ProjectLocalityRegisteredPromisedDelivery
Bhagwati ApartmentNew Swamiraj ConstructionSatpurApr 2026Feb 2028Due Jun 2028, extended 4 mo
Shree Sham ApartmentShree Sham Builders And DevelopersNashikApr 2026Mar 2029Due Jul 2029, extended 4 mo
Pm1220002503052Patil Epitome Pvt LtdDeolaligaonMar 2026Dec 2029Due Apr 2030, extended 4 mo
Nashik Business Park Phase 2Santosh Eknath ChakankarNashikMar 2026Dec 2031Due Apr 2032, extended 4 mo
Shripad AvenueShriram Builders And DevelopersNashikMar 2026Mar 2030Due Jul 2030, extended 4 mo
Inayat CityInayat Builders and DevelopersNashik (M Corp.)Mar 2026Dec 2030Due Apr 2031, extended 4 mo
Alaknanda ApartmentRam ConstructionsAanandwaliMar 2026Dec 2030Due Apr 2031, extended 4 mo
Balaji HeightsGeeta DevelopersSatpurMar 2026Dec 2030Due Apr 2031, extended 4 mo
Halpani EnclaveHalpani BuildconPanchakMar 2026Jan 2031Due May 2031, extended 4 mo
Swami SankulSwami BuildconGangapurMar 2026Dec 2028Due Apr 2029, extended 4 mo
Vishrant CHS LtdKalash InfrastructureKamatwadeMar 2026Dec 2029Due Apr 2030, extended 4 mo
Yashoda's Maheshwar KunjShree Jyoti InfraNashik (M Corp.)Mar 2026Dec 2029Due Apr 2030, extended 4 mo
Viraj SattvaViraj Estates Private LimitedAmbad KhurdMar 2026Dec 2029Due Apr 2030, extended 4 mo
Bramhand ApartmentShree Builders And DevelopersNashik (M Corp.)Mar 2026Dec 2029Due Apr 2030, extended 4 mo
Govinda HarmonyRadhe DevelopersNashikMar 2026Dec 2028Due Apr 2029, extended 4 mo
Manohar EnclaveMonarch ConstructionsNashikMar 2026Dec 2030Due Apr 2031, extended 4 mo
Rajas ResidenceShiva InfraNashikMar 2026Dec 2028Due Apr 2029, extended 4 mo
Rathod ResidencySiddhant DevelopersAdgaonMar 2026Dec 2028Due Apr 2029, extended 4 mo
Sai Raj ResidencySai Ganraj DevelopersNashikMar 2026Mar 2029Due Jul 2029, extended 4 mo
Shree Vyankatesh PrideShree Siddhi ConstructionsPathardiMar 2026Apr 2029Due Apr 2029
Shri Ganesh VandanDilip Babulal WaniNashikMar 2026May 2028Due Sep 2028, extended 4 mo
Ganraj SankulTrident DevelopersGangapurMar 2026Mar 2029Due Jul 2029, extended 4 mo
Yugandhar ApartmentM.k.groupsMakhmalabadMar 2026Dec 2028Due Apr 2029, extended 4 mo
Amrut Kalash ApartmentSwastik EstatesJail RoadMar 2026Dec 2029Due Apr 2030, extended 4 mo
Ganga Residency Building BGajsiddhi DevelopersNashikMar 2026Dec 2030Due Apr 2031, extended 4 mo
Pokar Villa Co-operative Housing Society Limited NashikSkyline BuildersNashikMar 2026Dec 2027Due Apr 2028, extended 4 mo
Golden Peacock-Phase OneDeepak Infra And Homes Private LimitedGovardhanMar 2026Dec 2032Due Apr 2033, extended 4 mo
Sagar Co Op Housing SocietyNice HomeDeolali (Cb)Mar 2026Dec 2028Due Apr 2029, extended 4 mo
Vastushree ApartmentVastushree Builders & DevelopersNashik (M Corp.)Mar 2026Dec 2029Due Apr 2030, extended 4 mo
Platinum Care By ParksydeJaikumar Constructions LtdNashikFeb 2026May 2028Due Sep 2028, extended 4 mo
Lila HeightsYamuna ConstructionBhagur RuralFeb 2026Dec 2028Due Apr 2029, extended 4 mo
Roongta Techone ApartmentShree Tirumala BuildconNashikFeb 2026Mar 2032Due Jul 2032, extended 4 mo
Shiv AnganDsp DevelopersNashikFeb 2026Dec 2029Due Apr 2030, extended 4 mo
Pranav Apartment Co. Operative Housing Society Ltd.Pravin Bhalchandra PawarNashik ShiwarFeb 2026Dec 2028Due Apr 2029, extended 4 mo
Revati ShantipuramRevati Infra EngineersNashikFeb 2026Dec 2031Due Apr 2032, extended 4 mo
Gaurav Shri Apartment Co-op Hsg Society LtdGurudatta Constructions Builders And Land DevelopersNashik (M Corp.)Feb 2026May 2029Due Sep 2029, extended 4 mo
Shri GirnarAshwamedh BuildconMakhmalabadFeb 2026Dec 2029Due Apr 2030, extended 4 mo
Sai InfinityTirtha BuildconAdgaonFeb 2026Mar 2029Due Jul 2029, extended 4 mo
Ashok JivandharaAshok BuildwellGangapurFeb 2026Dec 2028Due Apr 2029, extended 4 mo
Rudra HeightsVakratunda ConstructionNashikFeb 2026Nov 2029Due Mar 2030, extended 4 mo
The ArcSkia Properties LLPNashikFeb 2026Dec 2028Due Apr 2029, extended 4 mo
Pooja Elementpooja constructionsAanandwaliFeb 2026Dec 2029Due Apr 2030, extended 4 mo
Varad EmpireMauli ConstructionPathardiJan 2026Mar 2029Due Jul 2029, extended 4 mo
Padmavati HeightsSanskar Ajay KelaNashikJan 2026Dec 2028Due Apr 2029, extended 4 mo
Samarth IconGeocare Resources Private LimitedAanandwaliJan 2026Dec 2030Due Apr 2031, extended 4 mo
Alkapuri Co-Op Housing SocietySky DevelopersNashik (M Corp.)Jan 2026Dec 2028Due Apr 2029, extended 4 mo
The ReserveBagad PropertiesNashikJan 2026Oct 2032Due Feb 2033, extended 4 mo
Daksh LevantaH K PropertiesAdgaonJan 2026Dec 2031Due Dec 2031
Landmark SolitaireLandmark GroupNashikJan 2026Dec 2028Due Apr 2029, extended 4 mo
Kshiti EliteKshiti GroupNashikJan 2026Dec 2029Due Apr 2030, extended 4 mo