Dombivli, Thane
Deedo IDDL-THN-DOMBIVLI5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects406
Registrations414some projects hold several
Completion still due189225 past their date
Median extension4 months50% of registrations extended
Regulatory cases21on 3 projects
9 in 10 registrations run late here
414 MahaRERA registrations in Dombivli
7 completed46 not yet due143 extended, not yet due218 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Dombivli
406 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Bhargav Co-Op Housing Society LimitedNilpadma Homes | Due Dec 2030 | — | — |
| The MeadowsPriism Infraa | Due Aug 2029 | — | — |
| Om Ganesh PujaBrahmand Lifespaces | Due Feb 2028 | — | — |
| Aditya Darshan ChsOm Swaminarayan Infra | Due Mar 2031 | — | — |
| Sajan Shantaram KrupaTirupati Developers | Due Dec 2030 | — | 0% |
| Jay Annapurna Co Operative Housing Society LtdS M Enterprises | Due Dec 2027 | — | 0% |
| Ram JankiFore Holdings | Due Apr 2028 | — | — |
| AsteriaAariv Buildcon | Due Mar 2028 | — | — |
| Krishna KunjKrishna Kunj Developers | Due Mar 2028 | — | — |
| The Identity - IndiraSaish Intech | Due Feb 2028 | — | 0% |
| Kulswamini Brahmand Wing B Janai ShankarKulswamini Builders & Developers | Due Dec 2030 | — | 0% |
| Shree Omkar Co-Operative Housing Society LTDSankalp Developers | Due Jun 2027 | — | 0% |
| Pralhad Sakar ArcadeSakar Developers | Due Jun 2027 | — | 0% |
| Amber EleganceAmber Enterprises | Due Dec 2028 | — | — |
| Patels PearlPramukh Developers | Due Oct 2026 | — | — |
| Ashokas EmpireAshokas Empire | Due Dec 2026 | — | — |
| H R HeightsJay Ashapura Developers | Due Apr 2027 | — | — |
| Gangubai HeightVinayak Construction | Due Dec 2026 | — | — |
| Gajanan PrideBalaji Infra | Due Dec 2027 | — | — |
| Swaminarayan City Phase 1DSwaminarayan Life Space LLP | Due Dec 2030 | — | — |
| Om Shiv Ganesh Co Operative Housing Society LtdImpressions Nxt | Due Mar 2027 | — | 0% |
| Trinity - Shashank SaptshrungRadhika Construction Company | Due Aug 2028 | — | — |
| Shivleela Co. Op. Hsg. Society. Ltd.Yogiraj Skyline | Due Dec 2026 | — | — |
| Ravichandra Chs ProposedSplendor Shelters Private Limited | Due Sep 2027 | — | — |
| Ashtavinayak DarshanYashashree Construction | Due Aug 2028 | — | 0% |
Nearby: other localities in Kalyan
Most active promoters
- Bhalchandra Wadnerkar5 projects
- Runwal Residency Private Limited5 projects
- Swaminarayan Life Space LLP5 projects
- Fore Holdings4 projects
- Impressions4 projects
- Impressions Nxt4 projects
- Neelpadma Associates4 projects
- Splendor Shelters Pvt Ltd4 projects
- Horizon Projects Pvt Ltd3 projects
- Narendra Kalyanji Patel3 projects
Data through27 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology