Dhamote, Raigarh
Deedo IDDL-RAI-DHAMOTE10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects55
Registrations58some projects hold several
Completion still due1345 past their date
Median extension18 months47% of registrations extended
Regulatory cases1on 1 project
10 in 10 registrations run late here
58 MahaRERA registrations in Dhamote
1 not yet due12 extended, not yet due45 past even the latest date
Extended registrations moved their completion date by a median of 18 months.
Projects in Dhamote
55 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| The MorningSatyambuildcon | 3 yrs 11 mo late | — | 65% |
| STUDIO HIGH 5 Phase 2Ramshiromani Lurkhur Yadav | Completed, extended 1 yr 10 mo | — | 100% |
| Shree Samarth DarshanShree Samarth Residency | Completed | — | 70% |
| My Sky Residency Phase IAshapura Abode | Completed | — | 30% |
| Shree Mahalakshmi Park Building No.2Jayvardhan Infraprojects Pvt. Ltd. | Completed | — | 78% |
Nearby: other villages in Karjat
Most active promoters
- Ramshiromani Lurkhur Yadav3 projects
- Nirman Realtors And Developers Ltd2 projects
- Nirman Realtors And Developers Ltd2 projects
- Rajesh Amarlal Thakur2 projects
- Shree Samarth Residency2 projects
- Silverline Homes Pvt Ltd2 projects
- Triple 8 Realty Pvt Ltd2 projects
- Vrushti Enterprises2 projects
- Adesh Homes1 project
- Ahamedsharief Lalusaheb Sayed1 project
Dhamote, in questions
How many projects in Dhamote run late?
10 in 10 MahaRERA registrations (57 of 58): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Dhamote by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology