RERA projects in Barave

5 projects under 5 MahaRERA registrations, registered 2021–2026. None has an extended completion date on record.

Locality
5RERA projects
5Registrations
5Completion still due0 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20211
20220
20232
20241
20250
20261

Projects in Barave

5 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Rm SolitaireShiv Shakti InfraPR13300026017954 Sep 202631 Dec 2029—Not yet due0
Precious Villas by RM | ParijasRM BuildconP5170005617316 May 202431 Dec 2030—Not yet due0
Cross WindVg InfraP5170005196013 Jul 202330 Jun 2028—Not yet due0
Gnp LandmarkGnp LandmarkP517000498956 Mar 202331 Jan 2027—Not yet due0
Midtown Twin TowersShirdi Sai Sheltors LLPP5170003195129 Nov 202124 Nov 202624 Nov 2026Not yet due0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Gnp Landmark1 project
  2. RM Buildcon1 project
  3. Shirdi Sai Sheltors LLP1 project
  4. Shiv Shakti Infra1 project
  5. Vg Infra1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology