Albin Developers
Deedo IDDP-THN-7NH5Completion was pushed back 1 year to Jun 2025, and that date has passed too; no MahaRERA orders on record; 91% of its units are booked.
Kamba, Thane 421306 · by Albin Anthony Cheyaden
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year to Jun 2025, and that date has passed too
- This projectRegistered 20 Sep 2021, completion promised 15 Jun 2024, revised to 15 Jun 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700030834
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700030834 | 20 Sep 2021 | 15 Jun 2024 | 15 Jun 2025 | Albin Anthony Cheyaden | Project page |
Documents96
3 documents held by Deedo, 93 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN Card1PAN CARD.pdf · uploaded 12 Jul 2021Source
Legal
Migrated
- 1 PAN Card1PAN CARD.pdf · uploaded 12 Jul 2021Source
Show all 96 documentsShow fewer documents
Migrated
- 1 Copy of the legal title report2FORMAT A LEGAL TITAL REPORT.pdf · uploaded 12 Jul 2021Source
- 1 Details of encumbrances3No encubersement certificate.pdf · uploaded 12 Jul 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCONSTRUCTION APPORVAL_compressed.pdf · uploaded 12 Jul 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)9FORM 1 ARCHITECH CERTIFICATE.pdf · uploaded 12 Jul 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)10FORM 2 Engineer.pdf · uploaded 12 Jul 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)11FORM 3 FINAL.pdf · uploaded 12 Jul 2021Source
- 1 Proforma of Allotment letter19DRAFT sale AGREEMENT.pdf · uploaded 12 Jul 2021Source
- 1 Copy of Layout Approval (in case of layout)4COPY OF LAYOUT.pdf · uploaded 18 Sep 2021Source
- 1 Building Plan Approval / NA Order for plotted development5BUILDING LAYOUT.pdf · uploaded 18 Sep 2021Source
- 1 Declaration about Commencement Certificate6Declaration about commencement certificate format D.pdf · uploaded 18 Sep 2021Source
- 1 Declaration in FORM B8Declaration in FORM B.pdf · uploaded 18 Sep 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 11 Feb 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SH.pdf · uploaded 11 Feb 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 signed.pdf · uploaded 11 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 FINAL.pdf · uploaded 11 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 FINAL.pdf · uploaded 11 Feb 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect- Annexure A 31-Mar-2023.pdf · uploaded 23 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Annexure A 31-Dec-2022.pdf · uploaded 23 Oct 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect- Annexure A 30-Sep-2022.pdf · uploaded 23 Oct 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Annexure A 30-June-2022.pdf · uploaded 23 Oct 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 23 Oct 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 23 Oct 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 23 Oct 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 23 Oct 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q4 23-24 SIGNED.pdf · uploaded 23 Oct 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Q2-2024-25 SIGNED.pdf · uploaded 23 Oct 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Q1-2024-25 SIGNED.pdf · uploaded 23 Oct 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q3 23-24 SIGNED.pdf · uploaded 23 Oct 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q2 23-24 SIGNED.pdf · uploaded 23 Oct 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q1 22-23 SIGNED.pdf · uploaded 23 Oct 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q2 22-23 SIGNED.pdf · uploaded 23 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q3 22-23 SIGNED.pdf · uploaded 23 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q4 22-23 SIGNED.pdf · uploaded 23 Oct 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q1 -2023-24.pdf · uploaded 23 Oct 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Q2 -2023-24 SH.pdf · uploaded 23 Oct 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Q4 -2023-24 SH.pdf · uploaded 23 Oct 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Q3 -2023-24 SH.pdf · uploaded 23 Oct 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Q1 -2023-24 SH.pdf · uploaded 23 Oct 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Q1 -2022-23 SH.pdf · uploaded 23 Oct 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Q2 -2022-23 SH.pdf · uploaded 23 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Q3 -2022-23 SH.pdf · uploaded 23 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Q4 -2022-23 SH.pdf · uploaded 23 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryPro Disclosuresigned.pdf · uploaded 23 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Audit Report-Signed.pdf · uploaded 23 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Audit Report- 2023-24-signed.pdf · uploaded 24 Oct 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect.pdf · uploaded 26 Oct 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect.pdf · uploaded 26 Oct 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer.pdf · uploaded 26 Oct 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer.pdf · uploaded 26 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A - ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE_31 MARCH 2023.pdf · uploaded 26 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A - ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE_31 MARCH 2024.pdf · uploaded 26 Oct 2024Source
- 1 Declaration in FORM Bnotarised Form B.pdf · uploaded 7 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 23 Jun 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 23 Jun 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q3 Sweet home.pdf · uploaded 23 Jun 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q4 Sweet home.pdf · uploaded 23 Jun 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 23 Jun 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 23 Jun 2025Source
- 1 Disclosure of sold/ booked inventoryPro Disclosure.pdf · uploaded 23 Jun 2025View
- 2 Disclosure of sold/ booked inventoryPro Disclosure.pdf · uploaded 23 Jun 2025View
Technical
Technical (Architect)
- DocumentForm 1.pdf · uploaded 11 Feb 2023Source
- DocumentArchitect- Annexure A 31-Mar-2023.pdf · uploaded 23 Oct 2024Source
- DocumentAnnexure A 31-Dec-2022.pdf · uploaded 23 Oct 2024Source
- DocumentArchitect- Annexure A 30-Sep-2022.pdf · uploaded 23 Oct 2024Source
- DocumentAnnexure A 30-June-2022.pdf · uploaded 23 Oct 2024Source
- DocumentArchitect certificate.pdf · uploaded 23 Oct 2024Source
- DocumentArchitect certificate.pdf · uploaded 23 Oct 2024Source
- DocumentArchitect certificate.pdf · uploaded 23 Oct 2024Source
- DocumentArchitect certificate.pdf · uploaded 23 Oct 2024Source
- Documentarchitect.pdf · uploaded 26 Oct 2024Source
- DocumentArchitect.pdf · uploaded 26 Oct 2024Source
- DocumentArchitect Certificate.pdf · uploaded 23 Jun 2025Source
- DocumentArchitect Certificate.pdf · uploaded 23 Jun 2025Source
Technical (Engineer)
- DocumentFORM 2 SH.pdf · uploaded 11 Feb 2023Source
- DocumentEngineer Q4 -2022-23 SH.pdf · uploaded 23 Oct 2024Source
- DocumentEngineer Q3 -2022-23 SH.pdf · uploaded 23 Oct 2024Source
- DocumentEngineer Q2 -2022-23 SH.pdf · uploaded 23 Oct 2024Source
- DocumentEngineer Q1 -2022-23 SH.pdf · uploaded 23 Oct 2024Source
- DocumentEngineer Q1 -2023-24 SH.pdf · uploaded 23 Oct 2024Source
- DocumentEngineer Q2 -2023-24 SH.pdf · uploaded 23 Oct 2024Source
- DocumentEngineer Q3 -2023-24 SH.pdf · uploaded 23 Oct 2024Source
- DocumentEngineer Q4 -2023-24 SH.pdf · uploaded 23 Oct 2024Source
- Documentengineer.pdf · uploaded 26 Oct 2024Source
- DocumentEngineer.pdf · uploaded 26 Oct 2024Source
- DocumentEngineer Certificate.pdf · uploaded 23 Jun 2025Source
- DocumentEngineer Certificate.pdf · uploaded 23 Jun 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 102 H NO 4
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop90 units in all
- Address
- 102 H No 4, Kamba Road, KambaPIN 421306
- Village
- Kamba, Kalyan taluka
- Location
- 19.28730, 73.25180
- Land area for this project
- 3,350 sq m (36,059 sq ft)
- Permissible built-up area
- 3,036 sq m (32,683 sq ft)
- Sanctioned built-up area
- 3,036 sq m (32,683 sq ft)
- Designated bank account
- 66
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
102 H NO 4
Boundaries
- North
- Greenfileld India Heavy Febricators
- South
- St Charles Home Senior Citizens
- East
- Road
- West
- Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking90 units
82 of 90 units booked (91%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 29.56 sq m · 318 sq ft | 4 | 4 |
| 1BHK | 29.89 sq m · 322 sq ft | 4 | 4 |
| 1BHK | 29.98 sq m · 323 sq ft | 30 | 29 |
| 1BHK | 30.56 sq m · 329 sq ft | 6 | 5 |
| 1BHK | 30.59 sq m · 329 sq ft | 2 | 2 |
| 1BHK | 32.69 sq m · 352 sq ft | 2 | 1 |
| 1BHK | 33.28 sq m · 358 sq ft | 2 | 1 |
| 1BHK | 33.89 sq m · 365 sq ft | 1 | 0 |
Show all 24 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 45.49 sq m · 490 sq ft | 4 | 4 |
| 2BHK | 45.72 sq m · 492 sq ft | 12 | 12 |
| 2BHK | 50.07 sq m · 539 sq ft | 2 | 2 |
| Shop | 12.91 sq m · 139 sq ft | 1 | 1 |
| Shop | 13.55 sq m · 146 sq ft | 3 | 2 |
| Shop | 13.83 sq m · 149 sq ft | 1 | 1 |
| Shop | 14.45 sq m · 156 sq ft | 1 | 1 |
| Shop | 14.53 sq m · 156 sq ft | 2 | 2 |
| Shop | 15.25 sq m · 164 sq ft | 3 | 3 |
| Shop | 15.63 sq m · 168 sq ft | 1 | 1 |
| Shop | 15.9 sq m · 171 sq ft | 1 | 1 |
| Shop | 17.29 sq m · 186 sq ft | 2 | 1 |
| Shop | 18.65 sq m · 201 sq ft | 2 | 2 |
| Shop | 20.69 sq m · 223 sq ft | 1 | 1 |
| Shop | 25.04 sq m · 270 sq ft | 1 | 1 |
| Shop | 26.81 sq m · 289 sq ft | 2 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Other projects in Kamba
- Nest ParadiseRERA P51700053453
- Sweet Home LuxuriaRERA P51700053303
- Saptshrungi DevelopersRERA P51700050874
- Green ValleyRERA P51700017701
All 5 projects in Kamba · Compare Albin Developers with another project