RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Completed
P50900008437
Vaibhavi Heights · Datala, Chandrapur · Yashpal Dewanand Khobragade
Promised for 30 Dec 2023; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 47
Show all 47 documents
OtherView
Title reportView
OtherView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
Allotment letterView
OtherView
OtherView
Orders 0
No MahaRERA order or list names this number.
Questions about P50900008437
Is Vaibhavi Heights delayed?
MahaRERA reports it completed. Its promised completion date was 30 Dec 2023.
How many extensions has it had?
Deedo holds 0 extension certificates for P50900008437.
Who is the promoter?
MahaRERA records Yashpal Dewanand Khobragade as the promoter of P50900008437.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50900008437.
Answers are generated from the record.
Data through23 Nov 2026, 01:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology