8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects9
Registrations9
Completion still due34 past their date
Median extension4 months57% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

9 MahaRERA registrations in Bhadravati and the places within it

3 extended, not yet due4 past even the latest date2 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Bhadravati

9 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Gajanan NagariR B InfraDue Apr 2029, extended 4 mo——
9 Star Height9 Star DevelopersDue Sep 2027, extended 4 mo——
Balaji TownShrihari Builders And DevelopersCompleted——
Rajwada Township Phase IISkyline Builders And DevelopersDue Apr 2029, extended 4 mo——
Deul Construction Mandirayan Phase 1Prashant Sudhakarrao KashettiwarCompleted, extended 1 yr 6 mo—47%
All 9 projects →
Bhadravati market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Prashant Sudhakarrao Kashettiwar3 projects
  2. 9 Star Developers1 project
  3. R B Infra1 project
  4. Shrihari Builders And Developers1 project
  5. Skyline Builders And Developers1 project

Bhadravati, in questions

How many projects in Bhadravati run late?

8 in 10 MahaRERA registrations (7 of 9): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhadravati by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology