chirag Developers | Ambegaon BkPune | Apr 2018 | Dec 2025 | 8 yrs 7 mo late |
| Nirman CrownNirman Superstructures | Nagpur (M Corp.)Nagpur | Apr 2018 | Apr 2019 | 8 yrs 7 mo late |
| Suba ZirconSuba Realty Private Limited | AndheriMumbai Suburban | Apr 2018 | Jan 2020 | 8 yrs 7 mo late |
| Lobpsons And Tania IndustriesLobpsons & Tania Builders | SativaliPalghar | May 2018 | Jun 2025 | 8 yrs 6 mo late |
| StatusParadise Developers | Kolhapur (M Corp.)Kolhapur | May 2018 | May 2018 | 8 yrs 6 mo late |
| Blue OasisKarimkhan Mohidinkhan Pathan | Satara (Ct)Aurangabad | May 2018 | Jun 2023 | 8 yrs 6 mo late |
| Le JardinJay Construction India | KurlaMumbai Suburban | May 2018 | Apr 2019 | 8 yrs 6 mo late |
| Sunrise hillssamir manohar mantri | Dahiwali T. WarediRaigarh | May 2018 | Oct 2020 | 8 yrs 6 mo late |
| Aditya IconAditya Buildcon | TandulwadiPune | May 2018 | May 2018 | 8 yrs 6 mo late |
| Ashwa AnnexAshwamedh Construction | Thane (M Corp.)Thane | May 2018 | May 2018 | 8 yrs 6 mo late |
| Bhagyoday ResidencyMangalmay Realities | Pen (M Cl)Raigarh | May 2018 | May 2018 | 8 yrs 6 mo late |
Delayed projects by district
Pune · 2,217Thane · 1,161Raigarh · 1,042Mumbai Suburban · 996Nashik · 481Palghar · 364Nagpur · 323Aurangabad · 243Mumbai City · 243Satara · 227Ratnagiri · 193Sangli · 176Solapur · 156Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 11Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology