Makane, Palghar
Deedo IDDL-PAL-MAKANE9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects86
Registrations89some projects hold several
Completion still due5138 past their date
Median extension4 months64% of registrations extended
Regulatory cases2on 2 projects
9 in 10 registrations run late here
89 MahaRERA registrations in Makane
8 not yet due43 extended, not yet due38 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Makane
86 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Nine Star Landmark Ph II Bldg-2 ORCHIDNine Homemakers | Completed | — | — |
| Nine Star Landmark Ph II Bldg-7 DAISYNine Homemakers | Completed | — | — |
| Nine Star Landmark Ph I Bldg-3 IRISNine Homemakers | Completed, extended 2 yrs | — | — |
| Nine Star Residency KritikaYogesh Bidye | Completed | — | 7% |
| Nine Star Landmark Ph-I Bldg-1 ASTERNine Homemakers | Completed, extended 2 yrs | — | — |
| Nine Star Residency RevatiNine Lifespace Developers | Completed | — | 58% |
| VishakaKrisha Lifespace Developers | Completed | — | 60% |
| Nine Star Residency PhalguniKrisha Constructions | Completed | — | 84% |
| Nine Star Residency PurvaSai Mudraa Construction | Completed | — | 40% |
| Nine Star Residency Rohini BuildingTrinity Concrete Structures Private Limited | Completed, extended 4 yrs | — | 22% |
| Nine Star Landmark Phase III Bldg-5 TULIPNine Homemakers | Completed | — | — |
Nearby: other villages in Palghar
Most active promoters
- Nine Homemakers12 projects
- Star Builders & Developers3 projects
- Star Builders & Developers3 projects
- Visharia Sadguru Bhoomi Llp3 projects
- Aditi Developers2 projects
- Fine Homes2 projects
- Nine Home Developers2 projects
- Vishnu Govind Patil2 projects
- Yogesh Bidye2 projects
- Zinal Builders And Developers2 projects
Makane, in questions
How many projects in Makane run late?
9 in 10 MahaRERA registrations (81 of 89): their completion date was extended or has passed, data through 5 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Makane by Deedo. Medians on fewer than 3 deeds are not shown.
Data through5 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology