Skip to content

Navkhala, Chandrapur

Deedo IDDL-CHA-NAVKHALA

10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4
Registrations4
Completion still due04 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

4 MahaRERA registrations in Navkhala

4 past even the latest date

Projects in Navkhala

4 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Gaurav NagariJiya Shabir Qureshi & 1 Other2 yrs 8 mo late——
Laxmi NagriVijay Tulsiram Yerne & Swapnil Ramesh Yerne2 yrs 8 mo late——
Lalaji TownshipRajan Pannalal JaiswalCompleted——
Lalaji TownshipAbhishek Rajan JaiswalCompleted——
Navkhala market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Nearby: other villages in Chandrapur

Most active promoters

  1. Abhishek Rajan Jaiswal1 project
  2. Jiya Shabir Qureshi & 1 Other1 project
  3. Rajan Pannalal Jaiswal1 project
  4. Vijay Tulsiram Yerne & Swapnil Ramesh Yerne1 project

Navkhala, in questions

How many projects in Navkhala run late?

10 in 10 MahaRERA registrations (4 of 4): their completion date was extended or has passed, data through 7 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Navkhala by Deedo. Medians on fewer than 3 deeds are not shown.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology