Residential / Group Housing · 2 buildings · 21 unitsRERA P99000025229

Om Residency

Deedo IDDP-PAL-DZ3G

Completion was pushed back 1 year to Mar 2026, and that date has passed too; no MahaRERA orders on record; 95% of its units are booked.

Makane, Palghar 401102 · by Om Enterprises

Delivery1 yr 8 mo latePromised Mar 2025 · revised Mar 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales95% booked20 of 21 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 1 year to Mar 2026, and that date has passed too

  • This projectRegistered 23 Mar 2020, completion promised 30 Mar 2025, revised to 31 Mar 2026, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000025229
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900002522923 Mar 202030 Mar 202531 Mar 2026Om EnterprisesProject page
Documents98

3 documents held by Deedo, 95 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN Cardom ent pan card.pdf · uploaded 9 Feb 2020Source

Legal

  • Legal Title reporttitle search bldg no8 new.pdf · uploaded 9 Feb 2020Source
  • Declaration Form Bform b new.pdf · uploaded 9 Feb 2020Source
  • Declaration Form Bform b 500 new.pdf · uploaded 20 May 2025Source

Migrated

  • 1 PAN Cardom ent pan card.pdf · uploaded 9 Feb 2020Source
Show all 98 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reporttitle search bldg no8 new.pdf · uploaded 9 Feb 2020Source
  • 1 Details of encumbrancesencumbrance letter new.pdf · uploaded 9 Feb 2020Source
  • 1 Copy of Layout Approval (in case of layout)layout plan2.pdf · uploaded 9 Feb 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentbldg plan 2.pdf · uploaded 9 Feb 2020Source
  • 1 Declaration in FORM Bform b new.pdf · uploaded 9 Feb 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 architech certificate.pdf · uploaded 9 Feb 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificate.pdf · uploaded 9 Feb 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 ca certificate.pdf · uploaded 9 Feb 2020Source
  • 1 Proforma of Allotment letterdraft agreement n allotment.pdf · uploaded 10 Feb 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentcc copy updated1.pdf · uploaded 12 Mar 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)1April 2018 to march 31 2019 - converted.pdf · uploaded 6 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)April 2019 to march 2020 - converted.pdf · uploaded 6 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)April 2020 to march 2021 - converted.pdf · uploaded 6 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)April 2021 to march 22 - converted.pdf · uploaded 6 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)April 22 to march 23 - converted.pdf · uploaded 6 Mar 2024Source
  • 1 Declaration in FORM Bform b 500 new.pdf · uploaded 20 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 30062022.pdf · uploaded 20 May 2025Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31032025.pdf · uploaded 20 May 2025Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31122024.pdf · uploaded 20 May 2025Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30092024.pdf · uploaded 20 May 2025Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30062024.pdf · uploaded 20 May 2025Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 31032024.pdf · uploaded 20 May 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31122023.pdf · uploaded 20 May 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30092023.pdf · uploaded 20 May 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30062023.pdf · uploaded 20 May 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31032023.pdf · uploaded 20 May 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31122022.pdf · uploaded 20 May 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30092022.pdf · uploaded 20 May 2025Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)rinky gupta and company f3 31325.pdf · uploaded 20 May 2025Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)rinky gupta and company 311224 f3.pdf · uploaded 20 May 2025Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)rinky gupta and company 30924.pdf · uploaded 20 May 2025Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)rinky gupta and company 3062024.pdf · uploaded 20 May 2025Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)rinky gupta and company 31324.pdf · uploaded 20 May 2025Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)rinky gupta and company 311223.pdf · uploaded 20 May 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 rinky gupta and company 30623.pdf · uploaded 20 May 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 rinky gupta and company 3132023.pdf · uploaded 20 May 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 rinky gupta and company 31122022.pdf · uploaded 20 May 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)rinky gupta and company 3092022.pdf · uploaded 20 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)rinky gupta and company 30062022.pdf · uploaded 20 May 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)rinky gupta and company f3 3092023.pdf · uploaded 20 May 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30092023.pdf · uploaded 20 May 2025Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31032025.pdf · uploaded 20 May 2025Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31122024.pdf · uploaded 20 May 2025Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30062024.pdf · uploaded 20 May 2025Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31032024.pdf · uploaded 20 May 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31122023.pdf · uploaded 20 May 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30062023.pdf · uploaded 20 May 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31032023.pdf · uploaded 20 May 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31122022.pdf · uploaded 20 May 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30092022.pdf · uploaded 20 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30062022.pdf · uploaded 20 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)apirl to June 2022.pdf · uploaded 20 May 2025Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)july to sep 2022.pdf · uploaded 20 May 2025Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)oct to dec 2022.pdf · uploaded 20 May 2025Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2 jan to mar 2022.pdf · uploaded 20 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A 2023-24.pdf · uploaded 20 May 2025Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A 2024-25.pdf · uploaded 20 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate(2).pdf · uploaded 22 May 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 23-24.pdf · uploaded 22 May 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)form 5 24-25.pdf · uploaded 22 May 2025Source
  • 1 Disclosure of sold/ booked inventorysold unsold inventory om new.pdf · uploaded 1 Jul 2025View
  • 1 Declaration about Commencement CertificateFormat D om new.pdf · uploaded 1 Jul 2025Source

Technical

  • Documentlayout plan2.pdf · uploaded 9 Feb 2020Source
  • Documentbldg plan 2.pdf · uploaded 9 Feb 2020Source

Technical (Architect)

  • Documentform 1 architech certificate.pdf · uploaded 9 Feb 2020Source
  • Documentform 1 30062022.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 30092022.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 31122022.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 31032023.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 30062023.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 30092023.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 31122023.pdf · uploaded 20 May 2025Source
  • Documentform 1 31032024.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 30062024.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 30092024.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 31122024.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 31032025.pdf · uploaded 20 May 2025Source

Technical (Engineer)

  • Documentengineer certificate.pdf · uploaded 9 Feb 2020Source
  • DocumentFORM 2 30062022.pdf · uploaded 20 May 2025Source
  • DocumentFORM 2 30092022.pdf · uploaded 20 May 2025Source
  • DocumentFORM 2 31122022.pdf · uploaded 20 May 2025Source
  • DocumentFORM 2 31032023.pdf · uploaded 20 May 2025Source
  • DocumentFORM 2 30062023.pdf · uploaded 20 May 2025Source
  • DocumentFORM 2 30092023.pdf · uploaded 20 May 2025Source
  • DocumentFORM 2 31122023.pdf · uploaded 20 May 2025Source
  • DocumentFORM 2 31032024.pdf · uploaded 20 May 2025Source
  • DocumentFORM 2 30062024.pdf · uploaded 20 May 2025Source
  • DocumentFORM 2 31122024.pdf · uploaded 20 May 2025Source
  • DocumentFORM 2 31032025.pdf · uploaded 20 May 2025Source
  • DocumentEngineer Certificate(2).pdf · uploaded 22 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel GUT NO.224, GUT NO.226 HISSA NO.2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Address
Gut No.224, Gut No.226 Hissa No.2, Gut No.226 Hissa No.3, , Makane, Safale WestPIN 401102
Village
Makane, Palghar taluka
Land area for this project
1,016 sq m (10,934 sq ft)
Permissible built-up area
1,016 sq m (10,934 sq ft)
Sanctioned built-up area
1,016 sq m (10,934 sq ft)
Designated bank account
227
Developed in phases
No

Survey, CTS, gat or plot numbers

GUT NO.224GUT NO.226 HISSA NO.2GUT NO.226 HISSA NO.3

Land as published on MahaRERA's project page

GUT NO.224, GUT NO.226 HISSA NO.2, GUT NO.226 HISSA NO.3,

Boundaries

North
Adj Gut No 226pt At North
South
9 M Layout Road At South
East
Bldg No 9 At East
West
Adj Gut No226 At West

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectArchitect Roshan Patil And Associates—
Chartered accountantMishra Mayekar And Co—
Chartered accountantRinky Gupta And Company—
EngineerMahesh Kumar—

Source: MahaRERA project page. Contact details are not shown.