Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51900005378

Lodha Venezia - 49th To 65th Floor · Ward Fsouth, Mumbai City · Lodha Developers Limited

Promised for 31 Dec 2018 — that date has passed and MahaRERA does not mark the project complete.

7 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2018, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate11 Aug 2017View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51900005378

Is Lodha Venezia - 49th To 65th Floor delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51900005378.

Who is the promoter?

MahaRERA records Lodha Developers Limited as the promoter of P51900005378.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900005378.

Answers are generated from the record.

Data through23 Nov 2026, 01:38SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology