Macrotech Developers Limited

Deedo IDDD-P32E

Of 124 registrations whose promised date has arrived, 106 kept it (86%). The rest ran a median 12 mo late.

Projects105130 RERA registrations
Kept RERA date86%Maharashtra: 73%
Median delay12 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases8no insolvency

Delivery record

18 of 130 registrations with dates moved or missed their RERA date · months late against the original promise

Show all 130 registrations

130 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Lodha Splendora Platino E To G , Vivant A To DP51700000199Thane (M Corp.)Certificate Signed30 Jun 201930 Jun 2019On date
Lodha FiorenzaP51800000195BorivaliCertificate Signed31 Jan 201831 Jan 2018On date
Lodha Belmondo AugustaP52100000174GahunjeCertificate Signed31 Dec 201731 Dec 2017On date
Lodha Belmondo St. Andrews EP52100000182GahunjeCertificate Signed31 Dec 201931 Dec 2019On date
Lodha Belmondo Sawgrass BP52100000221GahunjeCertificate Signed30 Apr 201830 Apr 2018On date
Lodha Belmondo St. Andrews B, C, D Villa 1 to 28P52100000283GahunjeCertificate Signed31 Jul 201831 Jul 2018On date
Lodha Eternis Idyllia B, Serena B, Natura B And CP51800000293AndheriCertificate Signed31 Dec 201831 Dec 2018On date
Lodha Eternis SerenaP51800000294AndheriCertificate Signed31 Dec 201931 Dec 2019On date
Lodha Eternis Natura AP51800000345AndheriCertificate Signed30 May 202230 May 2022On date
New Cuffe Parade - Lodha Dioro And ElisiumP51900000314Ward FnorthCertificate Signed30 Jun 201930 Jun 2019On date
New Cuffe Parade - Lodha EnchanteP51900000367Ward FnorthCertificate Signed30 Jun 201930 Jun 2019On date
LODHA BELMONDO Pebble Beach E, Estancia AP52100000350GahunjeCertificate Signed30 Sep 201830 Sep 2018On date
Lodha Belmondo AugustaP52100000406GahunjeCertificate Signed30 Jun 201930 Jun 2019On date
Palava Savana And SienaP51700000546UsargharCertificate Signed28 Feb 202128 Feb 2021On date
New Cuffe Parade - Lodha EstrellaP51900000521Ward FnorthCertificate Signed31 Jan 201931 Jan 2019On date
NEW CUFFE PARADE - LODHA EVOQ 41st FloorP51900000567Ward FnorthCertificate Signed30 Jun 201930 Dec 2020+18 mo
New Cuffe Parade -Lodha AltiaP51900000629Ward FnorthCertificate Signed30 Mar 202230 Mar 2022On date
Lodha Splendora - Platino - DP51700000659Thane (M Corp.)Certificate Signed30 Sep 202230 Sep 2022+50 mo*
Lodha AzzuroP51900000828Ward FsouthCertificate Signed30 Jun 202230 Jun 2022On date
Lodha AmaraP51700000981Thane (M Corp.)Certificate Signed30 Jul 202230 Jul 2022On date
Lodha AmaraP51700001030Thane (M Corp.)Certificate Signed28 Aug 202228 Aug 2022On date
Lodha AmaraP51700001031Thane (M Corp.)Certificate Signed30 Dec 202130 Dec 2021On date
Lodha AmaraP51700001065Thane (M Corp.)Certificate Signed30 Nov 201930 Nov 2019On date
Casa Univis - Cielo DP51700001153Thane (M Corp.)Certificate Signed31 Mar 201831 Mar 2018On date
Lodha ParkP51900001339Ward GsouthCertificate Signed31 Dec 202130 Dec 2023+24 mo
Lodha FreshiaP51700004667NeljeCertificate Signed31 Dec 201731 Dec 2017On date
Lodha Venezia - 49th To 65th FloorP51900005378Ward FsouthCertificate Signed31 Dec 201831 Dec 2018On date
Upper Thane Greenville A - E, E1, F - IP51700006147SuraiCertificate Signed30 Sep 202230 Sep 2022On date
Lodha FreshiaP51700006149NeljeCertificate Signed31 Dec 201931 Dec 2019On date
Upper Thane EcopolisP51700007192MankoliCertificate Signed30 Sep 202230 Sep 2022On date
The World Towers - World One - Tier IIP51900008345Ward GsouthCertificate Signed30 Sep 201925 Feb 2020+5 mo
Upper Thane Treetops A - C, C1, C2, D - FP51700008449SuraiCertificate Signed30 Sep 202230 Sep 2022On date
Palava River View E And FP51700008764GhesarCertificate Signed31 Dec 201731 Dec 2017On date
The World Towers - World One - Tier III And TrinityP51900008962Ward GsouthCertificate Signed30 Jun 202130 Jun 2023+24 mo
Lodha SeaviewP51900010326Ward AbcdCertificate Signed30 Dec 202230 Dec 2022On date
Lodha Belmondo Ashbridge D, EP52100011522GahunjeCertificate Signed31 Dec 201731 Dec 2017On date
Lodha Mira Road Project 1P51700012991Mirabhayandar (M Corp.)Certificate Signed28 Nov 202227 Nov 2023+12 mo
Lodha MajiwadaP51700013263MajiwadeCertificate Signed28 Nov 202228 Nov 2022On date
Lodha Supremus - AndheriP51800013696AndheriCertificate Signed28 Aug 202228 Aug 2022On date
Lodha MajiwadaP51700013789MajiwadeCertificate Signed28 Nov 202228 Nov 2022On date
Lodha AmaraP51700013961Thane (M Corp.)Certificate Signed30 Dec 202230 Dec 2022On date
Lodha AmaraP51700014760Thane (M Corp.)Certificate Signed30 Jan 202430 Jan 2024On date
Upper Thane - Sereno D and EP51700014770SuraiCertificate Signed30 Mar 202330 Mar 2023On date
UPPER THANE - TIARA A to BP51700014814MankoliCertificate Signed30 Oct 202230 Oct 2022On date
Lodha Patel EstateP51800014860BorivaliCertificate Signed31 Jul 202331 Jul 2023On date
Lodha Patel EstateP51800014869BorivaliCertificate Signed30 Oct 202330 Oct 2023On date
Lodha Patel EstateP51800014891BorivaliCertificate Signed31 Jul 202331 Jul 2023On date
One Lodha PlaceP51900014984Mumbai CityCertificate Signed30 Mar 202330 Mar 2023On date
Lodha KolshetP51700015040Thane (M Corp.)Certificate Signed30 Jun 202230 Jun 2022On date
Lodha KolshetP51700015243Thane (M Corp.)Certificate Signed30 Dec 202230 Dec 2022On date
Lodha Supremus - Thane, KolshetP51700015598KolshetCertificate Signed31 Jul 202231 Jul 2022On date
New Cuffe Parade - Lodha GardeniaP51900015715Mumbai CityCertificate Signed30 Mar 202330 Mar 2023On date
Upper Thane - Sereno A, B, B1P51700016243SuraiCertificate Signed30 Sep 202330 Sep 2023On date
Upper Thane - Woodlands G, H, IP51700016245AnjurCertificate Signed30 Sep 202330 Sep 2023On date
Lodha Splendora - River ViewP51700016375BhayandarpadaCertificate Signed30 Sep 202430 Sep 2024On date
Upper Thane TiaraP51700016437MankoliCertificate Signed30 Sep 202330 Sep 2023On date
Lodha Patel EstateP51800016528BorivaliCertificate Signed28 Aug 202327 Feb 2025+18 mo
Lodha Park - Town HousesP51900016526Lower ParelCertificate Signed30 Dec 202130 Dec 2021On date
Upper Thane EcopolisP51700016666MankoliCertificate Signed30 Sep 202230 Sep 2022On date
Lodha Belmondo - Estancia BP52100016840GahunjeCertificate Signed31 Aug 201831 Aug 2018On date
Apollo RetailP51700016927MajiwadeCertificate Signed30 Sep 202030 Sep 2020On date
Lodha AmaraP51700016961Thane (M Corp.)Certificate Signed30 Sep 202330 Sep 2023On date
Lodha Panacea IIP51700017060BhoparCertificate Signed31 Oct 202631 Oct 2026On date
Lodha Panacea IP51700017078BhoparCertificate Signed31 Dec 202114 Aug 2024+32 mo
Lodha Belmondo - TownhousesP52100017082GahunjeCertificate Signed30 Jun 202229 Jun 2023+12 mo
Lodha Global ParkP51700017924BhoparCertificate Signed30 Dec 202230 Dec 2022On date
NCP Commercial Tower 1 - Floors 24 to 28P51900017945Ward FnorthCertificate Signed30 Jun 201930 Jun 2019On date
UPPER THANE - Tiara IP51700018035MankoliCertificate Signed30 Mar 202430 Mar 2024On date
UPPER THANE - Woodlands E and FP51700018107AnjurCertificate Signed30 Mar 202430 Mar 2024On date
Lodha Belmondo - Pebble Beach DP52100018308GahunjeCertificate Signed31 Dec 201831 Dec 2018On date
LODHA AMARA - TOWER 38 and 39P51700018393Thane (M Corp.)Certificate Signed31 Jul 202431 Jul 2024On date
Lodha Amara - Tower 46P51700018579KolshetCertificate Signed31 Jul 202431 Jul 2024On date
Lodha Amara - Tower 45P51700018593KolshetCertificate Signed31 Jul 202431 Jul 2024On date
Upper Thane TiaraP51700019121MankoliCertificate Signed30 Mar 202430 Mar 2024On date
NCP Commercial Tower 1 - Floor 23rdP51900019176Ward FnorthCertificate Signed30 Sep 201930 Sep 2019On date
Lodha Belmondo - Sawgrass AP52100019434GahunjeCertificate Signed30 Jun 201930 Jun 2019On date
Lodha AmaraP51700020088Thane (M Corp.)Certificate Signed29 Nov 202428 Nov 2025+12 mo
Lodha AmaraP51700020093Thane (M Corp.)Certificate Signed30 Dec 202229 Dec 2023+12 mo
Upper Thane TiaraP51700020141MankoliCertificate Signed30 Jun 202530 Jun 2025On date
Upper Thane TiaraP51700020154MankoliCertificate Signed28 Nov 202528 Nov 2025+12 mo*
Lodha Sterling - Tower GP51700020158Thane (M Corp.)Certificate Signed30 Sep 202530 Sep 2025On date
Upper Thane - Meadows E, F, GP51700020170SuraiCertificate Signed30 Oct 202530 Oct 2025+13 mo*
Lodha Sterling - Tower HP51700020189ThaneCertificate Signed30 May 202430 May 2024On date
Upper Thane -Sereno A1P51700020191SuraiCertificate Signed31 Jul 202431 Jul 2024On date
Magnolia A B and CP51700020197AnjurCertificate Signed28 Nov 202327 Nov 2024+12 mo
Upper Thane - Sereno A1, C & C1P51700020217SuraiCertificate Signed30 May 202630 May 2026On date
Lodha Eternis SerenaP51800020147AndheriCertificate Signed30 Dec 202329 Dec 2024+12 mo
Lodha Belmondo - Tower 29P52100020142GahunjeCertificate Signed30 Sep 202430 Sep 2024On date
Lodha Belmondo St. Andrews AP52100020156GahunjeCertificate Signed28 Feb 202728 Feb 2027On date
Lodha Belmondo - Tower 31P52100020172GahunjeCertificate Signed30 Mar 202530 Mar 2025On date
Upper Thane - Meadows AP51700020266AnjurCertificate Signed30 Sep 202530 Sep 2025+14 mo*
NCP Commercial Tower - SupremusP51900021485Ward FnorthCertificate Signed30 Mar 202430 Mar 2024On date
Lodha Quality HomeP51700022250Thane (M Corp.)Certificate Signed31 Jul 202431 Jul 2024On date
Lodha Quality HomeP51700022251Thane (M Corp.)Certificate Signed31 Jul 202431 Jul 2024On date
Lodha Lower Parel ProjectP51900022245Lower ParelCertificate Signed30 Dec 202429 Jun 2025+6 mo
Lodha Quality Home Tower 3P51700022533Thane (M Corp.)Certificate Signed30 Sep 202430 Sep 2024On date
NCP Commercial Tower 1 - up to 22nd FloorP51900022549Ward FnorthCertificate Signed31 Dec 201931 Dec 2019On date
Lodha Quality HomeP51700024777Thane (M Corp.)Certificate Signed30 Sep 202430 Sep 2024On date
Lodha iThink BP51700025627NeljeCertificate Signed28 Feb 202228 Feb 2022On date
Lodha Amara MLCP RetailP51700025892Thane (M Corp.)Certificate Signed31 Jul 202231 Jul 2022On date
Lodha Quality Home Tower 6P51700025932Thane (M Corp.)Certificate Signed30 Sep 202530 Sep 2025On date
Lodha Quality Home Tower 7P51700026454Thane (M Corp.)Certificate Signed30 Mar 202630 Mar 2026On date
Lodha Quality HomeP51700027449Thane (M Corp.)Certificate Signed30 Mar 202530 Mar 2025On date
Lodha Clariant C3P51700027452BalkumCertificate Signed30 Jun 202330 Jun 2023On date
Lodha Venezia- wing CP51900029289Ward FsouthCertificate Signed30 Dec 202330 Dec 2023On date
Lodha Signet Lower Parel Wing AP51900029416WorliCertificate Signed30 May 202530 May 2025On date
Lodha Kandivali ProjectP51800031346BorivaliCertificate Signed30 Jun 202630 Jun 2026On date
Lodha Kandivali Project - Tower 2P51800031351AkurliCertificate Signed31 Jul 202631 Jul 2026On date
Lodha Kandivali ProjectP51800031532BorivaliCertificate Signed31 May 202531 May 2025On date
ForestaP51700032683MangaonCertificate Signed30 Apr 202630 Apr 2026On date
Fiora A, B and CP51700032684HedutaneCertificate Signed30 Nov 202530 Nov 2025On date
ForestaP51700032990MangaonCertificate Signed30 Nov 202530 Nov 2025On date
Foresta FP51700033750MangaonCertificate Signed31 Jan 202631 Jan 2026On date
Liana AP51700033751MangaonCertificate Signed28 Feb 202628 Feb 2026On date
iThink Tower-AP51700033958Thane (M Corp.)Certificate Signed31 May 202231 May 2022On date
Liana BP51700033964MangaonCertificate Signed28 Feb 202628 Feb 2026On date
FioraP51700033965HedutaneCertificate Signed31 Jan 202631 Jan 2026On date
Pearl AP51700034753KhoniCertificate Signed31 Dec 202531 Dec 2025On date
JardinoP51700034861MangaonCertificate Signed31 Aug 202731 Aug 2027On date
FioraP51700035051HedutaneCertificate Signed31 Mar 202631 Mar 2026On date
Lodha Signet Palava-Signet 1P51700045631KoleCertificate Signed31 Dec 202531 Dec 2025On date
Lodha Belmondo Townhouse 3P52100045926GahunjeCertificate Signed31 Mar 202631 Mar 2026+8 mo*
JardinoP51700046094MangaonCertificate Signed31 Aug 202831 Aug 2028On date
Fiora FP51700046315HedutaneCertificate Signed31 Aug 202631 Aug 2026On date
Lodha Signet Lower Parel Wing BP51900046367WorliCertificate Signed31 Aug 202631 Aug 2026On date
Lodha Belmondo Townhouse 2P52100046398GahunjeCertificate Signed30 Nov 202630 Nov 2026On date
Pearl BP51700048930KhoniCertificate Signed31 Jul 202631 Jul 2026On date
Dombivli ArcadeP51700055366NeljeCertificate Signed31 Oct 202731 Oct 2027On date
MLCP 3 Retail ShopsP51700077338KhoniCertificate Signed31 Dec 202431 Dec 2024On date
Upper Thane-MLCP C ShopsP51700077506MankoliCertificate Signed31 Dec 202631 Dec 2026On date
Show all 130 registrationsShow fewer

Macrotech Developers Limited, in questions

Does Macrotech Developers Limited finish projects on time?

Of 124 MahaRERA registrations whose promised completion date has arrived, 106 kept it (86%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.

How many projects has Macrotech Developers Limited registered with MahaRERA?

105 projects under 130 MahaRERA registrations; 122 completed on MahaRERA.

Does Macrotech Developers Limited have MahaRERA regulatory cases?

8 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology