Skip to content
Residential / Group Housing · 1 building · 15 unitsRERA P99000022395

Priti Darpan

Deedo IDDP-PAL-S2J5

Its promised completion date, Jul 2022, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 87% of its units are booked.

Makane, Palghar 401102 · by Ms Rajlaxmi Developers

Delivery4 yrs 4 mo past duePromised Jul 2022 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales87% booked13 of 15 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Jul 2022, has passed and MahaRERA does not show it completed

  • This projectRegistered 19 Sep 2019, completion promised 31 Jul 2022, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000022395
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900002239519 Sep 201931 Jul 202231 Jul 2022Ms Rajlaxmi DevelopersProject page
Documents46

1 document held by Deedo, 45 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan card.pdf · uploaded 15 Jun 2019Source

Legal

  • Declaration Form BFORM B.pdf · uploaded 21 Jun 2019Source
  • Declaration Form BFORM B 2.pdf · uploaded 21 Jun 2019Source
  • Legal Title reportSEARCH.pdf · uploaded 4 Sep 2019Source
  • Legal Title reporttitle.pdf · uploaded 4 Sep 2019Source
  • OtherSOLD,BOOKED FLAT LIST.pdf · uploaded 5 Jul 2021Source

Migrated

  • 1 PAN Cardpan card.pdf · uploaded 15 Jun 2019Source
Show all 46 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesNO ENCRUMBANCES LETTER.pdf · uploaded 15 Jun 2019Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 15 Jun 2019Source
  • 1 Copy of Layout Approval (in case of layout)00000002.pdf · uploaded 21 Jun 2019Source
  • 1 Building Plan Approval (IOD)00000001.pdf · uploaded 21 Jun 2019Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 21 Jun 2019Source
  • 2 Declaration in FORM BFORM B 2.pdf · uploaded 21 Jun 2019Source
  • 1 Copy of the legal title reportSEARCH.pdf · uploaded 4 Sep 2019Source
  • 2 Copy of the legal title reporttitle.pdf · uploaded 4 Sep 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE FORM 3 PRITI DARPAN.pdf · uploaded 4 Sep 2019Source
  • 2 Proforma of Allotment letterdraft agreement priti darpan.pdf · uploaded 4 Sep 2019Source
  • 1 Commencement Certificates / NA Order for plotted development1.pdf · uploaded 16 Sep 2019Source
  • 2 Commencement Certificates / NA Order for plotted development2.pdf · uploaded 16 Sep 2019Source
  • 3 Commencement Certificates / NA Order for plotted development3.pdf · uploaded 16 Sep 2019Source
  • 4 Commencement Certificates / NA Order for plotted development4.pdf · uploaded 16 Sep 2019Source
  • 5 Commencement Certificates / NA Order for plotted development5.pdf · uploaded 16 Sep 2019Source
  • 6 Commencement Certificates / NA Order for plotted development6.pdf · uploaded 16 Sep 2019Source
  • 7 Commencement Certificates / NA Order for plotted development7.pdf · uploaded 16 Sep 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)BLDG No 20 architect certificate 1.pdf · uploaded 16 Sep 2019Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)BLDG No 20 architect certificate 2.pdf · uploaded 16 Sep 2019Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)BLDG No 20 architect certificate 3.pdf · uploaded 16 Sep 2019Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE ANNEXURE A.pdf · uploaded 16 Sep 2019Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)PRITI DARPAN 3032020 ARCHITECH LETTER.pdf · uploaded 22 Jul 2020Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)PRITI DARPAN CA 271019.pdf · uploaded 22 Jul 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Scan.pdf · uploaded 27 Jul 2020Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Scan2.pdf · uploaded 27 Jul 2020Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Scan3.pdf · uploaded 27 Jul 2020Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)priti darpan ca letter 27thjuly2020-compressed.pdf · uploaded 27 Jul 2020Source
  • 3 Proforma of Allotment letterPRITI DARPAN BLANK.pdf · uploaded 3 Sep 2020Source
  • 1 OtherSOLD,BOOKED FLAT LIST.pdf · uploaded 5 Jul 2021Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate of Priti Darpan .pdf · uploaded 1 Jun 2022Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate of Priti Darpan .pdf · uploaded 1 Jun 2022Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate of Priti Darpan.pdf · uploaded 1 Jun 2022Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer pd.pdf · uploaded 18 Jul 2022Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA PRITI DARPAN.pdf · uploaded 13 Aug 2022Source

Technical

  • Document00000001.pdf · uploaded 21 Jun 2019Source
  • Document00000002.pdf · uploaded 21 Jun 2019Source

Technical (Architect)

  • DocumentArchitect Certificate of Priti Darpan .pdf · uploaded 1 Jun 2022Source

Technical (Engineer)

  • Documentengineer pd.pdf · uploaded 18 Jul 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel G NO 224, GUT NO 226/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK15 units in all
Address
G No 224, Gut No 226/2, Gut No 226/3, Makane Virathan Road, Central ParkPIN 401102
Village
Makane, Palghar taluka
Land area for this project
497 sq m (5,354 sq ft)
Permissible built-up area
523 sq m (5,632 sq ft)
Sanctioned built-up area
523 sq m (5,632 sq ft)
Designated bank account
203
Developed in phases
No

Survey, CTS, gat or plot numbers

G NO 224GUT NO 226/2GUT NO 226/3

Land as published on MahaRERA's project page

G NO 224,GUT NO 226/2, GUT NO 226/3

Boundaries

North
Adj G No 230
South
Building No 19
East
15 Mt Wide Road
West
G No 227

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking15 units

13 of 15 units booked (87%), as the promoter reported to MahaRERA

1BHK · 15 units
TypeCarpet areaUnitsBooked
1BHK25.65 sq m · 276 sq ft54
1BHK25.94 sq m · 279 sq ft109

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals8

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectArchitectroshan Patil And Associates—
Chartered accountantDarshan B Raut And Associates—
EngineerJay Shree Krishna Consulting Engg—
OtherDhiraj Chovatiya—
Registered real estate agentBapu Shivaji Kendle—
Registered real estate agentHasmukh Kuverji Dedhia—
Registered real estate agentJitendra Narayanlal Rawal—
Registered real estate agentMoses Thomas Nadar—

Source: MahaRERA project page. Contact details are not shown.