RERA projects in Ballarpur (M Cl)
8 projects under 8 MahaRERA registrations, registered 2017–2025. 13% have a completion date extended beyond the one promised.
8RERA projects
8Registrations
1Completion still due7 past their completion date, 3 marked completed
22 monthsMedian extension beyond promised date13% of registrations extended
1Regulatory caseson 1 project
3Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 3 |
| 2019 | 1 |
| 2020 | 2 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 1 |
Projects in Ballarpur (M Cl)
8 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Rishi PlazaPremkumar Sadhumal Mulani | P50900080939 | 25 Aug 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Ganpati PrimeBhaskar Manohar Wadaskar | P50900025625 | 1 Jul 2020 | 15 Dec 2023 | — | Completed | 0 |
| Adtiya PlazaAnklesh Natthuji Khaire | P50900023705 | 2 Jan 2020 | 15 Nov 2023 | — | Completed | 1 |
| Nikhil PlanetJ K Builders And Developers | P50900022124 | 28 Aug 2019 | 30 Apr 2024 | 14 Mar 2026 | Extended 23 mo | 0 |
| Aryan Appartment - 4Aryan Developers | P50900018219 | 15 Oct 2018 | 20 Dec 2021 | — | Promised date passed | 0 |
| Ganpati HeritageBhaskar Manohar Wadaskar | P50900017240 | 24 Jul 2018 | 20 Dec 2021 | — | Promised date passed | 0 |
| Vasant VillaR&P Developers | P50900015809 | 26 Mar 2018 | 30 Sep 2020 | — | Promised date passed | 0 |
| Ballarpur Business CenterDilip Dadaji Mamidwar | P50900005099 | 9 Aug 2017 | 30 Jan 2021 | — | Completed | 0 |
Other localities in Ballarpur
- Bamni1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- Bhaskar Manohar Wadaskar2 projects
- Anklesh Natthuji Khaire1 project
- Aryan Developers1 project
- Dilip Dadaji Mamidwar1 project
- J K Builders And Developers1 project
- Premkumar Sadhumal Mulani1 project
- R&P Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology