Residential / Group Housing · 6 buildings · 458 unitsRERA P51700020217

Upper Thane - Sereno A1, C & C1

Deedo IDDP-THN-V8AV

MahaRERA shows it completed; no MahaRERA orders on record; 82% of its units are booked.

Surai, Thane 421302 · by Macrotech Developers Limited · 86% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales82% booked376 of 458 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 29 Mar 2019, completion promised 30 May 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700020217
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002021729 Mar 201930 May 202630 May 2026Macrotech Developers LimitedProject page
Documents81

2 documents held by Deedo, 79 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Legal

  • Declaration Form BForm B.pdf · uploaded 23 Mar 2019Source
  • Legal Title report3a Anjur TR_compressed-1-35.pdf · uploaded 23 Mar 2019Source
  • Legal Title report3a Anjur TR_compressed-36-60.pdf · uploaded 23 Mar 2019Source
  • Legal Title report3a Anjur TR_compressed-61-83.pdf · uploaded 23 Mar 2019Source
  • Legal Title report3b Anjur - First Supplemental Report on Title dated 03102018.pdf · uploaded 23 Mar 2019Source
  • Legal Title report3c Upper Thane - Supplemental Report on Title.pdf · uploaded 23 Mar 2019Source
Show all 81 documentsShow fewer documents

Legal

  • OtherLDL to MDL.pdf · uploaded 28 May 2019Source
  • Legal Title reportReport On Title - Surai 104.pdf · uploaded 25 Sep 2020Source

Migrated

  • 1 Copy of the legal title report3a Anjur TR_compressed-1-35.pdf · uploaded 23 Mar 2019Source
  • 2 Copy of the legal title report3a Anjur TR_compressed-36-60.pdf · uploaded 23 Mar 2019Source
  • 3 Copy of the legal title report3a Anjur TR_compressed-61-83.pdf · uploaded 23 Mar 2019Source
  • 4 Copy of the legal title report3b Anjur - First Supplemental Report on Title dated 03102018.pdf · uploaded 23 Mar 2019Source
  • 5 Copy of the legal title report3c Upper Thane - Supplemental Report on Title.pdf · uploaded 23 Mar 2019Source
  • 1 Details of encumbrancesCluster 4 03B.pdf · uploaded 23 Mar 2019Source
  • 1 Copy of Layout Approval (in case of layout)layout plan 1.pdf · uploaded 23 Mar 2019Source
  • 2 Copy of Layout Approval (in case of layout)layout plan 2.pdf · uploaded 23 Mar 2019Source
  • 1 Building Plan Approval (IOD)Cluster 4_03B_IOD_1.pdf · uploaded 23 Mar 2019Source
  • 2 Building Plan Approval (IOD)Cluster 4_03B_IOD_2.pdf · uploaded 23 Mar 2019Source
  • 3 Building Plan Approval (IOD)Cluster 4_03B_IOD_3.pdf · uploaded 23 Mar 2019Source
  • 4 Building Plan Approval (IOD)Cluster 4_03B_IOD_4.pdf · uploaded 23 Mar 2019Source
  • 5 Building Plan Approval (IOD)Cluster 4_03B_IOD_5.pdf · uploaded 23 Mar 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC_compressed -1.pdf · uploaded 23 Mar 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC_compressed -2.pdf · uploaded 23 Mar 2019Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 23 Mar 2019Source
  • 1 Certificates of CA (Form 3)Upper Thane Cluster No 4 03B.pdf · uploaded 23 Mar 2019Source
  • 1 Proforma of Allotment letterAllotment Letter Final.pdf · uploaded 23 Mar 2019Source
  • 2 Proforma of Allotment letterATS Upper Thane.pdf · uploaded 23 Mar 2019Source
  • 1 OtherLDL to MDL.pdf · uploaded 28 May 2019Source
  • 1 Form 2AUT Cluster 4 03 B.pdf · uploaded 17 Jun 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5)Upper Thane Cluster 4 03B.pdf · uploaded 30 Sep 2019Source
  • 2 Form 2AUpper Thane Cluseter 4 03B.pdf · uploaded 25 Aug 2020Source
  • 6 Copy of the legal title reportReport On Title - Surai 104.pdf · uploaded 25 Sep 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)36 Upper Thane Cluster no 4 03 B.pdf · uploaded 27 Oct 2020Source
  • 6 Building Plan Approval (IOD)SHEET 9 WOODLAND SERENO.pdf · uploaded 25 Feb 2021Source
  • 7 Building Plan Approval (IOD)SHEET 8 WOODLAND SERENO2.pdf · uploaded 25 Feb 2021Source
  • 8 Building Plan Approval (IOD)SHEET 10 WOODLAND SERENO3.pdf · uploaded 25 Feb 2021Source
  • 3 Form 2AVipul Pandya Conso[079-081].pdf · uploaded 11 Aug 2021Source
  • 3 Commencement Certificates / NA Order for plotted developmentUT_Commencement Certificate above Plinth_A1_C_C1-1.pdf · uploaded 9 Sep 2021Source
  • 4 Commencement Certificates / NA Order for plotted developmentUT_Commencement Certificate above Plinth_A1_C_C1-2.pdf · uploaded 9 Sep 2021Source
  • 2 Certificates of CA (Form 3)88 UPPER THANE - CLUSTER NO 403B-SERENO A1,C and C1.pdf · uploaded 9 Oct 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)97 Upper Thane - Sereno A1, C and C1.pdf · uploaded 14 Oct 2021Source
  • 1 Disclosure of sold/ booked inventoryP51700020217.pdf · uploaded 14 Oct 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)92_Sereno A1, C - C1.pdf · uploaded 15 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)35 Upper Thane - Sereno A1, C,C1.pdf · uploaded 15 Oct 2021Source
  • 4 Form 2A177 UPPER THANE CLUSTER 4 03B.pdf · uploaded 18 Nov 2021Source
  • 3 Certificates of CA (Form 3)88 UPPER THANE - SERENO A1, C C1.pdf · uploaded 15 Dec 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)97 Upper Thane - Sereno A1, C C1.pdf · uploaded 17 Dec 2021Source
  • 2 Disclosure of sold/ booked inventoryUPPER THANE - SERENO A1, C C1.pdf · uploaded 27 Dec 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)88 UPPER THANE - SERENO A1, C C1.pdf · uploaded 30 Jun 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sereno A,C,C1.pdf · uploaded 29 Aug 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)88 UPPER THANE - SERENO A1, C C1.pdf · uploaded 12 Nov 2022Source
  • 2 Details of encumbrancesUPPER THANE - SERENO A1, C C1.pdf · uploaded 2 Mar 2023Source
  • 3 Disclosure of sold/ booked inventorySereno A1, C,C1.pdf · uploaded 31 Mar 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same36 Sereno A1,c C1.pdf · uploaded 27 Apr 2023Source
  • 4 Certificates of CA (Form 3)Sereno A1 C C1 - Form3.pdf · uploaded 22 Jul 2023Source
  • 4 Disclosure of sold/ booked inventorySereno - A1 C C1 - March23.pdf · uploaded 24 Jul 2023Source
  • 5 Disclosure of sold/ booked inventorySereno A1 C C1 - June23.pdf · uploaded 24 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Upper Thane - Sereno A1, C C1.pdf · uploaded 16 Oct 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Upper Thane Sereno A1 C C1 - Form1 - Sep23.pdf · uploaded 21 Nov 2023Source
  • 6 Disclosure of sold/ booked inventoryUpper Thane - Sereno A1, C C1 - P51700020217 - Sep23.pdf · uploaded 13 Dec 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 - UPPER THANE - SERENO A1 C C1(Casa 4 03 (B) E F G - P51700020217 - Dec23.pdf · uploaded 26 Feb 2024Source
  • 7 Disclosure of sold/ booked inventorySold Unsold - UPPER THANE - SERENO A1 C C1(Casa 4 03 (B) E F G) - P51700020217 - Dec23.pdf · uploaded 27 Feb 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - UPPER THANE - SERENO A1, C C1 - P51700020217 - Project Close.pdf · uploaded 21 Mar 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCasa Sereno A1 C C1.pdf · uploaded 21 Mar 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 - UPPER THANE - SERENO A1, C C1 - P51700020217.pdf · uploaded 21 Mar 2024Source
  • 8 Disclosure of sold/ booked inventorySold Unsold - UPPER THANE - SERENO A1 C C1 - P51700020217 - March 24.pdf · uploaded 16 May 2024View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700020217 - Upper Thane - Sereno A1, C C1.pdf · uploaded 19 Oct 2024Source

Technical

  • DocumentCluster 4_03B_IOD_1.pdf · uploaded 23 Mar 2019Source
  • DocumentCluster 4_03B_IOD_2.pdf · uploaded 23 Mar 2019Source
  • DocumentCluster 4_03B_IOD_3.pdf · uploaded 23 Mar 2019Source
  • DocumentCluster 4_03B_IOD_4.pdf · uploaded 23 Mar 2019Source
  • DocumentCluster 4_03B_IOD_5.pdf · uploaded 23 Mar 2019Source
  • Documentlayout plan 1.pdf · uploaded 23 Mar 2019Source
  • Documentlayout plan 2.pdf · uploaded 23 Mar 2019Source
  • DocumentSHEET 9 WOODLAND SERENO.pdf · uploaded 25 Feb 2021Source
  • DocumentSHEET 8 WOODLAND SERENO2.pdf · uploaded 25 Feb 2021Source
  • DocumentSHEET 10 WOODLAND SERENO3.pdf · uploaded 25 Feb 2021Source

Technical (Architect)

  • DocumentForm 1 - UPPER THANE - SERENO A1, C C1 - P51700020217 - Project Close.pdf · uploaded 21 Mar 2024Source

Technical (Engineer)

  • DocumentSereno A,C,C1.pdf · uploaded 29 Aug 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 252pt, 262

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 1BHK458 units in all
Address
351pt, 351A, 262, 2814pt, 252pt, ., .PIN 421302
Village
Surai, Bhiwandi taluka
Land area for this project
4,102 sq m (44,148 sq ft)
Permissible built-up area
36,604 sq m (3,94,003 sq ft)
Sanctioned built-up area
17,431 sq m (1,87,620 sq ft)
Recreational open space
2,514 sq m (27,058 sq ft)
Designated bank account
85
Developed in phases
Yes

Survey, CTS, gat or plot numbers

252pt2622814pt351A351pt

Land as published on MahaRERA's project page

351pt, 351A, 262, 2814pt, 252pt

Boundaries

North
255 By 1p
South
267 By 1p
East
266 By 2
West
265 By 2

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking458 units

376 of 458 units booked (82%), as the promoter reported to MahaRERA

2BHK · 363 units1BHK · 95 units
BuildingTypeCarpet areaUnitsBooked
Wing A12BHK31.32 sq m · 337 sq ft10
Wing A12BHK33.32 sq m · 359 sq ft10
Wing A12BHK33.36 sq m · 359 sq ft20
Wing A12BHK43.39 sq m · 467 sq ft20
Wing A12BHK43.57 sq m · 469 sq ft22
Wing A12BHK43.66 sq m · 470 sq ft1111
Wing A12BHK43.68 sq m · 470 sq ft220
Wing A12BHK44.69 sq m · 481 sq ft120119
Show all 30 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Wing A12BHK44.7 sq m · 481 sq ft110
Wing A12BHK46.62 sq m · 502 sq ft60
Wing C1BHK34.07 sq m · 367 sq ft10
Wing C1BHK34.84 sq m · 375 sq ft11
Wing C1BHK34.93 sq m · 376 sq ft4343
Wing C1BHK35.49 sq m · 382 sq ft40
Wing C1BHK39.27 sq m · 423 sq ft10
Wing C1BHK44.48 sq m · 479 sq ft10
Wing C2BHK47.1 sq m · 507 sq ft1919
Wing C2BHK47.32 sq m · 509 sq ft10
Wing C2BHK50.16 sq m · 540 sq ft10
Wing C2BHK50.63 sq m · 545 sq ft10
Wing C2BHK50.73 sq m · 546 sq ft22
Wing C2BHK53.47 sq m · 576 sq ft20
Wing C2BHK53.79 sq m · 579 sq ft6464
Wing C11BHK34.93 sq m · 376 sq ft2929
Wing C11BHK35.49 sq m · 382 sq ft150
Wing C12BHK47.1 sq m · 507 sq ft2121
Wing C12BHK47.32 sq m · 509 sq ft20
Wing C12BHK50.16 sq m · 540 sq ft30
Wing C12BHK53.47 sq m · 576 sq ft40
Wing C12BHK53.79 sq m · 579 sq ft6565

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.