Delayed projects in Raigarh

1,042 MahaRERA projects in Raigarh are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 3 of 21.

ProjectLocalityPromisedRevisedDelivery
Panvelkar Swarajya Phase-IPanvelkar Infrastructures Private LimitedKolhiwaliDec 2019Dec 20216 yrs 11 mo late
Sai Shanti ApartmentSanjyoth EnterprisesAsudgaonDec 2019Dec 20196 yrs 11 mo late
Shree Ganesh ApartmentsRajesh Kanha MhatreChinchvali GoheDec 2019Dec 20196 yrs 11 mo late
Shree Krupa Banubai ParkChandrakant Anant MhatreBokadviraDec 2019Dec 20196 yrs 11 mo late
Shree Krupa Chahu PrideChandrakant Anant MhatreBokadviraDec 2019Dec 20226 yrs 11 mo late
Shree SadanSupcon Developers Private LimitedUlaweDec 2019Dec 20196 yrs 11 mo late
Shrinath PrideDharmendrakumar Jayprakash MishraBhuwaneshwar (Ct)Dec 2019Dec 20196 yrs 11 mo late
Saurabh ResidencyAshiana Builders & DevelopersUkrulDec 2019Jun 20266 yrs 11 mo late
Tulip ApartmentMukesh Shrinath SharmaVadghar (Ct)Dec 2019Dec 20196 yrs 11 mo late
Thakur GalaxyMatyagayandra SinghUlaweDec 2019Dec 20196 yrs 11 mo late
Vastuvihar Residency - Building 6 - LilacDhanji Kheta SandhaWadgharDec 2019Dec 20196 yrs 11 mo late
The EmeraldRajesh Ramchandra KoliUlaweJan 2020Jan 20216 yrs 10 mo late
Anandi HeightsMarvel BuildconUlaweMar 2020Nov 20246 yrs 8 mo late
Decent ApartmentDecent Builders & DevelopersMamdapurApr 2020Apr 20226 yrs 7 mo late
Sai Shradha ResidencySumeet Chandrakant PatilVadghar (Ct)Sep 2020Sep 20206 yrs 2 mo late
Ashoka ResidencyKalbhairav EnterprisesKaranjadeSep 2020Sep 20206 yrs 2 mo late
AvhniAaum ConstructionsUranSep 2020Mar 20226 yrs 2 mo late
Cosmos ApartmentTushar Ramchandra PatilVadghar (Ct)Sep 2020Dec 20256 yrs 2 mo late
Dhawalgiri ApartmentDesire Homes DevelopersPushapakSep 2020Sep 20206 yrs 2 mo late
Ekvira VishwaOrbit Builders & DevelopersPen (M Cl)Sep 2020Sep 20206 yrs 2 mo late
Mahalaxmi EnclaveMahalaxmi EnterprisesDhamoteSep 2020Mar 20226 yrs 2 mo late
Maple IvyPankti Jignesh GoradiaUlaweSep 2020Dec 20226 yrs 2 mo late
Nilgiri ApartmentDesire Homes DevelopersVadghar (Ct)Sep 2020Sep 20236 yrs 2 mo late
Prabhu DevShree Sai Builders And DevelopersUlaweSep 2020Sep 20206 yrs 2 mo late
Sai - AarambhSai Shraddha Builders & DevelopersPenSep 2020Nov 20236 yrs 2 mo late
Savitri Mangal TowerSavitri Builders and DevelopersPushapakSep 2020Mar 20226 yrs 2 mo late
Shree Ganesh PlazaPratik ArjunConstruction And CompanyVadghar (Ct)Sep 2020Sep 20206 yrs 2 mo late
Shree SamarthRamdas Alya MundkarVadghar (Ct)Sep 2020Sep 20206 yrs 2 mo late
V VastuAtharva DevelopersVadghar (Ct)Sep 2020Mar 20226 yrs 2 mo late
Venus AlpineVenus Sublimes Private LimitedKhargharSep 2020Sep 20206 yrs 2 mo late
Sai MannatBhushan Bhalchandra MhatreVadghar (Ct)Oct 2020Dec 20236 yrs 1 mo late
Siddhagiri ResidencySs EngineeringUlaweNov 2020Dec 20246 yrs late
R K WonderMohammad Rashid Abdul Qayyum KhanChinchvali GoheNov 2020Mar 20256 yrs late
LotusSwasti InfraZiradNov 2020Nov 20206 yrs late
Paramount HeightMahir Builders And DevelopersTaloje PanchnadNov 2020Nov 20206 yrs late
Sai SagarSanjay Mahendra SinghNeralNov 2020Nov 20206 yrs late
Shree Samarth ResidencyShree Samarth Infra DevelopersPashaneNov 2020May 20236 yrs late
V AawasAtharva DevelopersKaranjadeNov 2020May 20226 yrs late
V AmberAtharva DevelopersVadghar (Ct)Nov 2020May 20226 yrs late
V NiwasAtharva DevelopersVadghar (Ct)Nov 2020May 20226 yrs late
sahil manzils.s.m.developerTaloje PanchnadDec 2020Dec 20205 yrs 11 mo late
Aishwarya AppartmentGlamour BuildersKhanda ColonyDec 2020Dec 20205 yrs 11 mo late
Avdhoot ResidencyVinayak DevelopersKoparDec 2020Jun 20225 yrs 11 mo late
Anand Nagar Phase 3Anubhavshri Realty Pvt. Ltd.LonereDec 2020—5 yrs 11 mo late
Ramsai Apartment - B WingJaved Latif HajiMahadDec 2020Jun 20225 yrs 11 mo late
Shree Samarth KrupaSulochana Vasudev PatilUlaweDec 2020Jun 20225 yrs 11 mo late
Saanvi ResidencySPH Builders & DevelopersPalidevadDec 2020Dec 20205 yrs 11 mo late
Satyam PlazaSeven HeavenVadghar (Ct)Dec 2020Dec 20205 yrs 11 mo late
Shivam PlazaSeven HeavenVadghar (Ct)Dec 2020Jun 20225 yrs 11 mo late
The CrystalSantosh Anant SomaseUlaweDec 2020Dec 20205 yrs 11 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology