RERA projects in Ballarpur (M Cl)

8 projects under 8 MahaRERA registrations, registered 2017–2025. 13% have a completion date extended beyond the one promised.

8RERA projects
8Registrations
1Completion still due7 past their completion date, 3 marked completed
22 monthsMedian extension beyond promised date13% of registrations extended
1Regulatory caseson 1 project
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20183
20191
20202
20210
20220
20230
20240
20251

Projects in Ballarpur (M Cl)

8 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Rishi PlazaPremkumar Sadhumal MulaniP5090008093925 Aug 202531 Dec 2028—Not yet due0
Ganpati PrimeBhaskar Manohar WadaskarP509000256251 Jul 202015 Dec 2023—Completed0
Adtiya PlazaAnklesh Natthuji KhaireP509000237052 Jan 202015 Nov 2023—Completed1
Nikhil PlanetJ K Builders And DevelopersP5090002212428 Aug 201930 Apr 202414 Mar 2026Extended 23 mo0
Aryan Appartment - 4Aryan DevelopersP5090001821915 Oct 201820 Dec 2021—Promised date passed0
Ganpati HeritageBhaskar Manohar WadaskarP5090001724024 Jul 201820 Dec 2021—Promised date passed0
Vasant VillaR&P DevelopersP5090001580926 Mar 201830 Sep 2020—Promised date passed0
Ballarpur Business CenterDilip Dadaji MamidwarP509000050999 Aug 201730 Jan 2021—Completed0

Other localities in Ballarpur

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Bhaskar Manohar Wadaskar2 projects
  2. Anklesh Natthuji Khaire1 project
  3. Aryan Developers1 project
  4. Dilip Dadaji Mamidwar1 project
  5. J K Builders And Developers1 project
  6. Premkumar Sadhumal Mulani1 project
  7. R&P Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology