Mharal, Thane

Deedo IDDL-THN-MHARAL

10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects10
Registrations10
Completion still due91 past their date
Median extension4 months90% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

10 MahaRERA registrations in Mharal

9 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Mharal

10 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Vishwajeet Town Phase IIGbk Group LLPDue Aug 2030, extended 4 mo——
Precious Avalon Phase-1Vinayak AssociatesDue Apr 2030, extended 4 mo——
Mahadev HeightsOnbv RealityDue Apr 2027, extended 4 mo——
Precious Meadows NxRadhe Krishna DevelopersDue Oct 2027, extended 4 mo—19%
Mahadev EnclavesMahadev EnclavesDue Jul 2028, extended 4 mo—6%
All 10 projects →
Mharal market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Vinayak Associates2 projects
  2. Anil Hardasmal Tharwani1 project
  3. Gbk Group LLP1 project
  4. Kedar Construction1 project
  5. Mahadev Enclaves1 project
  6. Onbv Reality1 project
  7. Radhe Krishna Developers1 project
  8. Siddhivinayak Builders And Developers1 project
  9. Sunil Purshottam Deshmukh1 project

Mharal, in questions

How many projects in Mharal run late?

10 in 10 MahaRERA registrations (10 of 10): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Mharal by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology