Kamba, Thane
Deedo IDDL-THN-KAMBA10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects5
Registrations5
Completion still due41 past their date
Median extension4 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
5 MahaRERA registrations in Kamba
4 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Kamba
5 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Nest ParadiseNest Developers | Due Dec 2028, extended 4 mo | — | 36% |
| Sweet Home LuxuriaAlbin Anthony Cheyaden | Due Oct 2028, extended 4 mo | — | 11% |
| Saptshrungi DevelopersSaptshrungi Developers | Due Jul 2028, extended 4 mo | — | 5% |
| Albin DevelopersAlbin Anthony Cheyaden | 2 yrs 5 mo late | — | 91% |
| Green ValleyM S Developers | Due Dec 2027, extended 4 yrs | — | — |
Nearby: other villages in Kalyan
Most active promoters
- Albin Anthony Cheyaden1 project
- Albin Anthony Cheyaden1 project
- M S Developers1 project
- Nest Developers1 project
- Saptshrungi Developers1 project
Kamba, in questions
How many projects in Kamba run late?
10 in 10 MahaRERA registrations (5 of 5): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kamba by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology