Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.

Mharal, Thane 421103 · by Onbv Reality

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 63 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 25 Jun 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700076750
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170007675025 Jun 202431 Dec 202630 Apr 2027Onbv RealityProject page
Documents64

1 document held by Deedo, 63 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFirm PAN (1).pdf · uploaded 22 May 2024Source

Legal

  • Declaration Form BForm B Partners.pdf · uploaded 16 May 2024Source
  • Other – Legaldeed.pdf · uploaded 4 Jun 2024Source
  • Legal Title reportOnbv Title merged_compressed.pdf · uploaded 14 Jun 2024Source

Migrated

  • 1 Declaration in FORM BForm B Partners.pdf · uploaded 16 May 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 16 May 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 16 May 2024Source
Show all 64 documentsShow fewer documents

Migrated

  • 1 Disclosure of Interest in Other Real Estate OrganizationsInterest Declaration Varsha.pdf · uploaded 16 May 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsInterest Declaration Sanjay.pdf · uploaded 16 May 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsInterest Declaration rupesh.pdf · uploaded 16 May 2024Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsInterest Declaration narendra.pdf · uploaded 16 May 2024Source
  • 1 Copy of Layout Approval (in case of layout)Plan 1_11zon_merged.pdf · uploaded 21 May 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan.pdf · uploaded 21 May 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC_11zon.pdf · uploaded 21 May 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Ca certificate.pdf · uploaded 21 May 2024Source
  • 1 PAN CardFirm PAN (1).pdf · uploaded 22 May 2024Source
  • 1 a Details of encumbrances concerned to FinanceLegal.pdf · uploaded 22 May 2024Source
  • 1 b Details of encumbrances concerned to LegalLegal.pdf · uploaded 22 May 2024Source
  • 1 Declaration about Commencement CertificateCommencement Declaration2 (2).pdf · uploaded 22 May 2024Source
  • 1 CERSAI detailsCERSAI CERTIFICATE.pdf · uploaded 22 May 2024Source
  • 1 Proforma of Agreement for saleAgreement for sale (3).pdf · uploaded 22 May 2024Source
  • 1 Proforma of Allotment letterAlottment Letter.pdf · uploaded 22 May 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Letter (3).pdf · uploaded 22 May 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation 2 (3).pdf · uploaded 22 May 2024Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation 1 (2).pdf · uploaded 22 May 2024Source
  • 1 Other – Legaldeed.pdf · uploaded 4 Jun 2024Source
  • 1 Other – Technicaldeclration Letter of Undertaking.pdf · uploaded 4 Jun 2024Source
  • 2 Other – TechnicalCC MAIL.pdf · uploaded 4 Jun 2024Source
  • 1 Copy of the legal title reportOnbv Title merged_compressed.pdf · uploaded 14 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect.pdf · uploaded 19 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 (1).pdf · uploaded 19 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer.pdf · uploaded 19 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 ARH.pdf · uploaded 7 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Onbv Reality Form CA.pdf · uploaded 7 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 7 May 2025Source
  • Form 1Form 1 Signed.pdf · uploaded 20 Jul 2025Source
  • Form 2Form 2 Signed.pdf · uploaded 20 Jul 2025Source
  • Form 3Ca.pdf · uploaded 20 Jul 2025Source
  • Disclosure of Sold and Booked InventoryOnbv.pdf · uploaded 20 Jul 2025Source
  • Form 5 (FY 2024-2025)Onbv Form 5.pdf · uploaded 19 Sep 2025Source
  • Withdrawal Update Form 1Form 1 signed Onbv.pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 2Form 2 signed Onbv.pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 3ONBV CA FINAL - 2 (1) (1).pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 26 Mar 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 26 Mar 2026Source
  • Withdrawal Update Form 3Form 3 merged.pdf · uploaded 26 Mar 2026Source
  • Withdrawal Update Form 1Form 1 signed.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 2Form 2 signed.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 3form 3 merged.pdf · uploaded 16 May 2026Source
  • Form 5 (FY 2025-2026)onbv reality Form singned.pdf · uploaded 28 Sep 2026Source
  • Withdrawal Update Form 1Form 1 June 2026 ONBV.pdf · uploaded 13 Oct 2026Source
  • Withdrawal Update Form 2Form 2 June 2026 ONBV.pdf · uploaded 13 Oct 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 13 Oct 2026Source

Technical

  • DocumentPlan 1_11zon_merged.pdf · uploaded 21 May 2024Source
  • DocumentPlan.pdf · uploaded 21 May 2024Source
  • Other – Technicaldeclration Letter of Undertaking.pdf · uploaded 4 Jun 2024Source
  • Other – TechnicalCC MAIL.pdf · uploaded 4 Jun 2024Source

Technical (Architect)

  • DocumentArchitect.pdf · uploaded 19 Jan 2025Source
  • DocumentForm 1 ARH.pdf · uploaded 7 May 2025Source
  • DocumentForm 1 June 2026 ONBV.pdf · uploaded 13 Oct 2026Source

Technical (Engineer)

  • DocumentEngineer.pdf · uploaded 19 Jan 2025Source
  • DocumentFORM 2.pdf · uploaded 7 May 2025Source
  • DocumentForm 2 June 2026 ONBV.pdf · uploaded 13 Oct 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S. NO. 1/3/B/1, S.NO. 1/3/B/11

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, LANDOWNER 1BHK, LANDOWNER 2BHK63 units in all
Address
S. No. 1/3/B/1 & S.no. 1/3/B/11, Mharal, MharalPIN 421103
Village
mharal, Kalyan taluka
Land area for this project
2,100 sq m (22,604 sq ft)
Permissible built-up area
4,043 sq m (43,518 sq ft)
Sanctioned built-up area
4,043 sq m (43,518 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

S. NO. 1/3/B/1S.NO. 1/3/B/11

Land as published on MahaRERA's project page

S. NO. 1/3/B/1 & S.NO. 1/3/B/11

Boundaries

North
Building
South
Building
East
Building
West
Building

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking63 units

0 of 63 units booked (0%), as the promoter reported to MahaRERA

1BHK · 20 units2BHK · 15 unitsLANDOWNER 1BHK · 15 unitsLANDOWNER 2BHK · 13 units
TypeCarpet areaUnitsBooked
1BHK35.93 sq m · 387 sq ft20
1BHK38.6 sq m · 415 sq ft60
1BHK38.8 sq m · 418 sq ft10
1BHK38.9 sq m · 419 sq ft110
2BHK47.17 sq m · 508 sq ft50
2BHK47.92 sq m · 516 sq ft30
2BHK50.05 sq m · 539 sq ft60
2BHK51.38 sq m · 553 sq ft10
Show all 16 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
LANDOWNER 1BHK35.93 sq m · 387 sq ft50
LANDOWNER 1BHK38.6 sq m · 415 sq ft10
LANDOWNER 1BHK38.8 sq m · 418 sq ft60
LANDOWNER 1BHK38.9 sq m · 419 sq ft30
LANDOWNER 2BHK47.17 sq m · 508 sq ft20
LANDOWNER 2BHK47.92 sq m · 516 sq ft40
LANDOWNER 2BHK50.05 sq m · 539 sq ft10
LANDOWNER 2BHK51.38 sq m · 553 sq ft60

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKaranjali Arch—
Chartered accountantGirish Tarwani—
Chartered accountantVinesh Ahuja—
EngineerTalreja And Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology