Prabhuleela Appartment

Completed

Chandrapur (M Cl), Chandrapur 442402 |Promoter: Pratibha Vinod Bhusari

16 Dec 2019Registered with MahaRERA
2 Dec 2022Promised completion
1Building
11Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Unit types
2BHK, Office space, Shop11 units in all
Land area for this project
296 sq m (3,189 sq ft)
Permissible built-up area
592 sq m (6,377 sq ft)
Sanctioned built-up area
592 sq m (6,377 sq ft)
Address
94/13179, Pathanpura Road, PathanpuraPIN 442402
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 2 Dec 2022

The latest completion date on record passed 3 years and 10 months ago.

Registered
16 Dec 2019
Promised
2 Dec 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5090002347516 Dec 20192 Dec 2022—Pratibha Vinod BhusariProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Prabhuleela Appartment411

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

11 units registered

2BHK · 8 unitsOffice space · 2 unitsShop · 1 unit
TypeCarpet areaUnits
2BHK51.38 sq m · 553 sq ft3
2BHK51.8 sq m · 558 sq ft2
2BHK53.11 sq m · 572 sq ft3
Office space51.8 sq m · 558 sq ft1
Office space58.26 sq m · 627 sq ft1
Shop11.05 sq m · 119 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Prabhuleela Appartment

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBORE WELL100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIK TANK0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 16 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRAIN WATER HARVESTING0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable
  • STAIRCASE PASSAGE LIFTSTAIRCASE PASSAGE LIFT:60%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

15 documents held by Deedo, 19 filings listed on MahaRERA's project page

Title report

Form B

Encumbrance details

Commencement certificate

Form 1

Form 2

Registration certificate

Occupancy / completion certificate

  • Occupancy / completion certificate22 Aug 2023ViewSource
Show all 34 documentsShow fewer documents

Form 4

Other (3)

Allotment letter

Layout plan

Building plan

Document library

  • Copy of the legal title report2-TITLE REPORT.pdf · uploaded 11 Dec 2019View
  • Details of encumbrances3-LOAN SANCTION.pdf · uploaded 11 Dec 2019View
  • Copy of Layout Approval (in case of layout)4-LAYOUT PLAN .pdf · uploaded 11 Dec 2019View
  • Commencement Certificates / NA Order for plotted development10-PRARAMPH CERT .pdf · uploaded 11 Dec 2019View
  • Declaration in FORM B6-AFFI.pdf · uploaded 11 Dec 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)7-ARCHITECTS CER .pdf · uploaded 11 Dec 2019View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)9- ENGINEER CER.pdf · uploaded 11 Dec 2019View
  • Proforma of Allotment letter5-AGREEMENT TO SALE.pdf · uploaded 11 Dec 2019View
  • Building Plan Approval / NA Order for plotted development11-SAN PLAN.pdf · uploaded 11 Dec 2019View
  • Other12-MALMATA.pdf · uploaded 11 Dec 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOCCUPANCY.pdf · uploaded 22 Aug 2023View
  • Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 22 Aug 2023View
  • Status of Formation of Legal Entity (Society/Co Op etc.)ENTITY.pdf · uploaded 22 Aug 2023View

Promoter documents

  • Legal Title report2-TITLE REPORT.pdf · uploaded 11 Dec 2019View
  • Declaration Form B6-AFFI.pdf · uploaded 11 Dec 2019View

Technical documents

  • Layout Approval4-LAYOUT PLAN .pdfView
  • Building Plan Approval11-SAN PLAN.pdfView

Other legal documents

  • Other12-MALMATA.pdfView

Proforma allotment letter

  • Proforma allotment letter5-AGREEMENT TO SALE.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Chandrapur (M Cl), Chandrapur taluka

Survey, CTS, gat or plot numbers

94/13179

As published on MahaRERA's project page

94/13179

Boundaries

North
Nazul Land
South
Muncipal Road
East
Land Of Shri Annadrao Khanke
West
Land Nad Construction Of Sharda Natthuji Baeane

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Parinita Meshram—
Chartered accountantRatan Rathi—
Engineerparinita meshram—
Otherchannu devangan—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology