Sai Dham

Deedo IDDP-RAI-D1ED

Completion was pushed back 3 years to Dec 2025, and that date has passed too; no MahaRERA orders on record; 100% of its units are booked.

Dhamote, Raigarh 410101 · Promoter: Triple 8 Realty Pvt Ltd

Delivery3 yrs 10 mo latePromised Dec 2022 · revised Dec 2025 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked20 of 20 units · as the promoter reported to MahaRERA
Sai Dham project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 3 years to Dec 2025, and that date has passed too

  • This projectRegistered 8 Jan 2018, completion promised 30 Dec 2022, revised to 31 Dec 2025, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000014830
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P520000148308 Jan 201830 Dec 202231 Dec 2025Triple 8 Realty Pvt LtdProject page
Documents103

2 documents held by Deedo, 101 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 27 Dec 2017Source

Legal

  • Legal Title reportTITTLE_CERTIFICATE.pdf · uploaded 27 Dec 2017Source
  • Declaration Form BForm B compressed.pdf · uploaded 28 Dec 2017Source
  • Declaration Form B2 Form B new.pdf · uploaded 25 Mar 2025Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 27 Dec 2017Source
  • 1 Copy of the legal title reportTITTLE_CERTIFICATE.pdf · uploaded 27 Dec 2017Source
Show all 103 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesNON ENCUMBRANCE.pdf · uploaded 27 Dec 2017Source
  • 1 Copy of Layout Approval (in case of layout)CC_PLAN.pdf · uploaded 27 Dec 2017Source
  • 1 Building Plan Approval (IOD)CC_PLAN.pdf · uploaded 27 Dec 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT_CERTIFICATE (1).pdf · uploaded 27 Dec 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE.pdf · uploaded 27 Dec 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS CERTIFICATE.pdf · uploaded 27 Dec 2017Source
  • 1 Certificates of CA (Form 3)Chartered Accountant CERTIFICATE.pdf · uploaded 27 Dec 2017Source
  • 1 Declaration in FORM BForm B compressed.pdf · uploaded 28 Dec 2017Source
  • 1 Proforma of Allotment letterMaha Rera Agreement for Sale SAI DHAM.pdf · uploaded 28 Dec 2017Source
  • 1 Certificates of CA (Form 5)FORM 5_SAI DHAM.pdf · uploaded 22 Oct 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ashok Gandhi Architect's Certificate_Sai Dham.pdf · uploaded 16 Jun 2021Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Ashok Gandhi Engineer's Certificate_Sai Dham.pdf · uploaded 16 Jun 2021Source
  • 1 Declaration about Commencement CertificateDECLARTAION OF CC.pdf · uploaded 16 Jan 2023Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 16 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM-2A(19-20).pdf · uploaded 16 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM-2A(20-21).pdf · uploaded 16 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM-2A(21-22).pdf · uploaded 16 Jan 2023Source
  • 1 Disclosure of sold/ booked inventorySOLD-UNSOLD INVENTORY.pdf · uploaded 16 Jan 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARTION OF SPRATE BANK.pdf · uploaded 16 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM-5 (18-19).pdf · uploaded 20 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM-5(19-20).pdf · uploaded 20 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM-5(20-21).pdf · uploaded 20 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM-5(21-22).pdf · uploaded 20 Jan 2023Source
  • 2 Disclosure of sold/ booked inventorySOLD INVENTORY.pdf · uploaded 9 Dec 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1.pdf · uploaded 26 Dec 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 26 Dec 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 22-23.pdf · uploaded 26 Dec 2023Source
  • 3 Disclosure of sold/ booked inventorySOLD INVENTORY.pdf · uploaded 26 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 2A 22-23.pdf · uploaded 26 Dec 2023Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 7 May 2024Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 7 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 7 May 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1.pdf · uploaded 28 Jan 2025Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1.pdf · uploaded 28 Jan 2025Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1.pdf · uploaded 28 Jan 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 28 Jan 2025Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 28 Jan 2025Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 28 Jan 2025Source
  • 1 Declaration in FORM B2 Form B new.pdf · uploaded 25 Mar 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 7 Apr 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 7 Apr 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 30 Apr 2025Source
  • 1 Certificates of CA (Form 3)Form-3-sign.pdf · uploaded 30 Apr 2025Source
  • 2 Certificates of CA (Form 3)Form-3-sign.pdf · uploaded 30 Apr 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 30 Apr 2025Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 30 Apr 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Final FORM 1.pdf · uploaded 22 May 2025Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Final FORM 1.pdf · uploaded 22 May 2025Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Final FORM 1.pdf · uploaded 22 May 2025Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Final FORM 1.pdf · uploaded 22 May 2025Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Final FORM 1.pdf · uploaded 22 May 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Final FORM 2.pdf · uploaded 22 May 2025Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Final FORM 2.pdf · uploaded 22 May 2025Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Final FORM 2.pdf · uploaded 22 May 2025Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Final FORM 2.pdf · uploaded 22 May 2025Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Final FORM 2.pdf · uploaded 22 May 2025Source
  • 1 Disclosure of sold/ booked inventoryInventory Sold Letter.pdf · uploaded 23 May 2025Source
  • 1 Certificates of CA (Form 3)Final FORM 3.pdf · uploaded 28 May 2025Source
  • 2 Certificates of CA (Form 3)Final FORM 3.pdf · uploaded 28 May 2025Source
  • 3 Certificates of CA (Form 3)Final FORM 3.pdf · uploaded 28 May 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Final FORM 5.pdf · uploaded 28 May 2025Source
  • Withdrawal Update Form 1Form 1 Sai Dham Q1 25-26.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 1Form 1 Q2 25-26.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 1Form 1 Q3 25-26.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 2Form 2 Sai Dham Q1 25-26.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 2Form 2 Q2 25-26.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 2Form 2 Q3 25-26.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 3Form 3 Sai Dham Q1 25-26.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 3Form 2 Q2 25-26.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 3Form 3 Q3 25-26.pdf · uploaded 7 May 2026Source

Technical

  • DocumentCC_PLAN.pdf · uploaded 27 Dec 2017Source
  • DocumentCC_PLAN.pdf · uploaded 27 Dec 2017Source

Technical (Architect)

  • Documentform 1.pdf · uploaded 28 Jan 2025Source
  • Documentform 1.pdf · uploaded 28 Jan 2025Source
  • Documentform 1.pdf · uploaded 28 Jan 2025Source
  • DocumentFORM 1.pdf · uploaded 7 Apr 2025Source
  • DocumentForm 1.pdf · uploaded 30 Apr 2025Source
  • DocumentFinal FORM 1.pdf · uploaded 22 May 2025Source
  • DocumentFinal FORM 1.pdf · uploaded 22 May 2025Source
  • DocumentFinal FORM 1.pdf · uploaded 22 May 2025Source
  • DocumentFinal FORM 1.pdf · uploaded 22 May 2025Source
  • DocumentFinal FORM 1.pdf · uploaded 22 May 2025Source
  • DocumentForm 1 Q3 25-26.pdf · uploaded 7 May 2026Source

Technical (Engineer)

  • Documentform 2.pdf · uploaded 28 Jan 2025Source
  • Documentform 2.pdf · uploaded 28 Jan 2025Source
  • Documentform 2.pdf · uploaded 28 Jan 2025Source
  • DocumentFORM 2.pdf · uploaded 7 Apr 2025Source
  • DocumentForm 2.pdf · uploaded 30 Apr 2025Source
  • Documentform 2.pdf · uploaded 30 Apr 2025Source
  • DocumentFinal FORM 2.pdf · uploaded 22 May 2025Source
  • DocumentFinal FORM 2.pdf · uploaded 22 May 2025Source
  • DocumentFinal FORM 2.pdf · uploaded 22 May 2025Source
  • DocumentFinal FORM 2.pdf · uploaded 22 May 2025Source
  • DocumentFinal FORM 2.pdf · uploaded 22 May 2025Source
  • DocumentForm 2 Q3 25-26.pdf · uploaded 7 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals31, PLOT NO 30

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK20 units in all
Address
Plot No 30 And 31, Bopele Dhamote Village Road, DhamotePIN 410101
Village
Dhamote, Karjat taluka
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

31PLOT NO 30

Boundaries

North
6 M Wide Internal Road
South
Plot No 33 And 32
East
Plot No 29
West
Plot No 21

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking20 units

20 of 20 units booked (100%), as the promoter reported to MahaRERA

1BHK · 10 units1RK · 8 units2BHK · 2 units
TypeCarpet areaUnitsBooked
1BHK23.55 sq m · 253 sq ft44
1BHK23.95 sq m · 258 sq ft44
1BHK31.06 sq m · 334 sq ft11
1BHK31.2 sq m · 336 sq ft11
1RK20.27 sq m · 218 sq ft88
2BHK30.65 sq m · 330 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMs The Design India—
Chartered accountantHitesh Mulchand shah—
EngineerMs The Design India—

Source: MahaRERA project page. Contact details are not shown.