Deedo IDDP-RAI-CMHZCompletion was pushed back 5 years, to Dec 2028; no MahaRERA orders on record; 0% of its units are booked.
Dhamote, Raigarh 410101 · by Triple 8 Realty Pvt Ltd
Buying a flat here?
See every deed registered on it.
Completion was pushed back 5 years, to Dec 2028
- This projectRegistered 14 Aug 2017, completion promised 30 Dec 2023, revised to 31 Dec 2028.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000006311
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000006311 | 14 Aug 2017 | 30 Dec 2023 | 31 Dec 2028 | Triple 8 Realty Pvt Ltd | Project page |
Documents72
2 documents held by Deedo, 70 filings listed on MahaRERA's project page
Legal
Show all 72 documentsShow fewer documents
Migrated
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architecture certificate - triple 8-ilovepdf-compressed.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineers certificate - triple 8-ilovepdf-compressed.pdf · uploaded 31 Jul 2017Source
- 1 Proforma of Allotment letterSale format.pdf · uploaded 31 Jul 2017Source
- 1 Details of encumbrancesENCUMBRANCES CERT.pdf · uploaded 4 Aug 2017Source
- 1 Declaration in FORM BFORM B LOW RES.pdf · uploaded 4 Aug 2017Source
- 1 Certificates of CA (Form 3)CA CERTIFICATE NEW.pdf · uploaded 10 Aug 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)archit.pdf · uploaded 3 Feb 2018Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engin.pdf · uploaded 3 Feb 2018Source
- 2 Certificates of CA (Form 3)FORM-3_SIGNED.pdf · uploaded 27 Mar 2018Source
- 1 Certificates of CA (Form 5)FORM 5_SAI DARSHAN.pdf · uploaded 17 Oct 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentfile_1613461612377_compressed.pdf · uploaded 18 Feb 2021Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ashok Gandhi Architect's Certificate_SaiDarshan.pdf · uploaded 16 Jun 2021Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Ashok Gandhi Engineer's Certificate_SaiDarshan.pdf · uploaded 16 Jun 2021Source
- 2 Declaration in FORM BForm B.pdf · uploaded 9 Dec 2023Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 9 Dec 2023Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sai darshan - Architect certificate - 1Dec 2023.pdf · uploaded 9 Dec 2023Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 9 Dec 2023Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)sai darshan - engineer certificate - 1 12 2023.pdf · uploaded 9 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 19-20.pdf · uploaded 9 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A 20-21.pdf · uploaded 9 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 21-22.pdf · uploaded 9 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A 22-23.pdf · uploaded 9 Dec 2023Source
- 1 Disclosure of sold/ booked inventorySOLD INVENTORY.pdf · uploaded 9 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)form 5 18-19.pdf · uploaded 21 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)form 5 19-20.pdf · uploaded 21 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form 5 20-21.pdf · uploaded 21 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 2A 21-22.pdf · uploaded 21 Dec 2023Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 21-22.pdf · uploaded 21 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form 5 22-23.pdf · uploaded 21 Dec 2023Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 7 May 2024Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 7 May 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 7 May 2024Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1.pdf · uploaded 28 Jan 2025Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1.pdf · uploaded 28 Jan 2025Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1.pdf · uploaded 28 Jan 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 28 Jan 2025Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 28 Jan 2025Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 28 Jan 2025Source
- 1 Certificates of CA (Form 3)FORM 3_.pdf · uploaded 22 Feb 2025Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 22 Feb 2025Source
- 1 Proforma of Agreement for saleSAI DARSHAN Agreement.pdf · uploaded 4 Apr 2025Source
- Withdrawal Update Form 1Form 1 Q1 25-26.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 1Form 2 Q2 25-26.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 1Form1 Q3 25-26.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 2Form 2 Q1 25-26.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 2Form 2 Q2 25-26.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 2Form2 Q3 25-26.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 3Form 3 Q1 25-26.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 3Form 3 Q2 25-26.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 3Form3 Q3 25-26.pdf · uploaded 22 Apr 2026Source
- Withdrawal Update Form 1Form 1 Q4 25-26.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 2Form 2 Q4 25-26.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 3Form3 Q3 25-26.pdf · uploaded 30 May 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 13, 14
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- Type a, Type b, Type c, Type d, Type e, Type f42 units in all
- Address
- S No 90 P No 12, 13, 14, 15, Plot No 12/13/14/15, Survey No 90PIN 410101
- Village
- Dhamote, Karjat taluka
- Location
- 19.03410, 73.33108
- Land area for this project
- 1,108 sq m (11,926 sq ft)
- Permissible built-up area
- 1,100 sq m (11,845 sq ft)
- Sanctioned built-up area
- 1,100 sq m (11,845 sq ft)
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S No 90 P No 12, 13, 14, 15
Boundaries
- North
- 13
- South
- 11
- East
- Shri Gaikwad Property
- West
- Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking42 units
0 of 42 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Type a | 25.22 sq m · 271 sq ft | 6 | 0 |
| Type b | 20.02 sq m · 215 sq ft | 18 | 0 |
| Type c | 25.15 sq m · 271 sq ft | 6 | 0 |
| Type d | 24.76 sq m · 267 sq ft | 3 | 0 |
| Type e | 25.23 sq m · 272 sq ft | 6 | 0 |
| Type f | 25.07 sq m · 270 sq ft | 3 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | The Design India | — |
| Chartered accountant | Hitesh Mulchand Shah | — |
| Engineer | The Design India | — |
Source: MahaRERA project page. Contact details are not shown.