RERA projects in Adivali

10 projects under 10 MahaRERA registrations, registered 2022–2026. None has an extended completion date on record.

Locality
10RERA projects
10Registrations
9Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20222
20230
20245
20252
20261

Projects in Adivali

10 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Olympia City Phase 1Balaji Rattan LifespacesPR133101260158719 Aug 202631 Jul 2031—Not yet due0
The Vaidiki AarambhShree Jari Mari Builders And DevelopersPR133000250160427 Nov 202531 Dec 2030—Not yet due0
Seasons Sahara Nano Building No. CSamarth Sai Builders & DevelopersP5170007935328 Feb 202530 Jun 2028—Not yet due0
Season Sahara Building No -6Samarth Sai Builders & DevelopersP5170007792913 Nov 202431 Dec 2026—Not yet due0
Seasons Sahara Building No. 1Samarth Sai Builders & DevelopersP5170007794013 Nov 202428 Dec 2028—Not yet due0
SEASONS SAHARA NANO BUILDING NO A and BSamarth Sai Builders & DevelopersP5170007774725 Oct 202431 Dec 2026—Not yet due0
The Vaidiki Signature - C WingShree Jari Mari Developers LLPP5170007741713 Aug 202431 Dec 2027—Not yet due0
Shivom LakesideShivom Builders And DevelopersP5170005495221 Feb 202431 Dec 2028—Not yet due0
The Vaidiki Signature - A WingShree Jari Mari Developers LLPP5170004615720 Jun 202231 Dec 2025—Promised date passed0
The Vaidiki Signature - B WingShree Jari Mari Developers LLPP5170004547924 May 202231 Dec 2026—Not yet due0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Samarth Sai Builders & Developers4 projects
  2. Shree Jari Mari Developers LLP3 projects
  3. Balaji Rattan Lifespaces1 project
  4. Shivom Builders And Developers1 project
  5. Shree Jari Mari Builders And Developers1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology