Lobpsons And Tania Industries

Certificate Signed

Sativali, Palghar 401202 |Promoter: Lobpsons & Tania Builders

18 Aug 2017Registered with MahaRERA
1 May 2018Promised completion
26 Jun 2025Revised completionPushed back 7 years and 1 month
1Building
42Units registered24 booked (57%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
Industiral shop, Industrial shop42 units in all
Address
S. No. 150 H. No. 2a, Pelhar, PelharPIN 401202
Designated bank account
19
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.37296, 72.82201
Lobpsons And Tania Industries is at latitude 19.37296, longitude 72.82201.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 7 years and 1 month

The latest completion date on record passed 1 year and 4 months ago.

Registered
18 Aug 2017
Promised
1 May 2018
Revised
26 Jun 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900000800518 Aug 20171 May 201826 Jun 2025Lobpsons & Tania BuildersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Lobpsons And Tania Industries242

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

24 of 42 units booked (57%), as the promoter reported to MahaRERA

Industiral shop · 30 unitsIndustrial shop · 12 units
TypeCarpet areaUnitsBooked
Industiral shop61.5 sq m · 662 sq ft33
Industiral shop86.96 sq m · 936 sq ft11
Industiral shop95.13 sq m · 1,024 sq ft44
Industiral shop113.81 sq m · 1,225 sq ft11
Industiral shop116.13 sq m · 1,250 sq ft22
Industiral shop129.13 sq m · 1,390 sq ft11
Industiral shop170.38 sq m · 1,834 sq ft11
Industiral shop176.05 sq m · 1,895 sq ft170
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Industrial shop61.87 sq m · 666 sq ft33
Industrial shop78.41 sq m · 844 sq ft11
Industrial shop109.44 sq m · 1,178 sq ft11
Industrial shop114.27 sq m · 1,230 sq ft21
Industrial shop147.71 sq m · 1,590 sq ft33
Industrial shop164.44 sq m · 1,770 sq ft11
Industrial shop174.38 sq m · 1,877 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 62 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN.pdf · uploaded 29 Jul 2017Source

Legal

  • Legal Title reportTitle Report-min.pdf · uploaded 29 Jul 2017Source
  • Declaration Form BForm 'B'-min.pdf · uploaded 29 Jul 2017Source
  • Declaration Form BForm B desuza.pdf · uploaded 5 Jul 2023Source

Migrated

  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate-min.pdf · uploaded 28 Jul 2017Source
  • 1 PAN CardPAN.pdf · uploaded 29 Jul 2017Source
Show all 64 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportTitle Report-min.pdf · uploaded 29 Jul 2017Source
  • 1 Details of encumbrancesDETAILS OF ENCUMBERANCE.pdf · uploaded 29 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan-ilovepdf-compressed.pdf · uploaded 29 Jul 2017Source
  • 1 Building Plan Approval (IOD)Building Approval-ilovepdf-compressed (1).pdf · uploaded 29 Jul 2017Source
  • 1 Declaration in FORM BForm 'B'-min.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate-min.pdf · uploaded 29 Jul 2017Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 29 Jul 2017Source
  • 2 Proforma of Allotment letterProform sale agreement.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of CA (Form 3)FORM 3.pdf · uploaded 31 Jul 2017Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Annual report on statement of accounts FY 2017-18.pdf · uploaded 24 Dec 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Annual report on statement of accounts FY 2018-19.pdf · uploaded 24 Dec 2019Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 28 Jun 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold.pdf · uploaded 28 Jun 2023Source
  • 2 Declaration in FORM BForm B desuza.pdf · uploaded 5 Jul 2023Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect's Certificate Form - 1.pdf · uploaded 5 Jul 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Form - 2.pdf · uploaded 5 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Engineer Certificate For Quality 19-20.pdf · uploaded 5 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineer Certificate For Quality 2020-21.pdf · uploaded 5 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineer Certificate For Quality 2021-22.pdf · uploaded 5 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineer Certificate For Quality 2022 -23.pdf · uploaded 5 Jul 2023Source
  • 2 Certificates of CA (Form 3)CA Certificate Form 3.pdf · uploaded 24 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)CA Certificate Form 5 19 20.pdf · uploaded 24 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)CA Certificate Form 5 20 21.pdf · uploaded 24 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)CA Certificate form 5 22 23.pdf · uploaded 24 Jul 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate _compressed (1).pdf · uploaded 25 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 21 22 (3).pdf · uploaded 25 Jul 2023Source
  • Form 1Declaration for Nil Quarterly Progress Report..pdf · uploaded 16 Dec 2025Source
  • Form 2FORM 2 - MAR 2024-SIGNED.pdf · uploaded 16 Dec 2025Source
  • Form 3Declaration in lieu of Form 3.pdf · uploaded 16 Dec 2025Source
  • Disclosure of Sold and Booked InventorySOLD BOOKED INVENTORY.pdf · uploaded 16 Dec 2025Source
  • Form 1Declaration for Nil Quarterly Progress Report..pdf · uploaded 16 Dec 2025Source
  • Form 2FORM 2 - JUNE 2024-SIGNED.pdf · uploaded 16 Dec 2025Source
  • Form 3Declaration in lieu of Form 3.pdf · uploaded 16 Dec 2025Source
  • Disclosure of Sold and Booked InventorySOLD BOOKED INVENTORY.pdf · uploaded 16 Dec 2025Source
  • Form 1FORM 1 - SEP -2024-SIGNED.pdf · uploaded 16 Dec 2025Source
  • Form 2FORM 2 - SEP 2024-SIGNED.pdf · uploaded 16 Dec 2025Source
  • Form 3Declaration in lieu of Form 3.pdf · uploaded 16 Dec 2025Source
  • Disclosure of Sold and Booked InventorySOLD BOOKED INVENTORY.pdf · uploaded 16 Dec 2025Source
  • Form 1FORM 1 - DEC 2024-SIGNED.pdf · uploaded 16 Dec 2025Source
  • Form 2FORM 2 - DEC 2024-SIGNED.pdf · uploaded 16 Dec 2025Source
  • Form 3Declaration in lieu of Form 3.pdf · uploaded 16 Dec 2025Source
  • Disclosure of Sold and Booked InventorySOLD BOOKED INVENTORY.pdf · uploaded 16 Dec 2025Source
  • Form 1FORM 1 - MAR 2025-SIGNED.pdf · uploaded 16 Dec 2025Source
  • Form 2FORM 2 - MAR 2025-SIGNED.pdf · uploaded 16 Dec 2025Source
  • Form 3Declaration in lieu of Form 3.pdf · uploaded 16 Dec 2025Source
  • Disclosure of Sold and Booked InventorySOLD BOOKED INVENTORY.pdf · uploaded 16 Dec 2025Source
  • Form 1FORM 1 - JUNE 2025-SIGNED.pdf · uploaded 16 Dec 2025Source
  • Form 2FORM 2 - JUNE 2025-SIGNED.pdf · uploaded 16 Dec 2025Source
  • Form 3Declaration in lieu of Form 3.pdf · uploaded 16 Dec 2025Source
  • Disclosure of Sold and Booked InventorySOLD BOOKED INVENTORY.pdf · uploaded 16 Dec 2025Source
  • Form 2A (FY 2024-2025)FORM 2A - FY 24-25-SIGNED.pdf · uploaded 19 Aug 2026Source
  • Form 2A (FY 2025-2026)FORM 2A - FY 25-26.pdf · uploaded 19 Aug 2026Source

Technical

  • DocumentBuilding Approval-ilovepdf-compressed (1).pdf · uploaded 29 Jul 2017Source
  • DocumentLayout Plan-ilovepdf-compressed.pdf · uploaded 29 Jul 2017Source

Technical (Architect)

  • DocumentArchitect's Certificate Form - 1.pdf · uploaded 5 Jul 2023Source

Technical (Engineer)

  • DocumentEngineer Certificate Form - 2.pdf · uploaded 5 Jul 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In sativali, Palghar taluka

Survey, CTS, gat or plot numbers

S. NO. 150 H. NO. 2A

Boundaries

North
Road
South
Survey No 150 Part
East
Nh 8
West
Survey No 151

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSanjay S Narang—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology