Makane, Palghar
Deedo IDDL-PAL-MAKANE9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects86
Registrations89some projects hold several
Completion still due5138 past their date
Median extension4 months64% of registrations extended
Regulatory cases2on 2 projects
9 in 10 registrations run late here
89 MahaRERA registrations in Makane
8 not yet due43 extended, not yet due38 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Makane
86 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Vastu Impressa B-WingPradeep Prabhakar Patil | Due Oct 2027, extended 4 mo | — | — |
| Shree Swami ApartmentBhoomi Avenue Developers | 5 mo late | — | — |
| Nakshatra ResidencyJsb Housing LLP | Completed | — | — |
| Ganesh ApartmentVishnu Govind Patil | Completed, extended 1 yr 1 mo | — | — |
| Nine Star PrideNine Home Realtors | Completed | — | 28% |
| Pride ApartmentFine Homes | 3 yrs late | — | — |
| Parivar ResidencyParivar Developers | Due Oct 2027, extended 4 mo | — | 60% |
| Om ResidencyOm Enterprises | 1 yr 8 mo late | — | — |
| Priti ChaayaRajlaxmi Developers | 3 yrs 5 mo late | — | 83% |
| Priti DarpanMs Rajlaxmi Developers | 4 yrs 4 mo late | — | 87% |
| Sadguru AarambhVisharia Sadguru Bhoomi LLP | Completed, extended 6 mo | — | 98% |
| Doha LifespaceDoha Lifespace Developers | Completed | — | 53% |
| Nine Star Pride 1 Building No 01Nine Home Developers | Completed | — | 49% |
| Nine Start Pride 1 Building No. 02Nine Home Developers | Completed | — | 37% |
| Excellence Residency 2Sai Excellence Realtors | Due Dec 2026, extended 2 yrs 5 mo | — | 84% |
| Sunshine ComplexAditi Developers | Due Jun 2027 | — | 92% |
| Mataji ComplexMataji Developers | Completed | — | 36% |
| Trinity GreensTrinity Housing Projects LLP | 2 yrs 11 mo late | — | — |
| Kanti Atharva Building No 3 And 4Mahavir Homemakers | Completed | — | 100% |
| Lifestyle ArcadeLifestyle Developers | Completed, extended 6 yrs 8 mo | — | 20% |
| Nine Star Residency - ImperiaA.K. Developers | Completed | — | — |
| Sai SiddhiDharmendra Singh Parihar | Completed, extended 3 yrs 3 mo | — | 58% |
| Kamdhenu FloraJay Bhawani Enterprises | 7 yrs 6 mo late | — | — |
| Nine Star Landmark Ph III Bldg 6 LOTUSNine Homemakers | Completed | — | — |
| Nine Star Landmark Ph-1 Blg-4 LILYNine Homemakers | Completed, extended 2 yrs | — | — |
Nearby: other villages in Palghar
Most active promoters
- Nine Homemakers12 projects
- Star Builders & Developers3 projects
- Star Builders & Developers3 projects
- Visharia Sadguru Bhoomi Llp3 projects
- Aditi Developers2 projects
- Fine Homes2 projects
- Nine Home Developers2 projects
- Vishnu Govind Patil2 projects
- Yogesh Bidye2 projects
- Zinal Builders And Developers2 projects
Makane, in questions
How many projects in Makane run late?
9 in 10 MahaRERA registrations (81 of 89): their completion date was extended or has passed, data through 5 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Makane by Deedo. Medians on fewer than 3 deeds are not shown.
Data through5 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology