9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects10
Registrations10
Completion still due91 past their date
Median extension4 months80% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

10 MahaRERA registrations in Adivali

1 not yet due8 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Adivali

10 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Olympia City Phase 1Balaji Rattan LifespacesDue Jul 2031——
The Vaidiki AarambhShree Jari Mari Builders And DevelopersDue Apr 2031, extended 4 mo——
Seasons Sahara Nano Building No. CSamarth Sai Builders & DevelopersDue Oct 2028, extended 4 mo——
Season Sahara Building No -6Samarth Sai Builders & DevelopersDue Apr 2027, extended 4 mo——
Seasons Sahara Building No. 1Samarth Sai Builders & DevelopersDue Apr 2029, extended 4 mo——
SEASONS SAHARA NANO BUILDING NO A and BSamarth Sai Builders & DevelopersDue Apr 2027, extended 4 mo—32%
The Vaidiki Signature - C WingShree Jari Mari Developers LLPDue Apr 2028, extended 4 mo—20%
Shivom LakesideShivom Builders And DevelopersDue Apr 2029, extended 4 mo——
The Vaidiki Signature - A WingShree Jari Mari Developers LLP11 mo late—93%
The Vaidiki Signature - B WingShree Jari Mari Developers LLPDue Apr 2027, extended 4 mo—90%
Adivali market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Samarth Sai Builders & Developers4 projects
  2. Shree Jari Mari Developers Llp3 projects
  3. Balaji Rattan Lifespaces1 project
  4. Ganesh Deepak Shinde1 project
  5. Shivom Builders And Developers1 project
  6. Shree Jari Mari Builders And Developers1 project

Adivali, in questions

How many projects in Adivali run late?

9 in 10 MahaRERA registrations (9 of 10): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Adivali by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology