Dhamote, Raigarh
Deedo IDDL-RAI-DHAMOTE10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects55
Registrations58some projects hold several
Completion still due1345 past their date
Median extension18 months47% of registrations extended
Regulatory cases1on 1 project
10 in 10 registrations run late here
58 MahaRERA registrations in Dhamote
1 not yet due12 extended, not yet due45 past even the latest date
Extended registrations moved their completion date by a median of 18 months.
Projects in Dhamote
55 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Swami KimayaGalaxy Enterprises | Due Dec 2026, extended 5 yrs | — | 83% |
| Shree Siddhi Vinayak SamarthShree Samarth Residency | Completed | — | 56% |
| Sai ChintamaniBalaji Builders And Developers | Completed | — | — |
| PrabhatPrabhat Creations LLP | Completed | — | 100% |
| Sai DhamTriple 8 Realty Pvt Ltd | 3 yrs 11 mo late | — | 100% |
| AltamonteConcept Superstructures Private Limited | Due Apr 2030, extended 4 mo | — | 5% |
| PrideSudha Developers | 7 yrs 11 mo late | — | — |
| Shree Mahalakshmi Park Building No 1Shree Mahalaxmi Home Makers | Completed | — | 19% |
| Pramukh DarshanPramukh Enterprises | Completed | — | 94% |
| Nirmal ArcadeAkshar Developers | Completed | — | 6% |
| Surya Galaxy Phase IShubh Laxmi Realty | Completed, extended 1 yr 6 mo | — | — |
| Laxmi OrchidLaxmi Global | Completed, extended 1 yr 6 mo | — | 47% |
| Shree Hingad PalaceS.m. Developers | Completed | — | 22% |
| Shubharambh GardensShubharambh Realty | Completed | — | 14% |
| Bliss ResidencyBashir Imamsahab Sayed | 3 yrs 11 mo late | — | 93% |
| Pankaj ResidencyPankaj Homes | Completed | — | 79% |
| Silverline HomesSilverline Homes Pvt Ltd | Completed, extended 1 yr 5 mo | — | — |
| Silverline ResidencySilverline Homes Pvt Ltd | Completed, extended 3 mo | — | 27% |
| Swami PratimaAtharva Promoters And Builders | Due Dec 2027, extended 8 yrs | — | 63% |
| Viviana - Block3Nirman Realtors And Developers Ltd | Completed | — | 77% |
| Sai DarshanTriple 8 Realty Pvt Ltd | Due Dec 2028, extended 5 yrs | — | — |
| VivianaNirman Realtors And Developers Ltd | Completed | — | 36% |
| Shree G SquareRajesh Amarlal Thakur | Completed, extended 1 yr 9 mo | — | 32% |
| Swagat VillageNayan Infrastructure | Due Jun 2027, extended 4 yrs | — | 70% |
| Vasant Nirvana Phase 2Shree Sai Developers | Completed | — | 94% |
Nearby: other villages in Karjat
Most active promoters
- Ramshiromani Lurkhur Yadav3 projects
- Nirman Realtors And Developers Ltd2 projects
- Nirman Realtors And Developers Ltd2 projects
- Rajesh Amarlal Thakur2 projects
- Shree Samarth Residency2 projects
- Silverline Homes Pvt Ltd2 projects
- Triple 8 Realty Pvt Ltd2 projects
- Vrushti Enterprises2 projects
- Adesh Homes1 project
- Ahamedsharief Lalusaheb Sayed1 project
Dhamote, in questions
How many projects in Dhamote run late?
10 in 10 MahaRERA registrations (57 of 58): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Dhamote by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology