Skip to content
Residential / Group Housing · 3 buildings · 58 unitsRERA P50900008437

Vaibhavi Heights

Deedo IDDP-CHA-CDYP

MahaRERA shows it completed; no MahaRERA orders on record.

Datala, Chandrapur 442406 · by Yashpal Dewanand Khobragade

DeliveryCompletedAs MahaRERA showsRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 18 Aug 2017, completion promised 30 Dec 2023.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP50900008437
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5090000843718 Aug 201730 Dec 2023—Yashpal Dewanand KhobragadeProject page
Documents118

47 documents held by Deedo, 71 filings listed on MahaRERA's project page

Title report (11)

Show all 118 documentsShow fewer documents

Title report (11)

Encumbrance details

Form B (3)

Allotment letter (2)

Registration certificate

Occupancy / completion certificate

  • Occupancy / completion certificate30 Dec 2022ViewSource

Form 4

Form 2A (3)

Other (17)

Building plan (7)

Document library

  • Commencement Certificates / NA Order for plotted developmentpage-1.pdf · uploaded 25 Jul 2017View
  • Building Plan Approval (IOD)Block-B-C.pdf · uploaded 25 Jul 2017View
  • Building Plan Approval (IOD)Block-D.pdf · uploaded 25 Jul 2017View
  • Building Plan Approval (IOD)site plan.pdf · uploaded 25 Jul 2017View
  • Details of encumbrancesEncumbrances Certificate.pdf · uploaded 26 Jul 2017View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-1.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-2.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-3.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-5.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-6.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-7.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-8.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-9.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-10.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-11.pdf · uploaded 26 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)page-1.pdf · uploaded 26 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)page-2.pdf · uploaded 26 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)page-3.pdf · uploaded 26 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)page-4.pdf · uploaded 26 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)page-5.pdf · uploaded 26 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)page-1.pdf · uploaded 26 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)page-2.pdf · uploaded 26 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)page-3.pdf · uploaded 26 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)page-4.pdf · uploaded 26 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentpage-2.pdf · uploaded 26 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentpage-3.pdf · uploaded 26 Jul 2017View
  • Copy of the legal title reportpage-4.pdf · uploaded 26 Jul 2017View
  • Declaration in FORM BFORM B.pdf · uploaded 26 Jul 2017View
  • Declaration in FORM BFORM B-1.pdf · uploaded 26 Jul 2017View
  • Declaration in FORM BFORM B-2.pdf · uploaded 26 Jul 2017View
  • Building Plan Approval (IOD)Block-A.pdf · uploaded 26 Jul 2017View
  • Copy of Layout Approval (in case of layout)page-5.pdf · uploaded 26 Jul 2017View
  • Proforma of Allotment letterundertaking for agreement to sell.pdf · uploaded 28 Jul 2017View
  • Otherbank ac dec.pdf · uploaded 28 Jul 2017View
  • OtherRevised Receipt.pdf · uploaded 24 Aug 2018View
  • Building Plan Approval (IOD)BLOCK A.pdf · uploaded 24 Aug 2018View
  • Building Plan Approval (IOD)BLOCK BC.pdf · uploaded 24 Aug 2018View
  • Building Plan Approval (IOD)BLOCK D.pdf · uploaded 24 Aug 2018View
  • Building Plan Approval (IOD)SITE PLAN.pdf · uploaded 24 Aug 2018View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentoccupancy.pdf · uploaded 30 Dec 2022View
  • Architect’s Certificate on Completion of Project (Form 4)Form No 4.pdf · uploaded 4 Feb 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Adobe Scan 21-Jun-2023 (2) (1).pdf · uploaded 21 Jun 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Adobe Scan 21-Jun-2023 (1).pdf · uploaded 21 Jun 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Adobe Scan 21-Jun-2023.pdf · uploaded 21 Jun 2023View

Promoter documents

  • Legal Title reportpage-1.pdf · uploaded 26 Jul 2017View
  • Legal Title reportpage-2.pdf · uploaded 26 Jul 2017View
  • Legal Title reportpage-3.pdf · uploaded 26 Jul 2017View
  • Legal Title reportpage-5.pdf · uploaded 26 Jul 2017View
  • Legal Title reportpage-6.pdf · uploaded 26 Jul 2017View
  • Legal Title reportpage-7.pdf · uploaded 26 Jul 2017View
  • Legal Title reportpage-8.pdf · uploaded 26 Jul 2017View
  • Legal Title reportpage-9.pdf · uploaded 26 Jul 2017View
  • Legal Title reportpage-10.pdf · uploaded 26 Jul 2017View
  • Legal Title reportpage-11.pdf · uploaded 26 Jul 2017View
  • Legal Title reportpage-4.pdf · uploaded 26 Jul 2017View
  • Declaration Form BFORM B.pdf · uploaded 26 Jul 2017View
  • Declaration Form BFORM B-1.pdf · uploaded 26 Jul 2017View
  • Declaration Form BFORM B-2.pdf · uploaded 26 Jul 2017View

Technical documents

  • Building Plan ApprovalBlock-A.pdfView
  • Layout Approvalpage-5.pdfView
  • Building Plan ApprovalBlock-B-C.pdfView
  • Building Plan ApprovalBlock-D.pdfView
  • Building Plan Approvalsite plan.pdfView
  • Building Plan ApprovalBLOCK A.pdfView
  • Building Plan ApprovalBLOCK BC.pdfView
  • Building Plan ApprovalBLOCK D.pdfView
  • Building Plan ApprovalSITE PLAN.pdfView

Other legal documents

  • Otherbank ac dec.pdfView
  • OtherRevised Receipt.pdfView

Proforma allotment letter

  • Proforma allotment letterundertaking for agreement to sell.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 293/1A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Unit types
Flat, 2BHK, 3BHK, Row house58 units in all
Address
293/1aPIN 442406
Village
Datala, Chandrapur taluka
Land area for this project
3,359 sq m (36,151 sq ft)
Permissible built-up area
5,374 sq m (57,841 sq ft)
Sanctioned built-up area
2,123 sq m (22,854 sq ft)
Designated bank account
Canara Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

293/1A

Land as published on MahaRERA's project page

293/1A

Boundaries

North
Part Of Survey No 293-1a
South
12 Mtr Service Road Then 30mtr Mdr
East
Survey No 293-1b
West
Wall Compound Then Nallah

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking58 units · 2 parking spaces

58 units registered

Flat · 12 units2BHK · 32 units3BHK · 12 unitsRow house · 2 units
BuildingTypeCarpet areaUnits
Vaibhavi Height Block-AFlat39.78 sq m · 428 sq ft12
Vaibhavi Height Block B And C2BHK28.55 sq m · 307 sq ft12
Vaibhavi Height Block B And C2BHK53.46 sq m · 575 sq ft20
Vaibhavi Height Block B And C3BHK67.31 sq m · 725 sq ft12
Vaibhavi Height Block DRow house50.45 sq m · 543 sq ft2

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Vaibhavi Height Block-AClosed/Covered00001
Vaibhavi Height Block-AOpen Space00000
Vaibhavi Height Block B And CClosed/Covered00001
Vaibhavi Height Block B And COpen Space00000
Vaibhavi Height Block DClosed/Covered00000
Vaibhavi Height Block DOpen Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress4 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Vaibhavi Height Block-A

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Vaibhavi Height Block B And C

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Vaibhavi Height Block D

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsBOLDER SOLING100%
  • Water SupplyFROM BOREWELL100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)WILL BE DONE AT THE TIME OF COMPLETION100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingTREE PLANTATION ONLY100%
  • Street LightingLED LIGHTS ON WALL COMPOUND100%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRAIN WATER HR. WILL DONE AT THE TIME OF COMPLETION100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationELE. ROOM WILL BE DONE AT THE TIME OF COMPLETION100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDeepak Panakanti Pratibimb Design Consortium—
EngineerAnant Ashok Kapse—
EngineerKajal Bhandari—
OtherBaijnath Pal—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology