P51700014814

UPPER THANE - TIARA A to B · Mankoli, Thane · Macrotech Developers Limited

Promised for 30 Oct 2022 — that date has passed and MahaRERA does not mark the project complete.

4 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Oct 2022, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51700014814

Is UPPER THANE - TIARA A to B delayed?

Yes. MahaRERA records a promised completion of 30 Oct 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700014814.

Who is the promoter?

MahaRERA records Macrotech Developers Limited as the promoter of P51700014814.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700014814.

Answers are generated from the record.

Data through23 Nov 2026, 01:41SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology