Deedo IDDL-CHA-CHANDRAPUR5 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects228in 35 localities
Registrations230some projects hold several
Completion still due35137 past their date
Median extension4 months21% of registrations extended
Regulatory cases16on 16 projects
5 in 10 registrations run late here
230 MahaRERA registrations in Chandrapur and the places within it
37 completed14 not yet due21 extended, not yet due100 past even the latest date58 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Chandrapur
228 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| WING A BUILDING(Residential) & WING B BUILDING(Residential)Patrakar Nagar Sahakari Gruhnirman Sanstha Maryadit | Due Oct 2029 | — | — |
| Sai Taj Nagar 2Masum Shabbirali Jiwani and Mohammad Ali Shabbirali Jiwani | Due Sep 2031 | — | — |
| Gajanan NagariR B Infra | Due Apr 2029, extended 4 mo | — | — |
| Skand ResidencyVaishnavi Construction | Due Jun 2029, extended 4 mo | — | — |
| Chawhan Royals Tower-1Chawhan Royals | Due Apr 2032, extended 4 mo | — | — |
Localities in Chandrapur
- Chandrapur (M Cl)47 projects
- Brahmapuri (M Cl)36 projects
- Chandrapur31 projects
- Kosara13 projects
- Ballarpur (M Cl)8 projects
- Beldati7 projects
- Datala6 projects
- Bhadravati (M Cl)5 projects
- Brahmapuri5 projects
- Navegaon Makta5 projects
- Ballarpur4 projects
- Khanji4 projects
Other districts
Most active promoters
- Pmg Associates6 projects
- Vibha Rajesh Thakur6 projects
- Vidarbha Town Developers6 projects
- Gajanan Moreshwar Nilawar5 projects
- Shree Gurukrupa Builders And Developers4 projects
- Synergy Plotters And Structures4 projects
- Tushar Santosh Kumar Agarwal4 projects
- Darshan Erectors Pvt Ltd3 projects
- Mhada(Nagpur Board)3 projects
- Niraj Pralhadrao Padgilwar3 projects
Chandrapur, in questions
How many projects in Chandrapur run late?
5 in 10 MahaRERA registrations (121 of 230): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Chandrapur by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology