RERA projects in Chandrapur
228 projects under 229 MahaRERA registrations across 35 localities, registered 2017–2026. 9% have a completion date extended beyond the one promised.
228RERA projectsin 35 localities
229Registrationssome projects hold several
34Completion still due137 past their completion date, 37 marked completed
22 monthsMedian extension beyond promised date9% of registrations extended
16Regulatory caseson 16 projects
147Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 40 |
| 2018 | 11 |
| 2019 | 17 |
| 2020 | 17 |
| 2021 | 18 |
| 2022 | 31 |
| 2023 | 8 |
| 2024 | 15 |
| 2025 | 8 |
| 2026 | 6 |
Localities in Chandrapur
By number of registered projects. Talukas and localities as MahaRERA names them.
Chandrapur (M Cl)46 projectsBrahmapuri (M Cl)36 projectsChandrapur33 projectsKosara11 projectsBallarpur (M Cl)8 projectsBeldati7 projectsBrahmapuri6 projectsDatala6 projectsBhadravati (M Cl)5 projectsKhanji5 projectsNavegaon Makta5 projectsBallarpur4 projects
All 35 localities
- Chandrapur (M Cl)46
- Brahmapuri (M Cl)36
- Chandrapur33
- Kosara11
- Ballarpur (M Cl)8
- Beldati7
- Brahmapuri6
- Datala6
- Bhadravati (M Cl)5
- Khanji5
- Navegaon Makta5
- Ballarpur4
- Navkhala4
- Bhadravati3
- Kharbi Makta3
- Khedmakta3
- Khutala3
- Madheli2
- Mul2
- Nanda (Ct)2
- Udapur2
- Arwat1
- Bamhani1
- Bamni1
- Chimur1
- Chincholi Bk1
- Delanwadi1
- Dewai Govindpur Rayyatwari1
- Morwa1
- Mul (M Cl)1
- Nandori Bk.1
- Rajoli1
- Rajura (M Cl)1
- Talodhi1
- Warora1
Projects in Chandrapur
228 projects registered with MahaRERA in this district and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Adtiya PlazaAnklesh Natthuji Khaire | P50900023705 | 2 Jan 2020 | 15 Nov 2023 | — | Completed | 1 |
| Khushi ResidencyRavneetkaur Charanjeetsingh Wadhwa | P50900023672 | 2 Jan 2020 | 28 Nov 2022 | 31 Dec 2025 | Extended 37 mo | 0 |
| Bokade layoutMahendra Shrawanji Bokade & Others | P50900023571 | 19 Dec 2019 | 30 Mar 2024 | 30 Mar 2025 | Completed | 0 |
| Prabhuleela AppartmentPratibha Vinod Bhusari | P50900023475 | 16 Dec 2019 | 2 Dec 2022 | — | Completed | 0 |
| Siddhesh ResidencyPritima Deepak Nilawar | P50900022710 | 12 Oct 2019 | 30 Dec 2021 | — | Promised date passed | 0 |
| Gaurav NagariSatish D Humne & Taufik N Pathan | P50900022137 | 28 Aug 2019 | 30 Mar 2022 | — | Completed | 0 |
| Nikhil PlanetJ K Builders And Developers | P50900022124 | 28 Aug 2019 | 30 Apr 2024 | 14 Mar 2026 | Extended 23 mo | 0 |
| Shri Pragati Developers And BuildersJitendra Nanaji Itankar | P50900021718 | 22 Jul 2019 | 30 Dec 2022 | — | Promised date passed | 0 |
| Royal AmbienceA B Plotters & Structures | P50900020616 | 26 Apr 2019 | 28 Feb 2025 | — | Completed | 0 |
| VinayakvillaShree Developer Partner | P50900020541 | 22 Apr 2019 | 28 Feb 2023 | — | Promised date passed | 0 |
| Sai Awas ApartmentNiraj Pralhadrao Padgilwar | P50900020406 | 9 Apr 2019 | 30 Dec 2021 | — | Completed | 0 |
| Tanush ResidencyGajanan Moreshwar Nilawar | P50900020345 | 5 Apr 2019 | 30 Dec 2021 | — | Completed | 0 |
| Matai NagarShri. Ashish Madanrao karande and Sau. Anjali Ashish Karande | P50900019970 | 15 Mar 2019 | 30 Dec 2021 | — | Completed | 0 |
| Thakrewadivyankatesh infraalliance | P50900019910 | 13 Mar 2019 | 15 Jan 2025 | 1 Jan 2030 | Extended 60 mo | 0 |
| Atharva Riddhi Appartmentsantosh sadashiv kolettiwar | P50900019759 | 5 Mar 2019 | 31 Dec 2019 | — | Promised date passed | 0 |
| Shri Ganesh ResidencyGharkul Construction Company Private Limited | P50900019776 | 5 Mar 2019 | 24 Jan 2022 | — | Promised date passed | 0 |
| Shri Sukhkarta PlazaGharkul Construction Company Private Limited | P50900019749 | 5 Mar 2019 | 2 Nov 2021 | — | Promised date passed | 0 |
| Vighnesh ResidencyGajanan Moreshwar Nilawar | P50900019410 | 29 Jan 2019 | 30 Dec 2021 | 31 Dec 2027 | Extended 72 mo | 0 |
| Chawhan RoyalsMangesh Ratilal Chawhan | P50900019244 | 14 Jan 2019 | 30 Sep 2025 | — | Promised date passed | 0 |
| Deul Construction Mandirayan Phase 1Prashant Sudhakarrao Kashettiwar | P50900018942 | 17 Dec 2018 | 30 Jun 2021 | 30 Dec 2022 | Extended 18 mo | 0 |
| Devalaya Phase 2Prashant Sudhakarrao Kashettiwar | P50900018937 | 17 Dec 2018 | 30 Dec 2021 | — | Promised date passed | 0 |
| Aryan Appartment - 4Aryan Developers | P50900018219 | 15 Oct 2018 | 20 Dec 2021 | — | Promised date passed | 0 |
| Sumukhay ApartmentSaurabh Sunil Abhyankar | P50900017767 | 17 Sep 2018 | 31 Jul 2019 | 30 Jun 2023 | Extended 47 mo | 0 |
| Riddhi Nagri Wing CVibha Rajesh Thakur | P50900017570 | 28 Aug 2018 | 31 Dec 2019 | — | Promised date passed | 0 |
| Shree PalaceAmit Vasantrao Mendhule | P50900017465 | 13 Aug 2018 | 30 Dec 2021 | — | Promised date passed | 0 |
| Balaji HeightsDnr Infra Ventures | P50900017303 | 31 Jul 2018 | 28 Feb 2018 | — | Promised date passed | 0 |
| Ganpati HeritageBhaskar Manohar Wadaskar | P50900017240 | 24 Jul 2018 | 20 Dec 2021 | — | Promised date passed | 0 |
| Kalpataru EnclaveKalpana Pundalik Telmasre | P50900016862 | 20 Jun 2018 | 31 Dec 2019 | — | Promised date passed | 0 |
| Nirmal ResidencyPritam Suresh Pachare | P50900015827 | 27 Mar 2018 | 31 Dec 2019 | 15 Dec 2020 | Extended 12 mo | 0 |
| Vasant VillaR&P Developers | P50900015809 | 26 Mar 2018 | 30 Sep 2020 | — | Promised date passed | 0 |
| Rishi Residency - Wing EApeksha Dhawal Raja | P50900014649 | 20 Dec 2017 | 30 Dec 2023 | — | Promised date passed | 0 |
| Riddhi ApartmentVibha Rajesh Thakur | P50900014490 | 4 Dec 2017 | 31 Mar 2019 | — | Promised date passed | 0 |
| Riddhi Nagri Wing AVibha Rajesh Thakur | P50900014207 | 14 Nov 2017 | 30 Jun 2019 | — | Promised date passed | 0 |
| Ashiyana PlazaDevashree Builder | P50900014114 | 7 Nov 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| CarnationSynergy Plotters And Structures | P50900012618 | 6 Sep 2017 | 1 Jul 2026 | — | Promised date passed | 0 |
| DaisySynergy Plotters And Structures | P50900012612 | 6 Sep 2017 | 1 Jul 2022 | — | Promised date passed | 0 |
| Shlok AppartmentSwati Prashant Dhatrak | P50900012515 | 1 Sep 2017 | 25 Dec 2018 | — | Promised date passed | 0 |
| Shree HeightsAnuj Vasantrao Mendhule | P50900012482 | 1 Sep 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Devalaya Phase 1Prashant Sudhakarrao Kashettiwar | P50900011153 | 31 Aug 2017 | 30 Jun 2019 | — | Promised date passed | 0 |
| ShriLaxmi ChambersSudhir Tulshiram Thakre | P50900010597 | 31 Aug 2017 | 30 Mar 2018 | — | Promised date passed | 0 |
| Tara ResidencyVaibhavi Builders | P50900011550 | 31 Aug 2017 | 30 Jun 2023 | — | Promised date passed | 0 |
| Vst3-Aakash Ganga 7Vidarbha Town Developers | P50900010888 | 31 Aug 2017 | 31 Dec 2019 | — | Promised date passed | 0 |
| Vst3- Aakasj Ganga 1Vidarbha Town Developers | P50900011774 | 31 Aug 2017 | 31 Dec 2019 | — | Promised date passed | 0 |
| Ganesha ResidencyGajanan Moreshwar Nilawar | P50900010219 | 24 Aug 2017 | 31 Dec 2019 | 30 Nov 2020 | Extended 11 mo | 0 |
| LilacSynergy Plotters And Structures | P50900009329 | 22 Aug 2017 | 1 Jul 2022 | — | Completed | 0 |
| Varad ResidencyGajanan Moreshwar Nilawar | P50900009833 | 22 Aug 2017 | 31 May 2018 | — | Promised date passed | 0 |
| Vst3- Aakash Ganga 6Vidarbha Town Developers | P50900009769 | 22 Aug 2017 | 31 Dec 2019 | — | Completed | 0 |
| Swapnapurti Infracon Private LimitedSwapnapurti Infracon Private Limited | P50900008841 | 19 Aug 2017 | 30 Nov 2018 | — | Completed | 0 |
| LilySynergy Plotters And Structures | P50900008051 | 18 Aug 2017 | 1 Jul 2022 | — | Completed | 0 |
| Vaibhavi HeightsYashpal Dewanand Khobragade | P50900008437 | 18 Aug 2017 | 30 Dec 2023 | — | Completed | 0 |
| Vasant VillaSmita Gajanan Nilawar | P50900008319 | 18 Aug 2017 | 31 Dec 2018 | — | Completed | 0 |
| VighnahartaGajanan Moreshwar Nilawar | P50900008262 | 18 Aug 2017 | 31 Jul 2018 | — | Completed | 0 |
| Vst3-AakashVidarbha Town Developers | P50900008017 | 18 Aug 2017 | 31 Dec 2019 | — | Completed | 0 |
| Parivartan PlazaAnkit Builders And Developer | P50900007040 | 17 Aug 2017 | 30 Nov 2018 | — | Completed | 0 |
| Aditya EnclaveAditya Infraventures | P50900006450 | 14 Aug 2017 | 15 Jan 2021 | — | Promised date passed | 0 |
| MrunaliniDeshak | P50900006276 | 14 Aug 2017 | 16 Feb 2019 | 30 Oct 2020 | Extended 20 mo | 0 |
| Saivilla AppartmentNiraj Pralhadrao Padgilwar | P50900005775 | 14 Aug 2017 | 30 Dec 2018 | — | Completed | 0 |
| Shree Balaji TowerVijay Ramdas Khade | P50900006547 | 14 Aug 2017 | 31 Dec 2017 | — | Completed | 0 |
| Vst3-Aakash Ganga4Vidarbha Town Developers | P50900005935 | 14 Aug 2017 | 31 Dec 2019 | — | Completed | 0 |
| Josa Residency IIJosa Infra | P50900005299 | 11 Aug 2017 | 21 Jan 2019 | — | Completed | 0 |
| Ballarpur Business CenterDilip Dadaji Mamidwar | P50900005099 | 9 Aug 2017 | 30 Jan 2021 | — | Completed | 0 |
| Chintamani ResidencyShree Chintamani Developers | P50900004838 | 9 Aug 2017 | 31 Jul 2018 | — | Completed | 0 |
| Vasant VillaD Y Developers | P50900004760 | 9 Aug 2017 | 31 Dec 2017 | — | Completed | 0 |
| Vst3-Jal And Aakash Ganga 5Vidarbha Town Developers | P50900004731 | 9 Aug 2017 | 31 Dec 2019 | — | Completed | 0 |
| atharva heightssantosh sadashiv kolettiwar | P50900003508 | 5 Aug 2017 | 20 Jan 2021 | — | Completed | 0 |
| Construction of 100 Flats under MIG on site No.134 at New ChandrapurMHADA(Nagpur Board) | P50900003200 | 4 Aug 2017 | 30 Aug 2018 | — | Promised date passed | 0 |
| Saidwarka AppartmentNiraj Pralhadrao Padgilwar | P50900002432 | 1 Aug 2017 | 30 Dec 2018 | — | Promised date passed | 0 |
| Dsk GreenDsk Infra Project | P50900002141 | 31 Jul 2017 | 30 Mar 2022 | — | Promised date passed | 0 |
| Construction of 96Ts EWS 36Ts MIG 8 Shops and 4 Office Chambers at site No 125 Datala New ChandrapurMHADA ( Nagpur Board ) | P50900001085 | 26 Jul 2017 | 30 Oct 2020 | — | Promised date passed | 0 |
| Site No.124, Datala, New ChandrapurMHADA(Nagpur Board) | P50900000159 | 5 Jul 2017 | 30 Oct 2020 | — | Promised date passed | 0 |
| Aditya InfinityAditya Infraventures | P50900026024 | — | — | — | — | 1 |
| Aman Plaza | P50900028207 | — | — | — | — | 0 |
| Antargaon Paradwahi | P50900031848 | — | — | — | — | 0 |
| Atharva PalaceAtharva Construction | P50900051643 | — | — | — | — | 1 |
| atharva sadan | P50900005992 | — | — | — | — | 0 |
| Avighana Heights | P50900027632 | — | — | — | — | 0 |
| Capital Residency Phase 1 | P50900014308 | — | — | — | — | 0 |
| Capital Residency Phase IVElevate Construction | P50900034886 | — | — | — | — | 1 |
| Chandrapur Bussiness Center | P50900012501 | — | — | — | — | 0 |
| Club Building | P50900015934 | — | — | — | — | 0 |
| Dsk Homes | P50900019539 | — | — | — | — | 0 |
| Dsk Park | P50900024365 | — | — | — | — | 0 |
| Dskpark 2 | P50900028197 | — | — | — | — | 0 |
| Exotica | P50900005976 | — | — | — | — | 0 |
| Gajanan Residency | P50900029366 | — | — | — | — | 0 |
| Gangaputra LayoutIndira Pramod Meshram | P50900053867 | — | — | — | — | 1 |
| Hanisha Enclave | P50900018134 | — | — | — | — | 0 |
| Jet Kingdom Breeze | P50900013270 | — | — | — | — | 0 |
| Jet Kingdom Breeze Phase I | P50900013689 | — | — | — | — | 0 |
| Krushna KunjNirman Developers | P50900050403 | — | — | — | — | 1 |
| Mahalaxmi Apartment | P50900019610 | — | — | — | — | 0 |
| Mahalaxmi AppartmentDarshan Erectors Pvt.Ltd | P50900046073 | — | — | — | — | 1 |
| Namo Nagari Part - 1 | P50900026441 | — | — | — | — | 0 |
| Narayan NagariRahul Narayanji Shetiye | P50900054075 | — | — | — | — | 1 |
| New Musabhai Nagar - IIGulzar Kamruddin Dhamani | P50900047173 | — | — | — | — | 1 |
| Nysa Residency | P50900029612 | — | — | — | — | 0 |
| P50900047503 | P50900047503 | — | — | — | — | 0 |
| Pushparaj Appartment | P50900022041 | — | — | — | — | 0 |
| Rajwada Height | P50900024711 | — | — | — | — | 0 |
| Rajwada Township | P50900004569 | — | — | — | — | 0 |
Other districts
- Pune13,424 projects
- Thane7,170 projects
- Mumbai Suburban6,592 projects
- Raigarh5,728 projects
- Nashik4,171 projects
- Palghar3,084 projects
- Nagpur2,793 projects
- Aurangabad1,469 projects
- Mumbai City1,380 projects
- Satara1,181 projects
- Ratnagiri1,138 projects
- Kolhapur863 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- PMG Associates7 projects
- Vibha Rajesh Thakur6 projects
- Vidarbha Town Developers6 projects
- Gajanan Moreshwar Nilawar5 projects
- Tushar Santosh Kumar Agarwal5 projects
- Shree Gurukrupa Builders And Developers4 projects
- Synergy Plotters And Structures4 projects
- Darshan Erectors Pvt Ltd3 projects
- MHADA ( Nagpur Board )3 projects
- Niraj Pralhadrao Padgilwar3 projects
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology