RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100017082
Lodha Belmondo - Townhouses · Gahunje, Pune · Macrotech Developers Limited
Promised for 30 Jun 2022, extended once to 29 Jun 2023 — and that date has passed without the project marked complete on MahaRERA.
4 years and 4 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2022 to 29 Jun 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 29 Jun 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100017082
Is Lodha Belmondo - Townhouses delayed?
Yes. MahaRERA records a promised completion of 30 Jun 2022, revised to 29 Jun 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100017082. The completion date moved from 30 Jun 2022 to 29 Jun 2023.
Who is the promoter?
MahaRERA records Macrotech Developers Limited as the promoter of P52100017082.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100017082.
Answers are generated from the record.